Dimapur–Kohima Rail Project Reaches 50% Physical Progress

The Dimapur–Kohima New Railway Line Project in Nagaland has achieved 50 per cent physical progress and 45.98 per cent financial progress, with expenditure reaching Rs. 71.76 bn by October 31, 2026. The figures were reported after an inspection by officials from the Northeast Frontier Railway (NFR) and the Nagaland government.

The inspection team included A Pongshi Phom, Advisor to Airway and Railway, Nagaland government; Thsuvisie Phoji, Additional Secretary, Aircell; Myingthungo Ababe Ezung, Officer on Special Duty, Aircell, Transport Department; and NFR Deputy Chief Engineer Harji Mal Meena. They visited project sites at Zubza, Piphema, Pherima and Molvom to review construction progress.

The team examined proposed station locations, tunnel sections, bridges and areas where tracks will be laid. The project was sanctioned in May 2007 and construction began during 2015–16. It covers 78.42 km and has a completion target of December 2029.

The line includes 20 tunnels, eight of which have been completed, including the longest at about 6,620 metres. Emergency escape or auxiliary tunnels are also planned to provide alternative passage during emergencies. There are 29 major bridges, with 15 completed, and 151 minor bridges, of which 138 are complete. Bridge No. 154, the longest, measures 551.60 metres.

Eight stations are planned, with Dhansiri, Dhansiripar, Sukhovi and Molvom completed. Pherima and Zubza are among the other principal locations, while Molvom is being developed as an important station. The inspection also covered a major bridge of about 500–600 feet and highlighted the technical challenges of construction across Nagaland’s terrain.

An extension from Zubza towards Imphal in Manipur is also under consideration. Survey work and consultations with consultants are under way for the proposed connectivity plan. The railway project is intended to strengthen transport links and support wider economic opportunities in Nagaland.