30 km Bypass To Ease Chakan MIDC Traffic by December 2026
ROADS & HIGHWAYS

30 km Bypass To Ease Chakan MIDC Traffic by December 2026

The Maharashtra Industrial Development Corporation (MIDC) is nearing completion of a 30 km alternative bypass corridor designed to relieve heavy congestion on the Talegaon-Chakan-Shikrapur highway. The route runs parallel to the existing state highway and cuts through Chakan MIDC Phase two and Phase five before merging with the Pune-Nashik national highway. MIDC officials stated that the project is targeted for completion by December 2026 and that it will offer substantial relief to industrial logistics and daily commuters.

About five point five km of construction remains across three specific bottlenecks identified by MIDC engineers. The Navlakh Umbre bypass spans one point seven km and will bypass the village to prevent local congestion. Two connector sections of a total of one point five km comprising seven hundred and fifty metre links will join Phase two and Phase five, while a two point nine km Pune-Nashik highway link will replace a narrow, bottlenecked carriageway.

MIDC Regional Officer Nitin Gawali said land acquisition for the remaining stretches is in its final phase and is expected to be wrapped up within two to three weeks, which will allow final paving work to proceed. The completion of these alignments is being prioritised to ensure uninterrupted industrial operations during upcoming construction of the elevated Talegaon-Chakan-Shikrapur highway. Project managers are coordinating with local authorities to sequence work so that traffic disruption is minimised.

Industry representatives warned that pillar construction on the narrow main highway will cause severe traffic disruption, reinforcing the need for an alternative corridor. The Chakan Industries Association emphasised that the 30 km bypass will act as the primary diversion to absorb traffic spillover during the elevated highway works. In line with directives from Pune District Collector Jitendra Dudi, a majority of pothole repair work on the existing stretch was completed ahead of the August 31 deadline, improving immediate transit conditions for industrial freight.

The Maharashtra Industrial Development Corporation (MIDC) is nearing completion of a 30 km alternative bypass corridor designed to relieve heavy congestion on the Talegaon-Chakan-Shikrapur highway. The route runs parallel to the existing state highway and cuts through Chakan MIDC Phase two and Phase five before merging with the Pune-Nashik national highway. MIDC officials stated that the project is targeted for completion by December 2026 and that it will offer substantial relief to industrial logistics and daily commuters. About five point five km of construction remains across three specific bottlenecks identified by MIDC engineers. The Navlakh Umbre bypass spans one point seven km and will bypass the village to prevent local congestion. Two connector sections of a total of one point five km comprising seven hundred and fifty metre links will join Phase two and Phase five, while a two point nine km Pune-Nashik highway link will replace a narrow, bottlenecked carriageway. MIDC Regional Officer Nitin Gawali said land acquisition for the remaining stretches is in its final phase and is expected to be wrapped up within two to three weeks, which will allow final paving work to proceed. The completion of these alignments is being prioritised to ensure uninterrupted industrial operations during upcoming construction of the elevated Talegaon-Chakan-Shikrapur highway. Project managers are coordinating with local authorities to sequence work so that traffic disruption is minimised. Industry representatives warned that pillar construction on the narrow main highway will cause severe traffic disruption, reinforcing the need for an alternative corridor. The Chakan Industries Association emphasised that the 30 km bypass will act as the primary diversion to absorb traffic spillover during the elevated highway works. In line with directives from Pune District Collector Jitendra Dudi, a majority of pothole repair work on the existing stretch was completed ahead of the August 31 deadline, improving immediate transit conditions for industrial freight.

Related Stories

Gold Stories

Next Story
Building Material

From Rough to Refined: How Modern Plastering Is Changing Wall Finishes

When Rohan first walked into his newly constructed home, he imagined what it would become—a warm living room, a bright bedroom, and walls smooth enough to complement his carefully chosen interiors.But there was one problem.The walls didn't look anything like the finished home he had imagined.They were uneven in places, rough to the touch, and covered with visible patches and minor surface imperfections. Rohan initially thought paint would fix everything.His contractor had a different answer.“Before the paint, we need to get the plastering right.”That conversation made Rohan realise somet..

Next Story
Infrastructure Urban

Embraer to Acquire 51 Per Cent Stake in Mahindra Aerospace Arm

Brazilian aerospace major Embraer will acquire a 51 per cent equity stake in Novavayu Aerospace, a step-down subsidiary of Mahindra and Mahindra, under an Investment Agreement notified by the automobile company in an exchange filing. The transaction will give Embraer control of the aerospace business. Following completion of the acquisition, Novavayu Aerospace will cease to be a wholly owned subsidiary and become an associate of Mahindra Defence Systems, which is a step-down wholly owned subsidiary of Mahindra and Mahindra. The agreement is expected to be completed on or before December 1. Mah..

Next Story
Infrastructure Urban

RBI Opens Special Dollar Window for Three State-Run OMCs

The Reserve Bank of India (RBI) has opened a special facility to meet the entire daily US dollar requirements of three public sector oil marketing companies (OMCs), in a move aimed at easing pressure on the Indian rupee. The facility will take effect on October 12, 2026, and remain available until further notice. Indian Oil Corporation, Hindustan Petroleum Corporation and Bharat Petroleum Corporation are eligible to use the arrangement. Under the facility, the RBI will sell US dollars to the three companies through designated banks, allowing them to meet their oil-import payments without sourc..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code