301 Piles Completed in Kochi Metro Phase 2 Construction Work
RAILWAYS & METRO RAIL

301 Piles Completed in Kochi Metro Phase 2 Construction Work

The construction of the second phase of the Kochi Metro, extending from Palarivattom to Infopark, is progressing at a steady pace. As of now, work on 301 piles has been completed, indicating significant advancement in the project timeline. In Kalamassery, key superstructure components such as pier caps are under construction, with four pier caps and four U-girders already cast.

This phase of the project involves two categories of construction. The second category includes the fabrication of various structural elements like I-girders, pier caps, parapets, T-girders, and L-girders. To support quality and efficiency, dedicated infrastructure such as a quality control lab and a concrete batching lab have been established. Additionally, a concrete waste recycling plant has been set up at the construction yard to minimise environmental impact by repurposing concrete debris.

Launched in July 2024, the second phase aims to enhance metro connectivity towards Infopark, a major IT hub. For viaduct construction, the plan includes the development of 500 U-girders, 580 I-girders, and 354 pier caps. Parallelly, station construction work involves the production of 100 U-girders, 120 pier arms, 400 T-girders, and 200 L-girders.

The structured approach and the establishment of dedicated support facilities are expected to contribute significantly to the timely completion of the project, while also aligning with sustainable construction practices.

News source: The New Indian Express

The construction of the second phase of the Kochi Metro, extending from Palarivattom to Infopark, is progressing at a steady pace. As of now, work on 301 piles has been completed, indicating significant advancement in the project timeline. In Kalamassery, key superstructure components such as pier caps are under construction, with four pier caps and four U-girders already cast. This phase of the project involves two categories of construction. The second category includes the fabrication of various structural elements like I-girders, pier caps, parapets, T-girders, and L-girders. To support quality and efficiency, dedicated infrastructure such as a quality control lab and a concrete batching lab have been established. Additionally, a concrete waste recycling plant has been set up at the construction yard to minimise environmental impact by repurposing concrete debris. Launched in July 2024, the second phase aims to enhance metro connectivity towards Infopark, a major IT hub. For viaduct construction, the plan includes the development of 500 U-girders, 580 I-girders, and 354 pier caps. Parallelly, station construction work involves the production of 100 U-girders, 120 pier arms, 400 T-girders, and 200 L-girders. The structured approach and the establishment of dedicated support facilities are expected to contribute significantly to the timely completion of the project, while also aligning with sustainable construction practices. News source: The New Indian Express

Next Story
Infrastructure Urban

Canal Water Boost for Mudki

In a significant push for public health and urban development, MLA Rajneesh Dahiya has announced a Rs.280 million canal water supply project for Mudki town in the Ferozepur Rural constituency. The initiative aims to provide clean drinking water to every household within Mudki’s municipal limits. Speaking about the development, Dahiya said the project falls under the Centre’s AMRUT (Atal Mission for Rejuvenation and Urban Transformation) scheme and is being carried out with the support of Punjab Chief Minister Bhagwant Singh Mann and Local Government Minister Dr. Inderbir Nijjar. “This ..

Next Story
Infrastructure Transport

6 Tunnel Boring Machines Idle in Chennai

Six tunnel boring machines (TBMs) deployed by the Chennai Metro Rail Limited (CMRL) are currently lying idle beneath city roads, stuck in limbo due to delayed construction of underground stations at Moolakadai, Perambur, and Mandaveli. The TBMs, launched as part of Corridor 3 of the Phase II Metro project from Madhavaram to SIPCOT, have reached their designated stations but are unable to proceed as the station boxes are incomplete. Without a completed diaphragm wall or station box, the machines cannot break through or be dismantled for reuse. According to CMRL officials, the root of the dela..

Next Story
Infrastructure Transport

Mumbai Metro 3 Nears Launch

The Mumbai Metro Rail Corporation shared a sneak peek of the newly completed Acharya Atre Chowk station on Metro Line 3 (Aqua Line) this Sunday, drawing both praise and impatience from the public. Located on the 9.77 km stretch between Bandra Kurla Complex (BKC) and Worli, the underground station is part of a long-anticipated corridor that promises to ease traffic and boost east-west connectivity. The social media update, posted by the handle @MumbaiMetro3, featured images of the station’s sleek new interiors. But the post quickly sparked a flurry of comments, with several users demanding c..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?