Bridge across Godavari undergoes maintenance first time in 43 years

01 Jun 2020

With passenger train services regulated during the extended lockdown, the South Central Railway (SCR) completed comprehensive track maintenance work on the iconic second rail-cum-road bridge across the Godavari River near Rajahmundry in Andhra Pradesh. Track maintenance work on the 3-km bridge was undertaken for the first time in 43 years after it was commissioned in 1977. 
The work was executed in a mega block of 36 hours. The work had been pending for want of such a long block to train services 
given that the bridge is critical to the South-East Rail link of India, bridging the two sides of the Godavari on the Vijayawada-Visakhapatnam Railway Section of the Zone. 