JSW Cement Commissions 1 MTPA Grinding Unit at Nagaur

JSW Cement has commissioned an additional 1 MTPA grinding unit at Nagaur in Rajasthan. MTPA refers to million tonnes per annum. The commissioning has increased the company’s total cement grinding capacity to 25.10 MTPA, while its total clinker manufacturing capacity, including capacity at its joint venture JSW Cement FZC, stands at 9.74 MTPA.

The company began operations in North India in March 2026 with the Nagaur Integrated Plant, which comprised a 3.30 MTPA clinkerisation unit and a 2.50 MTPA cement grinding unit. Following the latest commissioning, the plant’s total cement grinding capacity has risen to 3.50 MTPA.

The expanded facility is expected to strengthen JSW Cement’s ability to serve cement demand across Rajasthan, Haryana, Punjab and the National Capital Region. The project has been funded through a combination of equity and long-term debt, according to the company.

During the quarter ended 30 September 2026, JSW Cement also commissioned an Alternate Fuel Handling System and a Waste Heat Recovery System (WHRS) at the Nagaur Integrated Plant. The company said the additions formed part of its broader effort to improve operational efficiency at the facility.

Nilesh Narwekar, chief executive officer of JSW Cement, said the additional grinding capacity was a strategic priority that would support the company’s expansion in North India. He added that the unit had been commissioned within the expected timeline, reflecting the company’s project execution capabilities, and that the alternate fuel and waste heat recovery systems were expected to substantially reduce production costs going forward.

Related Stories

JSW Cement Commissions 1 MTPA Unit in Rajasthan
JSW Cement Boards Approve Proposed Shiva Cement Merger
JSW Cement commissions additional 1 MTPA grinding unit in Rajasthan
Adani begins construction of Dharavi rehabilitation homes
Seven Propel 470 HEV electric tippers go to work on coal haulage in Chhattisgarh