RIPPL Sets May 15, 2027 Deadline for Chakhabama–Kikruma Road
ROADS & HIGHWAYS

RIPPL Sets May 15, 2027 Deadline for Chakhabama–Kikruma Road

Ratna Infrastructure Project (RIPPL) has assured the Joint Action Committee (JAC) of National Highway-29 that the delayed Chakhabama–Kikruma road project will be completed by May 15, 2027. The commitment was made amid growing public concern over the slow progress of work on the Kohima–Jessami Road.

RIPPL authorised signatory Dr MSN Murthy gave the assurance during a meeting with the JAC at the company’s base camp in Kikruma, Phek district, on November 2. The meeting followed an inspection of the National Highway-29 Package-II stretch from Chakhabama to Kikruma, involving JAC members, company representatives and frontal organisations from Kohima, Phek, Meluri and Kiphire.

The inspection began at RIPPL’s stone quarry site in Chakhabama and ended at the Kikruma base camp. JAC Convenor Vivolie Kezo expressed dissatisfaction over the prolonged delay and questioned the commitment of the National Highways and Infrastructure Development Corporation (NHIDCL) to completing the project on schedule.

Kezo noted that RIPPL had been awarded the project on January 5, 2024, with January 4, 2026, set as the original completion deadline. He raised concerns about construction quality, alleged deviations from tender specifications and a shortage of machinery, manpower and raw materials, while also citing recurring fuel shortages and delays in staff salary payments as factors affecting execution.

Murthy said concerns relating to the Ministry of Road Transport and Highways (MoRTH) had been resolved and assured the committee that construction quality would be maintained. He said large-scale execution would resume shortly after November 15, 2026, in line with the ministry’s directive, and reiterated the May 15, 2027 completion target.

The JAC agreed to cooperate with RIPPL but said work would be closely monitored. It warned that failure to meet the latest deadline would lead it to approach higher authorities, noting that years of delay had significantly eroded public patience and confidence in the contractor.

Ratna Infrastructure Project (RIPPL) has assured the Joint Action Committee (JAC) of National Highway-29 that the delayed Chakhabama–Kikruma road project will be completed by May 15, 2027. The commitment was made amid growing public concern over the slow progress of work on the Kohima–Jessami Road. RIPPL authorised signatory Dr MSN Murthy gave the assurance during a meeting with the JAC at the company’s base camp in Kikruma, Phek district, on November 2. The meeting followed an inspection of the National Highway-29 Package-II stretch from Chakhabama to Kikruma, involving JAC members, company representatives and frontal organisations from Kohima, Phek, Meluri and Kiphire. The inspection began at RIPPL’s stone quarry site in Chakhabama and ended at the Kikruma base camp. JAC Convenor Vivolie Kezo expressed dissatisfaction over the prolonged delay and questioned the commitment of the National Highways and Infrastructure Development Corporation (NHIDCL) to completing the project on schedule. Kezo noted that RIPPL had been awarded the project on January 5, 2024, with January 4, 2026, set as the original completion deadline. He raised concerns about construction quality, alleged deviations from tender specifications and a shortage of machinery, manpower and raw materials, while also citing recurring fuel shortages and delays in staff salary payments as factors affecting execution. Murthy said concerns relating to the Ministry of Road Transport and Highways (MoRTH) had been resolved and assured the committee that construction quality would be maintained. He said large-scale execution would resume shortly after November 15, 2026, in line with the ministry’s directive, and reiterated the May 15, 2027 completion target. The JAC agreed to cooperate with RIPPL but said work would be closely monitored. It warned that failure to meet the latest deadline would lead it to approach higher authorities, noting that years of delay had significantly eroded public patience and confidence in the contractor.

Related Stories

Gold Stories

Next Story
Real Estate

IGBC Green Building Congress 2026 advances India’s net-zero agenda

The Indian Green Building Council (IGBC), part of the Confederation of Indian Industry (CII), opened the 24th edition of the Green Building Congress 2026 at the Jio World Convention Centre, Mumbai, with a focus on accelerating India's green and net-zero building movement. The three-day event, being held from 26 to 28 November, brought together policymakers, industry leaders and sustainability experts to discuss green buildings, climate-resilient infrastructure and sustainable communities.A key highlight of the inaugural session was the launch of five pilot rating systems: Green Retail, DigiBui..

Next Story
Real Estate

Maharashtra CM inaugurates fifth Model Sub-Registrar Office in Mumbai

Maharashtra Chief Minister Devendra Fadnavis has inaugurated a Model Sub-Registrar Office (SRO) in Lower Parel, Mumbai, taking the number of such centres launched in the state to five. The initiative aims to modernise property registration services through technology-enabled infrastructure and citizen-centric processes.Developed by the Government of Maharashtra in association with VFS Global and WE Excel Software, the Lower Parel centre follows the launch of Model SROs in Pune, Bandra Kurla Complex in Mumbai, Navi Mumbai and Nagpur.The centres provide facilities for registering property-relate..

Next Story
Infrastructure Transport

NHBF hails Indian Army aircraft operations on Amritsar–Jamnagar corridor

The National Highways Builders Federation (NHBF) has welcomed the successful landing and take-off of four Indian Army microlight aircraft on the Amritsar–Jamnagar Economic Corridor (NH-754K) in Gujarat. The exercise demonstrated the potential of highway infrastructure to support defence operations and emergency response. The expressway was developed by CDS Infra Projects, an NHBF member company.Developed under the Bharatmala Pariyojana, the six-lane greenfield corridor is described as India's second-longest expressway. The operation was conducted by the Indian Army's Team Mountain Eagles as ..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code