Irrigation Marvel
The raft downstream has energy-dissipating haunches to give a hydraulic jump to the water before flowing over 100 m of stone pitching,? says Desai.
Formwork

Irrigation Marvel

River Godavari is Peninsular India’s largest and a lifeline for crores of people in Telangana. However, much of the river’s torrential flow goes untapped, hence unutilised to its fullest potential—until now!

In 2008, the Telangana government conceived the Kaleshwaram Lift Irrigation Scheme (KLIS), one of the world’s largest irrigation projects, now operational, that aims to irrigate 18.25 lakh acre in 13 districts and stabilise another 18.75 lakh acre in seven more districts of Telangana. The plan is to harness water at the confluence of three rivers by the barrage at Medigadda which will pump the water back into the Godavari through a maze of reservoirs, tunnels, pipelines and canals. Almost 2,000million cu ft (tmc) of water per day will be moved upriver through gravity canals from the Medigadda barrage to the Annaram barrage, from where further back to the Sundilla barrage, then diverted to the Yellampalli reservoir to be distributed to the neighbouring districts.

In a three-part series, CW showcases the construction perspective and successful execution of the three barrages. In this article, we feature the first, and largest barrageof KLIS, the Medigadda Barrage, constructed by construction major Larsen & Toubro (L&T).

The highlights
According to SV Desai, Senior Vice-President & Head – Heavy Civil Infrastructure IC, L&T Construction, “Apart from the pride of associating with such an iconic project, L&T is equally proud to have completed this colossal project, which was inaugurated on June 21, 2019, by Telangana Chief Minister K Chandrashekar Rao, in a record timeline of just 24 months.”

During its execution, L&T set several records in terms of the amount of materials used such as concrete and steel, in an extremely challenging operating environment.

Some highlights:

  • 16,722 cu m concrete poured in 24 hours
  • 25,584 concrete poured in 72 hours
  • 1.94 lakh cu m concrete poured in a month
  • 9,200 mt of rebar in a single month
  • 10 m height formwork, first-of-its-kind in India, for the piers
  • 25,000 mt of steel gates fabricated in 12 months
  • 85 gates erected in four months.

Structural features
The barrage is 1,625m in length with 84 giant piers, each110mlong, 4m or 6mwide and 25mhigh. Two abutments situated on either bank of the river accommodate an open fish ladder to maintain uninterrupted movement of fish during the lean season. “The raft downstream has energy-dissipating haunches to give a hydraulic jump to the water before flowing over 100 m of stone pitching,” says Desai.“Both banks are protected with retaining walls beyond which are guide/flood bunds (11.71 km on the left bank and 6.32 km on the right bank)to protect the adjoining cultivable lands.”

The barrage bridges the states of Telangana and Maharashtra by a road with 7.5-m-wide carriageway constructed above the structure that reduces the distance by 60 km, saving millions of traffic hours and fuel cost.

Materials: High on quality

  • The 110-m-wide and 3.7-m-thickraft was of M2540MSA grade RCC, concreted in three successive lifts with pour heights of 1.5m, 1.5m and 0.7m respectively.
  • Each pier is 110mlong and 4mwide with RCC of M25 20MSA grade.
  • All batching plants were integrated with ice or chiller plants to control adiabatic temperature rise or heat produced owing to hydration of cement in mass concrete. The concrete was produced at a reduced temperature of 20°C by adding ice flakes and chilled water without affecting the water-cement ratio as per mix design. The temperature and slump of concrete were continuously monitored until placement.

Desai shares the major daily average material consumption during peak time:

  • Cement: 1,700 mt (34,000 bags): 50 bulkers
  • 1.1 lakh mt steel rebar was a huge task, properly streamlined to ensure uninterrupted supplies
  • Aggregates: 5,500 mt: 150 truck loads
  • Reinforcement: 250 mt: 10 trailers.

