Bagged it!
ROADS & HIGHWAYS

Bagged it!

Contract value: Rs.1,070 crore
Particulars: Railway construction work
The Railway Business Unit, a part of the Transportation Infrastructure business of L&T Construction, has won a railway order from BACS consortium (Bechtel-Almabani-CCC-Siemens) for construction of Ballastless tracks for Riyadh Metro Lines-I and II on a design and build basis.

Contract value:Rs.1,094 crore
Particulars: EPC contract
Punj Lloyd Engineering & Construction Co bagged a lump-sum turnkey contract for the EPCC package-2 at Haldia refinery at West Bengal from Indian Oil Corporation (IOC).

Contract value:Rs.986 crore
Particulars: Road upgradation
Gayatri Projects bagged a contract from NHAI for four-laning of Sultanpur to Varanasi section of NH-56 from 134.70 km to 205 km.

Contract value:Rs.205 crore
Particulars: DBFOMT work
Ashoka Buildcon Ltd bagged a contract from Karnataka Road Development Corporation Ltd for the design, build, finance, operate, maintain and transfer (DBFOMT) of existing state highway Hungund-Muddebihal-Talikot in Karnataka on DBFOMT annuity basis.

Contract value:Rs.2,650 crore
Particulars: Road upgradation
IRB Infrastructure Developers executed a Concession Agreement with NHAI for the six-laning of Agra-Etawah Bypass section of NH-2 (from 199.660 km to 323.525 km) in the state of Uttar Pradesh under NHDP Phase-V on BOT (toll) mode. The construction is estimated to be completed in 910 days.

Contract value:Rs.3,436 crore
Particulars: EPC contract
Toshiba JSW Power Systems Pvt Ltd bagged an EPC contract from Uttar Pradesh Rajya Vidyut Utpadan Nigam Ltd for setting up a 660 MW thermal power plant in Aligarh district. The completion is targeted in 48 months.

Contract value:Rs.170 crore
Particulars: Civil construction
JMC Projects (India) Ltd bagged an order for two building projects at Bengaluru, Karnataka.

Contract value:Rs.1783.42 crore
Particulars: Highway construction
Hindustan Construction Co (HCC) has been awarded a contract from NHAI to construct a 36 km highway, which includes three km of tunnels between Ramban and Banihal in Jammu and Kashmir. The project is a part of NHDP Phase-II program of NHAI on NH1A (now NH44).

Contract value:Rs.397 crore
Particulars: EPC contract
Gammon India Ltd bagged an EPC contract from Goa Public Works Department for the construction, operation and maintenance of balance work for four-laning of NH-17B from Varunapuri to Sada junction from 13.100 km to 18.300 km and elevated road cum ROB from Ravindra Bhavan to Gate No. 09 of MPT.

Contract value:Rs.785 crore
Particulars: Road upgradation
Gayatri Projects bagged a contract from NHAI for four-laning of Ghaghra Bridge to Varanasi section of NH-233 from 240.340 km to 299.350 km in the state of Uttar Pradesh under NHDP Phase-IV on EPC mode.

Contract value:Rs.190.88 crore
Particulars: Rural electrification work
IL&FS Engineering and Construction Co has received a letter of award (LOA) from Madhyanchal Vidyut Vitran Nigam Ltd (MVVNL) for rural electrification works in Shahjahanpur district of Uttar Pradesh on a turnkey basis under the Deen Dayal Upadhyay Gram Jyoti Yojana (DDUGJY) Phase-II.

Contract value:Rs.806 crore
Particulars: Road upgradation
Gayatri Projects bagged a contract from NHAI for four-laning of Sultanpur to Varanasi section of NH-56 from 205 km to 263 km in the state of Uttar Pradesh under NHDP Phase-IV on EPC mode.

Contract value:Rs.119 crore
Particulars: Power plant electrification
ABB India Ltd has received an order for power plant electrification, automation and substations solutions for solar power plants being built as part of India´s strong push for solar energy and renewables. It will be among the biggest solar projects worldwide.

Contract value:Rs.41.30 crore
Particulars: Civil construction
Nila Infrastructure has bagged an order from Ahmedabad Municipal Corporation (AMC) for the construction of 816 EWS residential flats and 24 shops including internal infrastructure and development work within its plot in Ahmedabad.

Contract value:Rs.235 crore
Particulars: DBFOMT work
Ashoka Buildcon Ltd bagged contract from Karnataka Road Development Corporation Ltd for the design, build, finance, operate, maintain and transfer (DBFOMT) of existing state highway (NH-4) Bagewadi-Bailhongal-Saundatti in Karnataka on DBFOMT annuity basis.

Contract value:Rs.199 crore
Particulars: Water supply work
JMC Projects (India) Ltd bagged an order for Bhagalpur Water Supply projects, Bihar.

Contract value:Rs.81 crore
Particulars: Railways
Siemens Ltd bagged an order from Diesel Locomotive Works (DLW), Varanasi. The scope of work for the project includes supply and supervision for installation and commissioning of AC-AC traction systems including locomotive controller for diesel electric locomotives.

Contract value:Rs.295 crore
Particulars: Tunnelling work
Afcons Infrastructure Ltd bagged an order from IRCON International Ltd for tunnelling work in Jammu. The work is expected to be completed in 24 months.

Contract value:Rs.181 crore
Particulars: Highway upgradation
JMC Projects (India) Ltd bagged an order for improvement of Karnataka state highways.

Contract value:Rs.73.9 crore
Particulars: Thermal power station work
Tata Enterprise company TRF Ltd has bagged an order from Telangana State Power Generation Corporation Ltd for four sets of stacker-cum-reclaimer package for its Kothagudem Thermal Power Station Unit 12 (1 X 800 MW) and Bhadradri Thermal Power Station (4 X 270 MW).

