Adani Green Says Tarali Project Involves No Forest Land

Adani Green Energy said its proposed Tarali Pumped Storage Project in Maharashtra involves no forest land or protected area, and that construction began only after statutory approvals. The facility, located in Patan taluka of Satara district, will have a capacity of 1,500 MW and combine a new upper reservoir with the existing Tarali reservoir as the lower reservoir.

The company said it received a No Objection Certificate confirming the absence of forest land on January 23, 2024, followed by environmental clearance on February 11, 2025. The Consent to Establish, which was required before construction could begin, was issued on April 7, 2025. Adani Green Energy said these approvals formed the basis for commencing work.

The clarification followed a reported order by the Maharashtra Forest Department to halt construction on November 13, citing pending approval from the National Board for Wildlife (NBWL). Adani Green Energy said the wildlife clearance process had been initiated as part of compliance requirements linked to the environmental clearance. It submitted a proposal for survey and investigation activities in January 2025, which was subsequently recommended by the State Board for Wildlife.

The company then submitted the proposal to the NBWL for clearance, with the matter remaining under consideration by wildlife authorities. Adani Green Energy said the project did not fall within any notified Protected Area and that its development was proceeding in compliance with applicable statutory requirements and directions from competent authorities.

Pumped storage projects use electricity to move water to an upper reservoir and release it through turbines when power is required. The Tarali project is therefore designed to provide storage capacity while generating electricity through the movement of water between the two reservoirs. The company’s clarification addressed the status of forest, environmental and wildlife-related approvals following the reported halt order.

Related Stories

Maharashtra Forest Department May Lift Stay on Adani Satara Project
Adani Green Expands BESS Capacity to 6.63 GWh
Adani Green Energy Crosses 20 GW Renewable Milestone And Expands BESS
Address Maker sells over 200 Apollo Address plots in six weeks
India's Construction Equipment Sales Surge 38% in October 2026