Heavy Rains Delay Opening of Kusmalli Bridge
ROADS & HIGHWAYS

Heavy Rains Delay Opening of Kusmalli Bridge

The long awaited opening of Kusmalli Bridge on the Belagavi–Goa Road via Chorla has been pushed back by several days because backfilling on the Jamboti side remains unfinished. Continuous downpours across the Jamboti–Kankumbi stretch have made it impossible to place the granular sub base (GSB) material required to complete the approach ramp.

National Highways Executive Engineer Rajendra and a team of officials inspected the site on Wednesday. He confirmed that the bridge structure itself is finished, but the protective walls and ramp backfill still need attention. “If the rain eases, we can complete the work in two to three days and reopen the route to light vehicles,” he said.

With the Malaprabha River running high, authorities have instructed contractors to observe strict safety procedures and install additional barriers to protect workers and motorists until conditions improve.

The long awaited opening of Kusmalli Bridge on the Belagavi–Goa Road via Chorla has been pushed back by several days because backfilling on the Jamboti side remains unfinished. Continuous downpours across the Jamboti–Kankumbi stretch have made it impossible to place the granular sub base (GSB) material required to complete the approach ramp.National Highways Executive Engineer Rajendra and a team of officials inspected the site on Wednesday. He confirmed that the bridge structure itself is finished, but the protective walls and ramp backfill still need attention. “If the rain eases, we can complete the work in two to three days and reopen the route to light vehicles,” he said.With the Malaprabha River running high, authorities have instructed contractors to observe strict safety procedures and install additional barriers to protect workers and motorists until conditions improve.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code