Mettupalayam-Avinashi Road Work Delayed by Two Months
ROADS & HIGHWAYS

Mettupalayam-Avinashi Road Work Delayed by Two Months

The widening of the Mettupalayam-Avinashi road has been halted at several locations for around two months, raising concerns over delays to bridge and road works. Local residents and commuters have expressed frustration at the prolonged suspension and its impact on travel, safety and local business activity.

The 38 km stretch between Mettupalayam and Avinashi via Annur is being widened from a two-lane road into a four-lane highway. New bridges are being constructed and existing infrastructure is being widened at locations where required, including near Nadoor and at the junction leading to the Government Arts College on Annur Road, and at other identified pinch points.

Construction of new bridges near Nadoor and at the college junction has remained suspended for about two months. Reinforcement rods installed at the Nadoor bridge have reportedly been left exposed, prompting concern about possible deterioration. Around 10 houses alongside the road near the Nadoor bridge were vacated and demolished to facilitate the expansion, yet residents say little progress has followed, prolonging inconvenience and uncertainty for families.

A senior official of the State Highways Department in the Coimbatore Division acknowledged the delay and said the contractor had been working slowly and had been served a notice. The official added that several labourers had gone to their hometowns and were expected to return next week, after which work would be expedited. The project has been divided into two packages, with more than 90 per cent of work completed in the first package covering the Avinashi-Naal Road junction near Annur, and around 72 per cent completed in the second package between Naal Road and Mettupalayam Town. A few land acquisition tasks remain pending and the department is targeting completion of the entire project by December this year, with officials to review progress periodically.

The widening of the Mettupalayam-Avinashi road has been halted at several locations for around two months, raising concerns over delays to bridge and road works. Local residents and commuters have expressed frustration at the prolonged suspension and its impact on travel, safety and local business activity. The 38 km stretch between Mettupalayam and Avinashi via Annur is being widened from a two-lane road into a four-lane highway. New bridges are being constructed and existing infrastructure is being widened at locations where required, including near Nadoor and at the junction leading to the Government Arts College on Annur Road, and at other identified pinch points. Construction of new bridges near Nadoor and at the college junction has remained suspended for about two months. Reinforcement rods installed at the Nadoor bridge have reportedly been left exposed, prompting concern about possible deterioration. Around 10 houses alongside the road near the Nadoor bridge were vacated and demolished to facilitate the expansion, yet residents say little progress has followed, prolonging inconvenience and uncertainty for families. A senior official of the State Highways Department in the Coimbatore Division acknowledged the delay and said the contractor had been working slowly and had been served a notice. The official added that several labourers had gone to their hometowns and were expected to return next week, after which work would be expedited. The project has been divided into two packages, with more than 90 per cent of work completed in the first package covering the Avinashi-Naal Road junction near Annur, and around 72 per cent completed in the second package between Naal Road and Mettupalayam Town. A few land acquisition tasks remain pending and the department is targeting completion of the entire project by December this year, with officials to review progress periodically.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train’s Surat-Vapi Section Set for 2027

The first section of the Mumbai-Ahmedabad Bullet Train corridor, linking Surat and Vapi, is targeted to begin services in 2027. Construction is expected to be completed by December 2026, while Railway Minister Ashwini Vaishnaw has indicated that an inauguration could take place around the middle of 2027. The National High Speed Rail Corporation (NHSRCL) said the train being manufactured in India is expected to reach the tracks around April or May 2027. The train will undergo extensive testing before the section is opened for passenger services. The project began construction in 2021 and includ..

Next Story
Infrastructure Transport

Indian Railways Approves Four Projects Worth Rs. 7.36 bn Across Four States

Indian Railways has approved four projects with a combined value of Rs. 7.36 bn across Uttar Pradesh, Maharashtra, Andhra Pradesh and Gujarat. The programme covers train protection, signalling, electric traction supply and a road overbridge, with each project assigned to a different railway zone. In Uttar Pradesh, Rs. 2.52 bn has been approved to extend the Kavach 4.0 automatic train protection system across 607.7 km in the Lucknow Division of North Eastern Railway. The system monitors train movements and can apply the brakes if a driver fails to observe a signal or exceeds a safe speed. The w..

Next Story
Infrastructure Urban

Chandru Raheja Sells 1.49% Stake in Mindspace REIT for Rs. 5 bn

Billionaire Chandru Lachmandas Raheja has sold a 1.49 per cent holding in Mindspace Business Parks REIT for Rs. 5 bn through a bulk deal on the BSE. The transaction involved 9.9 mn units and was executed at an average price of Rs. 505 per unit, according to exchange data. Following the sale, units of Mindspace Business Parks REIT were trading 0.18 per cent lower at Rs. 504.05 on Tuesday. Exchange data did not identify the buyers involved in the transaction. Raheja is the chairman of real estate company K Raheja Corp. The sale involved 99,00,990 units, representing 1.49 per cent of the Mumbai-b..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code