L&T system formwork: Was used for its low heat conductivity that prevented loss of heat that reduced stripping and cycle time and for its smooth finish and elegant appearance as well.
Sheet pile for seepage arrest in cofferdam: Sheet piles of 10 m depth were driven along the periphery of the cofferdam to reduce the seepage from the flowing river during monsoon and non-monsoon periods. The project consumed 2,500 mt of sheet pile to minimise the seepage.

Technology equipped
Equipment used for construction included wheel-loaders, ice and chilling plants, hydraulic, pick-and-carry and tower cranes, bull-dozers, excavators, dumpers, and automated pull-through welding and automated CNC cutting machines.

Construction of the raft foundation required ground improvement. Desai elaborates, “The geotechnical investigation revealed certain weak areas in the ground strata that required strengthening. While methods like vibro compaction, dynamic compaction or rapid impact compaction are available, they are also time-consuming and costly. After a thorough analysis, we adopted the cement stabilisation dry-and-wet method.”

Record time
When asked what factors helped in the completion of the project in a record 24 months, Desai responds: “Process improvements!” and elaborates:

  • Multiple projects within a project: The project was split into two mini projects—one on the either bank, each with its own setup of men, material and equipment. Reduction of cycle time for pier execution: A conventional 2.4-m height of concrete pouring method would have required 11 times more concrete to execute a single pier. Hence, an optimised formwork height of 5 m was adopted to increase speed of execution. Later, the formwork height was raised to 7.5 m, to eliminate one major lift and further speedup execution. The formwork height raised yet again to 10 m to achieve 4,045 cum of concrete pour.
  • Automated fabrication: All sequential activities of cutting, bending, rolling, welding and painting to fabricate the HM radial gates involving 26,000 mt of structural steel were fully automated.
  • Digital intervention: ‘Concrete management technology’ monitored the entire concreting process in real time, right from production and transportation to placement of concrete. Several machines were IoT-tagged and project progress digitally monitored to improve productivity, reduce execution time and enhance overall operational efficiency. ‘Live’ feeds from RF (radio frequency) and GPS systems from the batching plants, transit mixers and boom placers provided accurate, real-time data to monitor project progress on an hourly basis and tracked on a central dashboard.

  • Overcoming challenges
    MV Ramakrishna Raju, Project Director, L&T, shares the major challenges involved in constructing this barrage and measures taken to overcome them:
    18.5 lakh cu m concreting in a stringenttimelineof18months: This project required 1,850,000 cum of concrete in just 18 months, translating into an asking rate of 5,000 cum per day during peak months. Eight batching plants and 100+transit mixers making approximately 1,000 trips a day fed13 boom placers in different locations spread across 3 sq km to build 13-15 different structures across the site.

  • Meeting a massive requirement of aggregates, 20 lakh mt in 18 months: With an average daily requirement of 5,500 mt of aggregates, of different sizes varying from 10mm to 40mm according to the pour plan and grade of concrete, procurement, transportation and just-in-time delivery were critical considerations to meet targets.
  • To meet the threat of rising water levels of the Godavari during the monsoons: Coffer dams, specially designed by experts, were constructed, reinforced with sheet piles to withstand a staggering discharge of 9 lakh cu m per second.
  • Mobilising a huge workforce: The manpower requirement of 5,500 was across various categories like fitters, carpenters, welders, gas-cutters, drivers, plumbers, operators, fabricators, supervisors, foremen, etc. Mobilising and retaining such large numbers of skilled workmen, required a high level of functionality and strong administration. They were provided excellent accommodation, canteen and drinking water facilities with RO plant, refreshed with chilled buttermilk and oral dehydration salts during the summer when temperatures reached 45*C. The waste management for the entire workforce was routed through waste treatment plants of various capacities.

Consider this: This landmark project achieved 13.9 million safe man-hours. Another reason to label this endeavour a true marvel!

