Battery PLI Scheme Develops 1.4 GWh Capacity Against 50 GWh Target

India’s Production Linked Incentive (PLI) scheme for Advanced Chemistry Cell (ACC) batteries has developed only 1.4 gigawatt-hours (GWh) of manufacturing capacity against its 50 GWh target, with commercial production yet to begin, according to a report by NITI Aayog and IIM Ahmedabad. The assessment said the Rs. 181 bn scheme had progressed slowly because of technological limitations, import dependence and delays in establishing manufacturing facilities.

The scheme is intended to create domestic manufacturing capacity for advanced batteries used in electric vehicles and energy storage systems. It also seeks to reduce India’s dependence on imported battery technologies. Cumulative investment under the scheme reached Rs. 45.7 bn by March 2026, while employment generation stood at 1,245.

No incentive disbursements have been reported because commercial production has not commenced. NITI Aayog said India’s limited capabilities in advanced battery manufacturing had sustained dependence on foreign technology and expertise, while the absence of a developed domestic supply chain had made it difficult for manufacturers to meet localisation requirements.

Critical components, including cathodes, anodes and minerals such as lithium and cobalt, remain key supply-chain constraints. Beneficiary companies are required to achieve at least 25 per cent domestic value addition by the end of the second year and 60 per cent by the fifth year, requirements the report considered difficult under current manufacturing conditions.

The assessment attributed weak execution to limited capacity addition, the lack of incentive payments and slower growth in electric vehicle demand, which had reduced the pace of investment. It also said one beneficiary company had been disqualified for suppressing material facts. Despite the delays, the report maintained a positive long-term outlook, noting that advanced battery investments require substantial time before resulting in production and measurable impact.