Mumbai Metro Line 5 First Train Reaches Kasheli Depot

The first train for Mumbai Metro Line 5 has arrived at the Mumbai Metropolitan Region Development Authority’s (MMRDA) Kasheli Depot in Bhiwandi, advancing preparations for testing on the 24.9-km Thane-Bhiwandi-Kalyan corridor. Passenger services are targeted to begin in early 2027, subject to pending construction, trial runs and safety clearances.

The delivery will enable MMRDA to undertake initial inspections and other depot-related preparations while work continues on the remaining infrastructure. Kasheli Depot will serve as the principal facility for parking, testing, inspection and maintenance of trains operating on the corridor.

The depot is spread across 27 hectares and is being developed to accommodate around 30 trainsets. Basic facilities completed for receiving the first train include a coach loading and unloading platform and a temporary inspection bay. The planned infrastructure includes five inspection lines, four workshop lines, a dedicated test track and train-washing facilities.

Preparations for corridor testing began before the dedicated train arrived at Kasheli. Electrification work on Line 5 was completed in September, while a trainset kept at Mandale Depot was transported coach by coach to the Line 4 corridor in Thane. It was subsequently moved to Line 5 through the interchange connection at Kasarvadavali during Navratri to support the start of trial runs.

Mumbai Metro Line 5 is a 24.90-km fully elevated route with 15 stations connecting Thane, Bhiwandi and Kalyan. The project has a base cost of Rs. 84.17 bn, including taxes and duties, and will interchange with the ongoing Mumbai Metro Line 4 and the proposed Mumbai Metro Line 12. It will also connect with the Central Railway network, enabling transfers between suburban rail and Metro services. The arrival of the first dedicated train is expected to improve the efficiency of testing, but passenger operations can begin only after the depot is completed and the required approvals are secured.

Related Stories

Maharashtra clears Metro Line 5A, expansion of Mumbai Metro Line 5
Aurionpro Bags Platform Screen Door Order For Mumbai Metro
ABB wins propulsion systems order for Mumbai Metro Lines 5 and 6