Recently, the Nagpur Metro-Rail Project in Maharashtra has set a new record for building Asia’s longest double-decker viaduct. The Maha Metro was able to plan and design this multilayer structure with a metro on top and elevated national highway in the middle, supported on common pillars. This special rib-and-spine design has caused minimum inconvenience to road users and been built in the shortest possible time. Integrating well with the metro structure,it has proved to be cost-effective, faster to construct and aesthetic too.
“Another feature associated with this double-decker flyover is the connectivity it provides to the Manish Nagar locality by a connecting flyover on the adjacent railway line,” he continues. For years, residents of Manish Nagar needed to pass a railway level crossingeveryday, but one that mostly remained closed owing to heavy train movement on this North-South cum East-West combined corridor of the Indian Railways. Technical challenges of heavily built-up areas around and inadequate ramp space available in the area delayed construction of a flyover. And the increasing population of Manish Nagar over the years was worsening the problem. The provision of this technically enabled, double-decker flyover resolved the ticklish technical problem as well.
The first challenge was an existing flyover in the alignment of this multilayer structure at Chhatrapati Square. “The demolition work was to be carried out in such a way that it should not affect adjoining and nearby structures and had to be completed in minimal time to have the least effect on existing NH traffic,” says Dr Dixit. Considering this, the demolition was completed in a record-breaking time of just eightdays, including the removal of debris.
Second,the launching of spines and ribs on an extremely busy road (Wardha Road) of Nagpur was a challenge. “Hence, the MahaMetro devised a unique ‘double-decker launching girder’for the simultaneous erection of precast segmental girders of the metro viaduct as well as the multilayerviaduct,” explains Dr Dixit.
Constructing three stations over this double-decker structure also posed enormous challenges, which the corporation had to overcome.
As Dr Dixit explains:
The first was the fact that a common pier was used for both the metro viaduct and NHAI superstructure. The idea of utilising a common pier by optimising the design has greatly saved the cost of construction of the foundation and the time required to provide separate foundations for both the metro and NHAI. Further, it improved the aesthetics and land acquisition was minimised.
Secondwas the use of spine-and-wing technology for the construction of the multilayerviaductdeck. This allowed the smoother and sequential launching of segments of both the metro and multilayerviaduct. The double-decker launching girder was provided for simultaneous launching of segments of the metro as well as spine segments of NHAI. Special attention was paid to the additional construction loads raised owing to the self-weight of the double-decker launching girder.
These rib launchers were installed and fixed on already erected spines, then using these launchers. Ribs were erected and transverse, andprestressing of spine and ribs was done to unite the structure.Both technologies resulted in hassle-free work without causing any disturbance to local commuters.
In the first part,the spine/central part segment span launching was done. These are precast segments erected using launching girders. For the spine segment, launching of the precast segments of the spine spans are carried out using a ‘wing launcher’. Major activities involve segment erection;segment alignment and gluing;span stressing;load transfer of NHAI span to pier cap; Macalloy bars decoupling;and auto launching of the launching girder. Similar stages are followed for metro spans simultaneously using the same launching girder.
In the second part,ribs and end portion segments’ span on both sides of the central span were erected. These are all precast, which are erected using gantries. Activities involved erection of the wings gantry; precast wings lifting; wings alignment and levelling; shutter fixing for stitch concreting;reinforcement tying of stitch concreting; stitch concreting; transverse prestressing; load releasing from launcher; transverse ducts grouting; and auto-launching of the gantry to the next span.
Pre-casting of the segments saved the cost of additional space required for castingsegments at site. Further,the launching girder system made it possible to execute the work of lifting, gluing, stressing and aligning even during high traffic volume. The traffic diversion works were carried out easily during night-time.
One of the special features of the viaduct is the use of spherical bearings for the NHAI deck. “These have been used to balance the deck movement laterally and longitudinally and designed to take considerable rotation as well as displacement, and with their functioning life of 25 to 30 years provide better lifespan to the structure,” says Dr Dixit.To cater to the heavy loads coming onto the substructure from the NHAI multilayer viaduct, 420 spherical bearings have been used in all 105 spans of the viaduct.
The NHAI deck has both a longitudinal and lateral post-tensioned, prestressing cable arrangement, which further enhances the economics of the design and avoids bulkiness of the structure.
“Concrete quantity of around 34,000 cum, high-yield strength steel of grade Fe 500D around 6,000 mt, HT- strands of 1,050 mt were used in the project,” he adds. “To cater for heavy prestressing forces, concrete grades of upto M70 were used in this project.”
The concrete surfaces exposed to the atmosphere of the NHAI double-decker flyover have been coated with anti-corrosive epoxy paint with primer and epoxy coats of approved quality and colour. Epoxy coating increases the life of concrete surfaces exposed to dust, fumes and other pollutants. It has a UV protection film and prevents the interaction of harmful UV rays with the concrete surface. It helps maintain a uniform colour and texture of the concrete surface.The dust and soot accumulated on painted surfaces are easier to clean and maintenance cost is low.
The central corridor of alignment of around 9-m width was barricaded with steel barricades that were lit at night with LED rope and blinker lights to avoid any mishaps at site. Workers were provided with safety kits during construction. Traffic marshals as well as blinker lights were deployed along with the trailers carrying spine and ribs to avoid any accidents during movement from the casting yard.
Erection of the ribs was done only at night after complete barricading of the lifting area.Safety managers were deployed by consultants and contractor and approved safety protocols were followed throughout the project.Toolbox talks were conducted for educating workers regarding safety of work and mock drills were conducted. Each and every work was planned and coordinated with local administrations like NMC andthe traffic police.
The under-construction elevated structure also includes a four-layer structure in Gaddigodam. In February this year, the Maha Metro scripted history with the successful launch of a 85-m-long and 1,600-tonne heavy girder in Gaddigodam over the railway track. This was the first time that such a gigantic task has been executed. The highest ever girder launching is part of the four-layer transportation system at Kamptee Road (Gurudwara) – part of the North-South Corridor of the Maha Metro. The Nagpur-Delhi Railway track over which the work was executed is one of the busiest railway lines with over 150 trains passing over it every day.
Congested roads and heavy traffic in cities like Nagpur, Delhi, Pune, Bengaluru and Mumbai add to construction woes. Space constraint is a challenge in these cities. The fact that these projects are to be completed well in time and be cost-effective adds to the challenges. The primary imperative for project managers is to ensure that the common man faces minimum hardship. Shifting of utility services like the water supply pipeline, electricity and telephone cables and sewer lines is an immense challenge. The Maha Metro has successfully overcome all these challenges to execute Phase 1 of the Nagpur Metro Project.