Bengaluru Metro Blue Line Trial Run Covers 6 km
The 58.19-km Blue Line will connect Central Silk Board with Kempegowda International Airport through KR Puram and Hebbal. Bengaluru Development Minister Krishna Byre Gowda said the trial marked progress towards completing the project, while stating that the government was working to finish pending works and open the line to passengers at the earliest.
BMRCL plans to extend trial operations from the depot through KR Puram to Marathahalli by 15 November. The 33 kV cables and third rail between the depot and Marathahalli have been charged in stages since 30 October, enabling the testing programme to expand along the corridor.
Signalling integration remains the principal work required before comprehensive testing can begin. Around 2 km of track installation and work at some stations are also pending. The Railway Board granted in-principle approval in August for communications-based train control signalling on the Blue and Pink lines.
The 19.75-km Phase 2A section between Central Silk Board and KR Puram is targeted for opening in mid-2027. The target for completing the full airport link was moved to March 2028 from December 2027 because of pending work at Marathahalli, Silk Board and Hebbal.
The trials are taking place shortly before the planned inauguration of the Pink Line’s elevated Kalena Agrahara-Tavarekere section on 13 November. Its opening is expected to take Bengaluru’s operational metro network to 103.6 km. The Blue Line is planned to have 29 stations and remains under construction across its airport-bound alignment.