GERC Defers Rs2.34 per kWh Tariff For 1,250 MW Solar Procurement
The procurement covered 625 MW of base capacity and 625 MW under a greenshoe option following a Phase XXVIII competitive bidding process. The tender attracted 24 bids totalling 4,176.7 MW and an e-reverse auction in March 2026 produced the discovered tariff for three successful developers. NLC India Renewables Limited was allocated 900 MW (300 MW base and 600 MW under the greenshoe) with a capacity utilisation factor of 26 per cent; Welspun Renewable Energy Private Limited was allocated 300 MW with a capacity utilisation factor of 28.9 per cent and declined the greenshoe; Meghmani Renew Energy Private Limited was allotted 50 MW with a capacity utilisation factor of 24.5 per cent.
GUVNL argued the discovered tariff is lower than rates found in earlier procurement rounds and said the procurement would help Gujarat meet renewable purchase obligations through FY 2029–30 while contributing to India’s goal of 50 per cent non-fossil installed capacity by 2030. The utility asked the commission to weigh the longer term benefits of lower tariffs for consumers and the role of the procurement in state planning.
GERC issued a 13-point query seeking detailed information on curtailment, grid management, energy storage requirements, resource adequacy and the actual cost of solar after accounting for storage, balancing and backing down. The commission requested daily renewable curtailment data from one September 2025 to 31 August 2026 and asked for a time bound plan to address curtailment and measures to ensure grid stability. It also directed GUVNL to demonstrate consistency with updated resource adequacy plans and to quantify overall integration costs.
GUVNL sought three weeks to submit technical studies, curtailment data and supporting documents and the commission allowed the extension, setting a deadline of 23 September 2026 for additional filings. The matter will return to a subsequent hearing after the submission for the commission to decide whether to adopt the tariff and any conditions required to safeguard grid operations.