SERAPHINA D’SOUZA

BOX
Project details
Location: Medigadda, Telangana
Client: Irrigation & CAD Department, Government of Telangana. Website: www.telangana.gov.in
Project consultant: CE – Central Designs Organization, I & CAD Department, Government of Telangana.

River Godavari is Peninsular India’s largest and a lifeline for crores of people in Telangana. However, much of the river’s torrential flow goes untapped, hence unutilised to its fullest potential—until now! In 2008, the Telangana government conceived the Kaleshwaram Lift Irrigation Scheme (KLIS), one of the world’s largest irrigation projects, now operational, that aims to irrigate 18.25 lakh acre in 13 districts and stabilise another 18.75 lakh acre in seven more districts of Telangana. The plan is to harness water at the confluence of three rivers by the barrage at Medigadda which will pump the water back into the Godavari through a maze of reservoirs, tunnels, pipelines and canals. Almost 2,000million cu ft (tmc) of water per day will be moved upriver through gravity canals from the Medigadda barrage to the Annaram barrage, from where further back to the Sundilla barrage, then diverted to the Yellampalli reservoir to be distributed to the neighbouring districts. In a three-part series, CW showcases the construction perspective and successful execution of the three barrages. In this article, we feature the first, and largest barrageof KLIS, the Medigadda Barrage, constructed by construction major Larsen & Toubro (L&T). The highlights According to SV Desai, Senior Vice-President & Head – Heavy Civil Infrastructure IC, L&T Construction, “Apart from the pride of associating with such an iconic project, L&T is equally proud to have completed this colossal project, which was inaugurated on June 21, 2019, by Telangana Chief Minister K Chandrashekar Rao, in a record timeline of just 24 months.” During its execution, L&T set several records in terms of the amount of materials used such as concrete and steel, in an extremely challenging operating environment. Some highlights: 16,722 cu m concrete poured in 24 hours 25,584 concrete poured in 72 hours 1.94 lakh cu m concrete poured in a month 9,200 mt of rebar in a single month 10 m height formwork, first-of-its-kind in India, for the piers 25,000 mt of steel gates fabricated in 12 months 85 gates erected in four months. Structural features The barrage is 1,625m in length with 84 giant piers, each110mlong, 4m or 6mwide and 25mhigh. Two abutments situated on either bank of the river accommodate an open fish ladder to maintain uninterrupted movement of fish during the lean season. “The raft downstream has energy-dissipating haunches to give a hydraulic jump to the water before flowing over 100 m of stone pitching,” says Desai.“Both banks are protected with retaining walls beyond which are guide/flood bunds (11.71 km on the left bank and 6.32 km on the right bank)to protect the adjoining cultivable lands.” The barrage bridges the states of Telangana and Maharashtra by a road with 7.5-m-wide carriageway constructed above the structure that reduces the distance by 60 km, saving millions of traffic hours and fuel cost. Materials: High on quality The 110-m-wide and 3.7-m-thickraft was of M2540MSA grade RCC, concreted in three successive lifts with pour heights of 1.5m, 1.5m and 0.7m respectively. Each pier is 110mlong and 4mwide with RCC of M25 20MSA grade. All batching plants were integrated with ice or chiller plants to control adiabatic temperature rise or heat produced owing to hydration of cement in mass concrete. The concrete was produced at a reduced temperature of 20°C by adding ice flakes and chilled water without affecting the water-cement ratio as per mix design. The temperature and slump of concrete were continuously monitored until placement. Desai shares the major daily average material consumption during peak time: Cement: 1,700 mt (34,000 bags): 50 bulkers 1.1 lakh mt steel rebar was a huge task, properly streamlined to ensure uninterrupted supplies Aggregates: 5,500 mt: 150 truck loads Reinforcement: 250 mt: 10 trailers. L&T system formwork: Was used for its low heat conductivity that prevented loss of heat that reduced stripping and cycle time and for its smooth finish and elegant appearance as well. Sheet pile for seepage arrest in cofferdam: Sheet piles of 10 m depth were driven along the periphery of the cofferdam to reduce the seepage from the flowing river during monsoon and non-monsoon periods. The project