Akurdi station subway in Maha to be completed soon
RAILWAYS & METRO RAIL

Akurdi station subway in Maha to be completed soon

The Pimpri Chinchwad New Township Development Authority (PCNTDA) has resumed construction of the subway near Akurdi railway station and the work is expected to be completed by February 15.

The subway is being constructed using the 'push box' technology. PCNTDA Executive Engineer Vasant Patil said that the work of pushing two concrete boxes under the railway tracks has resumed after receiving permission from the railway administration

Explaining the subway digging process, Patil said that there are two separate boxes for the up and down vehicular traffic. The soil below the tracks will be slowly dug up and the boxes will be inserted. The railway administration has allotted us specific days for this work. Train traffic will be stopped in the afternoon on these days as a precautionary measure, he said. The two boxes have been constructed near the Gurudwara side of the railway tracks near Akurdi railway station.

The bids for the subway project were invited in March 2010 and the work order was given in May that year. The project, costing Rs 8.1 crore, was to be completed in 15 months.

The Pimpri Chinchwad New Township Development Authority (PCNTDA) has resumed construction of the subway near Akurdi railway station and the work is expected to be completed by February 15. The subway is being constructed using the 'push box' technology. PCNTDA Executive Engineer Vasant Patil said that the work of pushing two concrete boxes under the railway tracks has resumed after receiving permission from the railway administration Explaining the subway digging process, Patil said that there are two separate boxes for the up and down vehicular traffic. The soil below the tracks will be slowly dug up and the boxes will be inserted. The railway administration has allotted us specific days for this work. Train traffic will be stopped in the afternoon on these days as a precautionary measure, he said. The two boxes have been constructed near the Gurudwara side of the railway tracks near Akurdi railway station. The bids for the subway project were invited in March 2010 and the work order was given in May that year. The project, costing Rs 8.1 crore, was to be completed in 15 months.

Related Stories

Gold Stories

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram