Surat–Bilimora bullet train section electrified

The Mumbai–Ahmedabad Bullet Train project achieved a significant milestone with the successful energisation of the Overhead Equipment (OHE) system on the Surat–Bilimora section on 20 November 2026.

The approximately 50-km elevated section, covering both Up and Down lines, has progressed towards further testing activities. Energisation will be undertaken progressively across smaller sections under technical supervision to ensure operational safety and compliance.

The 508-km high-speed rail corridor incorporates an advanced 2 × 25 kV overhead traction system designed for high-speed railway operations. Its electrification network includes 14 traction substations positioned along the alignment to draw electricity from the national grid and supply power to trains.

Installation work at the first traction substation in Bilimora, Navsari district, has been completed across the control panel, changeover switch, transformer and circuit breaker buildings. The substation will receive electricity from Gujarat Energy Transmission Corporation Limited's 220 kV Ambetha Grid Substation.

A centralised control centre will monitor the electrical network to support reliable and safe operations.

The Surat–Bilimora alignment includes bridges across four rivers and a steel bridge over National Highway 53. Approximately 94,000 noise barriers have also been installed along the viaduct to minimise noise pollution in surrounding areas.

The energisation milestone represents another important advancement towards operational readiness of India's first high-speed rail corridor.

Related Stories

Second TBM begins Mumbai bullet train undersea tunnel
Tunnelling Towards Tomorrow
Mumbai–Ahmedabad Bullet Train Hits Tunnel Milestone
NDMC Approves Five Prakriti Cafés in Three Delhi Parks
Air India and Airbus to Build India's First Corporate SAF Programme