consumed 2,500 mt of sheet pile to minimise the seepage. Technology equipped Equipment used for construction included wheel-loaders, ice and chilling plants, hydraulic, pick-and-carry and tower cranes, bull-dozers, excavators, dumpers, and automated pull-through welding and automated CNC cutting machines. Construction of the raft foundation required ground improvement. Desai elaborates, “The geotechnical investigation revealed certain weak areas in the ground strata that required strengthening. While methods like vibro compaction, dynamic compaction or rapid impact compaction are available, they are also time-consuming and costly. After a thorough analysis, we adopted the cement stabilisation dry-and-wet method.” Record time When asked what factors helped in the completion of the project in a record 24 months, Desai responds: “Process improvements!” and elaborates: Multiple projects within a project: The project was split into two mini projects—one on the either bank, each with its own setup of men, material and equipment. Reduction of cycle time for pier execution: A conventional 2.4-m height of concrete pouring method would have required 11 times more concrete to execute a single pier. Hence, an optimised formwork height of 5 m was adopted to increase speed of execution. Later, the formwork height was raised to 7.5 m, to eliminate one major lift and further speedup execution. The formwork height raised yet again to 10 m to achieve 4,045 cum of concrete pour. Automated fabrication: All sequential activities of cutting, bending, rolling, welding and painting to fabricate the HM radial gates involving 26,000 mt of structural steel were fully automated. Digital intervention: ‘Concrete management technology’ monitored the entire concreting process in real time, right from production and transportation to placement of concrete. Several machines were IoT-tagged and project progress digitally monitored to improve productivity, reduce execution time and enhance overall operational efficiency. ‘Live’ feeds from RF (radio frequency) and GPS systems from the batching plants, transit mixers and boom placers provided accurate, real-time data to monitor project progress on an hourly basis and tracked on a central dashboard. Overcoming challenges MV Ramakrishna Raju, Project Director, L&T, shares the major challenges involved in constructing this barrage and measures taken to overcome them: 18.5 lakh cu m concreting in a stringenttimelineof18months: This project required 1,850,000 cum of concrete in just 18 months, translating into an asking rate of 5,000 cum per day during peak months. Eight batching plants and 100+transit mixers making approximately 1,000 trips a day fed13 boom placers in different locations spread across 3 sq km to build 13-15 different structures across the site. Meeting a massive requirement of aggregates, 20 lakh mt in 18 months: With an average daily requirement of 5,500 mt of aggregates, of different sizes varying from 10mm to 40mm according to the pour plan and grade of concrete, procurement, transportation and just-in-time delivery were critical considerations to meet targets. To meet the threat of rising water levels of the Godavari during the monsoons: Coffer dams, specially designed by experts, were constructed, reinforced with sheet piles to withstand a staggering discharge of 9 lakh cu m per second. Mobilising a huge workforce: The manpower requirement of 5,500 was across various categories like fitters, carpenters, welders, gas-cutters, drivers, plumbers, operators, fabricators, supervisors, foremen, etc. Mobilising and retaining such large numbers of skilled workmen, required a high level of functionality and strong administration. They were provided excellent accommodation, canteen and drinking water facilities with RO plant, refreshed with chilled buttermilk and oral dehydration salts during the summer when temperatures reached 45*C. The waste management for the entire workforce was routed through waste treatment plants of various capacities. Consider this: This landmark project achieved 13.9 million safe man-hours. Another reason to label this endeavour a true marvel!SERAPHINA D’SOUZA BOX Project details Location: Medigadda, Telangana Client: Irrigation & CAD Department, Government of Telangana. Website: www.telangana.gov.in Project consultant: CE – Central Designs Organization, I & CAD Department, Government of Telangana.

Related Stories

Gold Stories

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram