RVNL bags three orders from Chennai Metro Rail
The time period of the contract is 1,725 days and it is worth Rs 1,730 crore.
The second contract is for the construction of four underground stations at Dr Radhakrishnan Salai, Thirumayilai, Mandaneli, and Adyar Junction and two cross passage shafts and one emergency escape shaft and works other than diaphragm wall of one underground station at Greenways Road Metro in Corridor 3 of CMRL phase-II project.
The size of the contract is Rs 1,461 crore and the time period is 1,725 days.
The last contract is for the construction of three underground stations at Adyar Depot, Indira Nagar, and Taramani Road Junction (Taramani) and ramp and works other than the diaphragm wall of the underground station at Thiruvanmiyur Metro in Corridor 3 of CMRL phase-ii project. The time period of the contract is 1,630 days and it is worth Rs 8,065 crore, the company said.