New Land Acquisition Model Accelerates Kochi Seaport-Airport Road Project
The acquisition process is part of the second phase of the project, which includes three sections: HMT Road-NAD Junction to Mahilalayam Junction, Mahilalayam Junction to Chowara, and Chowara to Airport Road. Construction has been completed on the 1.5 km stretch from Kalamassery to NAD, but land from NAD is still pending acquisition.
The land from NAD is ready for acquisition, with Rs 230.06 million handed over to the tahsildar to issue award enquiry notes to landowners. Once the necessary documents are produced, the compensation will be given, and the land will be acquired. Authorities are focused on expediting the acquisition of HMT land, where only one landholder remains. The NAD-Mahilalayam stretch, which involves over 400 landowners, is expected to take at least six months to complete.
The 6.5 km section from NAD to Mahilalayam is progressing, with two bridges across the Periyar river already constructed. However, the final 4.15 km section from Chowara to the airport is still awaiting government approval for land acquisition.