Highways Department Adds 50 Workers to Thanneerpandal ROB Project
The department’s action followed a report highlighting that the project had reached only 45 per cent completion after 15 months of construction. The delay had raised concerns among residents and motorists, with the project facing the possibility of missing its stipulated deadline. The highways department has also issued a notice to the contractor over the delayed execution.
The road closure has been introduced for motorists’ safety and to facilitate construction, according to a senior department official. Vehicles travelling from Avinashi Road near Coimbatore Medical College can continue towards TIDEL Park, but cannot proceed towards the Vilankurichi-Thanneerpandal junction. Motorists heading in that direction have been advised to use CODISSIA Road, travel to the S-bend junction and then continue towards Vilankurichi and Sathy Road.
The additional workforce has been divided into teams, with each group assigned specific construction activities so that different components can be undertaken simultaneously. The department intends to recover lost time and complete the project within the deadline. Service road work from TIDEL Park towards Hope College junction on Avinashi Road will also be taken up, while work on the opposite side will begin only after a court verdict in a pending case.