Indian Railways Sets 120-Day Deadline to Redevelop Ahmedabad Platforms
To accelerate the work, Ahmedabad Division Divisional Railway Manager (DRM) Ved Prakash held a review meeting with officials from the Rail Land Development Authority, railway departments and the construction agency. Discussions covered construction progress, technical challenges, manpower and machinery availability, material supplies and coordination between the agencies involved.
Officials also reviewed the traffic and power blocks required for the construction. The plan includes 457 piles, 108 pile caps and 213 pedestals for platforms 4 and 5, and platforms 6 and 7. Around 6,400 t of structural steel will be fabricated and erected for the new concourse and related facilities.
The DRM directed officials to prioritise pile foundation work, pile caps and pedestals, Ballastless Track (BLT) work, and structural steel fabrication and erection. He also called for detailed planning at every stage and instructed the agencies to ensure adequate manpower, machinery and construction materials so the project can meet the 120-day schedule.
The redevelopment will be carried out while trains continue to operate through the station. Ahmedabad handles significant passenger and train movement, requiring the construction agencies to maintain operational continuity and passenger safety throughout the work. Railway officials said the project is intended to provide modern, safe and convenient facilities, including a world-class concourse, for passengers using the station.