Yadadri’s Fifth 800 MW Unit to Boost Telangana Power Supply

The 4,000 MW Yadadri Thermal Power Station in Damaracherla mandal of Nalgonda district is expected to strengthen Telangana’s power supply, with its fifth 800 MW unit scheduled to begin commercial operations in December. Four of the plant’s five units are already generating electricity for the state. The fifth unit was synchronised with the grid on October 20.

Telangana Power Generation Corporation (TGGENCO) is implementing an action plan to resolve technical issues in the coal-handling system and support generation from all five units during the upcoming Rabi season. The project faced delays because of the COVID-19 pandemic, forest clearances, railway land issues and environmental directions from the National Green Tribunal. Construction resumed in February 2024 after fresh environmental studies and public hearings.

TGGENCO officials said the plant’s boiler, turbine, generator, ash-handling and water-supply systems were functioning satisfactorily. Four coal-feeding lines have been restored, giving the facility a combined handling capacity of 3,200 t per hour and reducing interruptions in fuel supply. Coal is being transported from the Naini mine operated by Singareni Collieries Company, with three to four rakes arranged daily. About 426,000 t has so far been moved to Yadadri.

Agreements have also been finalised to procure 460,000 t from Mahanadi Coalfields and South Eastern Coalfields through the Window-II auction mechanism. Fuel Supply Agreements were concluded on November 4. Separately, the Standing Linkage Committee approved annual supplies of 7.71 mn t from Mahanadi Coalfields and Eastern Coalfields for two units.

Telangana recorded its highest power generation of 6,088 MW on November 11, with Yadadri contributing 2,754 MW. TGGENCO will restore the coal-feeding lines in phases, beginning with the first line from November 18 to 24, while maintaining generation through the others. Bharat Heavy Electricals and other contractors will work on conveyors, feeders, crushers, stackers and reclaimers. The plant is planned to reach its full 4,000 MW capacity after the restoration programme.

Related Stories

Naini Coal Consignment Reaches Yadadri Plant
YTPS Unit Three Declared Commercial After 811.99 MW Output
Telangana Inaugurates 800 MW Unit at Yadadri Plant
Hettich India And ECO Schulte Form Joint Venture In India
Address Maker sells over 200 Apollo Address plots in six weeks