A Balancing Act
Cost control system
Cost control begins long before the actual construction work starts. Even before we bid on a project, we create a tentative budget based on preliminary estimates. This initial budget forms the foundation of our bidding process and serves as the benchmark against which future costs are measured. Once a project is awarded through the tender process, we engage in detailed preparation, including the development of comprehensive designs, drawings, and the identification of necessary materials, manpower, and machinery. Each of these elements contributes to the creation of a final, detailed project budget.One of the key principles we adhere to is ensuring that the final budget, after all adjustments and refinements, does not deviate more than 5 per cent from the initial budget used during tendering.
This is a critical metric for our operations, as even minor deviations can have a significant impact on the overall profitability of the project. Therefore, the accuracy of the initial budget is paramount.
Monthly budgets and reconciliation
When the final budget is established, the next step in our cost control process involves breaking the overall budget down into smaller, more manageable monthly budgets. These monthly budgets are aligned with the work created by the technical team and are tailored to the specific phases of construction. Once the monthly budgets are approved by management, all expenses for that period must adhere strictly to the allocated budget. This segmented approach ensures greater control and accountability over the project’s finances.Every month, we hold review meetings at the management level to reconcile the actual expenses with the budgeted amounts. These meetings provide an opportunity to identify any deviations, address cost overruns, and assess the reasons for any discrepancies. This process ensures that there are no surprises at the end of the project, as any potential issues are addressed on a monthly basis. Additionally, by maintaining tight control over monthly expenditures, one can adjust future budgets if necessary, helping to prevent any significant cost overruns.
Dealing with unforeseen costs
Construction projects are inherently unpredictable, and despite our best efforts to plan meticulously, there are always factors beyond our control that can impact the budget. To account for this, we maintain a contingency fund to handle unforeseen expenses or budget overruns. While we make every effort to avoid such overruns, the nature of the construction industry makes it prudent to plan for worst-case scenarios. The contingency fund should be carefully monitored, and any expenses drawn from this reserve must be justified as being beyond the control of the project team.Common causes of cost overruns
Cost overruns can occur for a variety of reasons. We categorise these causes into four main areas: internal factors, rising material costs, external delays, and natural events. Understanding and addressing these causes is essential to maintaining cost control.
Embracing technology for better cost control
With technology continually evolving, we believe that the construction industry will increasingly rely on advanced tools and techniques to achieve better cost control. Innovations such as Building Information Modelling (BIM), drone surveys and predictive analytics are already helping companies like ours to make more accurate cost estimates, optimise resource allocation and reduce waste. We are committed to integrating these technologies into our operations to improve the efficiency and accuracy of our cost control systems.Importance of teamwork
Ultimately, effective cost control can only be achieved through the coordinated efforts of everyone involved in the project. From senior management to ground-level staff, each member of the team must work together to ensure that costs are kept in check and that any issues are addressed promptly. Cultivating a culture of collaboration and open communication has been instrumental in our ability to manage costs effectively. By fostering teamwork and aligning our efforts, we ensure that cost control is not just a management responsibility but a shared commitment across the organisation.