Nepal Approved to Import 350 MW of Power from India
The Central Electricity Authority (CEA), under India’s Ministry of Power, has authorised the Nepal Electricity Authority (NEA) to procure electricity at competitive rates through the Indian Energy Exchange (IEX). The approval allows imports for up to 17 hours a day and is valid from November 17, 2026, to July 31, 2027.
Of the approved capacity, Nepal can import 300 MW through the Kataiya-Kushaha, Ramnagar-Surajpura and Raxaul-Parwanipur transmission lines. The remaining 50 MW can be sourced through the New Nautanwa-Mainahiya transmission line, according to details released by the NEA.
Nepal relies heavily on run-of-the-river hydropower projects, making electricity generation seasonal. Higher river flows during summer enable the country to produce surplus power for export, mainly to India, while lower water levels during winter reduce domestic generation and increase the need for imports.
The power supply situation has also been affected by damage to hydropower projects in central Nepal during the Rasuwa-Bhotekoshi floods in August. Projects with a combined installed capacity of 431 MW remain disconnected from the national grid following the disaster.
Domestic generation is expected to improve from mid-April as river levels rise gradually. This could reduce Nepal’s reliance on imported electricity and enable the country to resume exports, subject to recovery in generation capacity and grid connectivity.