Only 450m of 1,140m Janakpuri Sewer Lines Laid, DJB Tells NGT
DJB officials indicated that progress has been hampered by utility relocation requirements, technical challenges in densely built sectors and contractor mobilisation delays, compounded by recent monsoon conditions that limited sustained field operations. The board said coordination with multiple agencies has been necessary to avoid damage to existing services, which has added to implementation time. Officials also noted that work sequencing has been adjusted to prioritise sections posing the greatest immediate pollution risk.
The tribunal requested a detailed action plan and progress timetable and asked the board to present measures to accelerate completion while ensuring environmental safeguards. DJB outlined steps intended to hasten work, including deploying additional labour shifts, increasing machinery and enhancing onsite supervision, alongside tighter agency coordination to clear bottlenecks. The board emphasised that health and environmental protections will be maintained even as schedules are compressed.
Resident groups have registered concerns about odour and surface contamination where sewer lines remain incomplete, prompting the tribunal to indicate it will monitor compliance closely at follow up hearings. The board said it will provide periodic status reports to the tribunal and engage with local stakeholders to manage interim risks. The matter will return to the tribunal for review, where the pace of work and adherence to environmental conditions will be assessed.