NHIDCL And Contractor Set September 12 Deadline For NH-29 Works

The District Administration, National Highways Infrastructure Development Corporation (NHIDCL) and officials of the engineering, procurement and construction (EPC) contractor have agreed to accelerate construction along National Highway 29 (NH-29) between Kohima and Jessami. A review meeting at the Deputy Commissioner’s Office in Kohima on August 25 assessed progress on the stretch linking Kohima with Phek and identified issues hampering the works. The session aimed to align timelines and responsibilities among stakeholders.

The meeting examined critical components including sinking zones, road maintenance and protection works, as well as granular sub-base (GSB), wet mix macadam (WMM), drainage, culverts and road shoulders. Officials reviewed current conditions of slopes and areas affected by subsidence and assessed requirements for remedial protection. Detailed sequencing for major layers and ancillary drainage works was considered to reduce delays and enhance durability.

Contractors committed to commence major granular sub-base, wet mix macadam and dense bituminous macadam (DBM) works from September 12 and to complete the identified works within the Kohima section by the first week of October 2026. NHIDCL officials indicated that mobilisation of plant and equipment would be accelerated and that progress would be measured against the contractor’s schedule. The administration requested a clear deployment plan for machinery, manpower and materials to avoid further slippage.

Deputy Commissioner Kohima B Henok Buchem, NCS, urged sensitivity to local considerations and public sentiment while executing the road project, noting its importance for regional connectivity. He instructed the contractor to ensure timely deployment and to coordinate with NHIDCL on necessary adjustments. The district administration assured continued support to resolve matters within its jurisdiction and said it would closely monitor progress against the timelines committed by the contractor.

Related Stories

RITES Signs MoU with NHIDCL for North-East Infrastructure Projects
Arunachal’s Roing-Hunli Alignment Review Targets December 2026 Works
RITES, NHIDCL Partner on North-East Highway Projects
Madhya Pradesh Plans Airport Every 150 Km, Airstrip Every 75 Km
West Bengal Plans Four Airports for 2028 Completion Under UDAN