Contract value: Rs.1,070 crore Particulars: Railway construction work The Railway Business Unit, a part of the Transportation Infrastructure business of L&T Construction, has won a railway order from BACS consortium (Bechtel-Almabani-CCC-Siemens) for construction of Ballastless tracks for Riyadh Metro Lines-I and II on a design and build basis. Contract value:Rs.1,094 crore Particulars: EPC contract Punj Lloyd Engineering & Construction Co bagged a lump-sum turnkey contract for the EPCC package-2 at Haldia refinery at West Bengal from Indian Oil Corporation (IOC). Contract value:Rs.986 crore Particulars: Road upgradation Gayatri Projects bagged a contract from NHAI for four-laning of Sultanpur to Varanasi section of NH-56 from 134.70 km to 205 km. Contract value:Rs.205 crore Particulars: DBFOMT work Ashoka Buildcon Ltd bagged a contract from Karnataka Road Development Corporation Ltd for the design, build, finance, operate, maintain and transfer (DBFOMT) of existing state highway Hungund-Muddebihal-Talikot in Karnataka on DBFOMT annuity basis. Contract value:Rs.2,650 crore Particulars: Road upgradation IRB Infrastructure Developers executed a Concession Agreement with NHAI for the six-laning of Agra-Etawah Bypass section of NH-2 (from 199.660 km to 323.525 km) in the state of Uttar Pradesh under NHDP Phase-V on BOT (toll) mode. The construction is estimated to be completed in 910 days. Contract value:Rs.3,436 crore Particulars: EPC contract Toshiba JSW Power Systems Pvt Ltd bagged an EPC contract from Uttar Pradesh Rajya Vidyut Utpadan Nigam Ltd for setting up a 660 MW thermal power plant in Aligarh district. The completion is targeted in 48 months. Contract value:Rs.170 crore Particulars: Civil construction JMC Projects (India) Ltd bagged an order for two building projects at Bengaluru, Karnataka. Contract value:Rs.1783.42 crore Particulars: Highway construction Hindustan Construction Co (HCC) has been awarded a contract from NHAI to construct a 36 km highway, which includes three km of tunnels between Ramban and Banihal in Jammu and Kashmir. The project is a part of NHDP Phase-II program of NHAI on NH1A (now NH44). Contract value:Rs.397 crore Particulars: EPC contract Gammon India Ltd bagged an EPC contract from Goa Public Works Department for the construction, operation and maintenance of balance work for four-laning of NH-17B from Varunapuri to Sada junction from 13.100 km to 18.300 km and elevated road cum ROB from Ravindra Bhavan to Gate No. 09 of MPT. Contract value:Rs.785 crore Particulars: Road upgradation Gayatri Projects bagged a contract from NHAI for four-laning of Ghaghra Bridge to Varanasi section of NH-233 from 240.340 km to 299.350 km in the state of Uttar Pradesh under NHDP Phase-IV on EPC mode. Contract value:Rs.190.88 crore Particulars: Rural electrification work IL&FS Engineering and Construction Co has received a letter of award (LOA) from Madhyanchal Vidyut Vitran Nigam Ltd (MVVNL) for rural electrification works in Shahjahanpur district of Uttar Pradesh on a turnkey basis under the Deen Dayal Upadhyay Gram Jyoti Yojana (DDUGJY) Phase-II. Contract value:Rs.806 crore Particulars: Road upgradation Gayatri Projects bagged a contract from NHAI for four-laning of Sultanpur to Varanasi section of NH-56 from 205 km to 263 km in the state of Uttar Pradesh under NHDP Phase-IV on EPC mode. Contract value:Rs.119 crore Particulars: Power plant electrification ABB India Ltd has received an order for power plant electrification, automation and substations solutions for solar power plants being built as part of India´s strong push for solar energy and renewables. It will be among the biggest solar projects worldwide. Contract value:Rs.41.30 crore Particulars: Civil construction Nila Infrastructure has bagged an order from Ahmedabad Municipal Corporation (AMC) for the construction of 816 EWS residential flats and 24 shops including internal infrastructure and development work within its plot in Ahmedabad. Contract value:Rs.235 crore Particulars: DBFOMT work Ashoka Buildcon Ltd bagged contract from Karnataka Road Development Corporation Ltd for the design, build, finance, operate, maintain and transfer (DBFOMT) of existing state highway (NH-4) Bagewadi-Bailhongal-Saundatti in Karnataka on DBFOMT annuity basis. Contract value:Rs.199 crore Particulars: Water supply work JMC Projects (India) Ltd bagged an order for Bhagalpur Water Supply projects, Bihar. Contract value:Rs.81 crore Particulars: Railways Siemens Ltd bagged an order from Diesel Locomotive Works (DLW), Varanasi. The scope of work for the project includes supply and supervision for installation and commissioning of AC-AC traction systems including locomotive controller for diesel electric locomotives. Contract value:Rs.295 crore Particulars: Tunnelling work Afcons Infrastructure Ltd bagged an order from IRCON International Ltd for tunnelling work in Jammu. The work is expected to be completed in 24 months. Contract value:Rs.181 crore Particulars: Highway upgradation JMC Projects (India) Ltd bagged an order for improvement of Karnataka state highways. Contract value:Rs.73.9 crore Particulars: Thermal power station work Tata Enterprise company TRF Ltd has bagged an order from Telangana State Power Generation Corporation Ltd for four sets of stacker-cum-reclaimer package for its Kothagudem Thermal Power Station Unit 12 (1 X 800 MW) and Bhadradri Thermal Power Station (4 X 270 MW).

Related Stories

Gold Stories

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram