Pending smart city works get boost during lockdown
01 Jul 2021
The second lockdown was utilised by the government and the Bengaluru Smart City (BSCL) to complete the ongoing smart city road works in Bengaluru. Work on a total of 15.15 km of road has been completed during the second lockdown and work on 4.843 km is pending. The completed roads is expected be be opened for commuters by July.