Shortage of Critical Equipment Hits Madhya Pradesh Power Transmission Expansion

Madhya Pradesh’s power transmission expansion programme is facing shortages of critical equipment, including high-voltage insulators and power transformers, as renewable energy development accelerates. The constraints have raised concerns about the timely execution of infrastructure projects needed to move electricity from generation plants to distribution substations.

Madhya Pradesh has a population of around 90 mn and installed power generation capacity of 12,090 MW, including solar power. Madhya Pradesh Power Transmission Company, known as MP Transco, transmits electricity from generating stations to distribution companies that supply households, industries and commercial establishments.

MP Transco officials said domestic manufacturing had not declined, but rapid infrastructure development across India had widened the gap between demand and supply. Availability of raw materials for porcelain insulators has become difficult, while gas shortages associated with disruptions in the global energy supply chain have affected production at some manufacturing units.

Thousands of insulator strings across different voltage capacities are required each year, while some specialised products continue to be imported. Manufacturers are increasingly adopting polymer and composite insulators because they are lighter, easier to handle and require less maintenance, particularly in polluted and dusty environments. Delivery schedules for certain insulator categories have increased from 12 to 15 months to around 18 to 20 months.

Transformer manufacturers are also facing higher demand for extra-high-voltage transformers, auto-transformers and interconnecting transformers used in 400 kV, 220 kV and 132 kV substations. These products require cold-rolled grain-oriented electrical steel, copper conductors, insulation materials, high-voltage bushings and on-load tap changers. Limited availability of some components has extended delivery periods for large extra-high-voltage transformers from 8 to 12 months to as much as 18 to 24 months.

More than 88 GW of renewable energy capacity has been auctioned in India over the past two years, increasing the need for new transmission corridors, pooling substations and grid interconnections. Madhya Pradesh is developing several solar and other renewable energy projects, requiring additional extra-high-voltage lines and substations. Industry representatives have called for stronger domestic manufacturing, assured supplies of raw materials and expanded production capacity to reduce import dependence and protect grid reliability.