DC Ganderbal Reviews Srinagar Ring Road Phase-II, Phase-IIA

Ganderbal Deputy Commissioner Shreya Singhal chaired a meeting on November 23 to review the progress of the ongoing Srinagar Ring Road Phase-II and Phase-IIA projects. The meeting focused on execution-related issues and measures required to keep work moving along the project alignments.

Officials presented a detailed account of the status of both projects, covering highway construction, structural works, land acquisition and the disbursement of compensation. The review also considered bottlenecks that could affect the timely execution of work and the need for coordinated action by the departments and agencies involved.

The meeting discussed a traffic management plan proposed by the National Highways Authority of India (NHAI) for the construction period. Singhal directed the Traffic Police, Civil Police, Revenue authorities and NHAI to jointly prepare a comprehensive plan to address potential disruptions and maintain smooth vehicular movement while construction is under way.

The Deputy Commissioner emphasised close coordination among all concerned departments and executing agencies. She instructed officials to follow the timelines fixed during the meeting and stressed that identified issues should be resolved on priority to support the timely completion of the projects.

Singhal also underlined the need to minimise inconvenience to the general public during the works. The meeting was attended by the Additional Deputy Commissioner, Ganderbal; Assistant Commissioner Revenue, Ganderbal; Superintending Engineers from Public Works (Roads and Buildings), Kashmir Power Distribution Corporation and NHAI; Executive Engineers from Irrigation and Flood Control and Public Health Engineering; Tehsildars of Lar and Wakura; and other concerned officials.

The review brought together administrative, engineering, revenue, policing and executing authorities responsible for different aspects of the projects. Their discussions covered both physical progress and supporting requirements, including compensation payments, land-related matters and arrangements for managing traffic during construction.

Related Stories

Kashmir Ring Road Stretch Gets December 31 Completion Deadline
Chief Minister Launches Rs. 582.6 mn Projects in Ganderbal
Srinagar Ring Road Phase 3 Alignment May Change to Protect Water Body