Kolkata Metro Purple Line Tunnel Breakthrough
RAILWAYS & METRO RAIL

Kolkata Metro Purple Line Tunnel Breakthrough

The tunnel boring machine (TBM) DIVYA has completed a breakthrough at Victoria metro station, marking the end of the drive between Khidderpore and Victoria on the Joka-Esplanade Metro Corridor. The drive covered one point seven two kilometre (km) beneath central Kolkata and advances the construction of the Purple Line. The milestone follows successive tunnelling stages that linked key stretches of the route and prepares the alignment for station fit-outs and system installations.

The tunnel boring machine measured 95 metre (m) in length and weighed around 600 tonne (t) when assembled. Its outer diameter was six point six metre (m) with a finished tunnel diameter of five point eight metre (m). Precast segments specified at grade M50 and thickness 275 millimetre (mm) were used to line the bore, and two TBMs are being deployed to create twin tube tunnels along the corridor.

Key construction works included a launching shaft excavated inside St Thomas School at Khidderpore measuring 37 metre by 22 metre and 17 metre deep, which served as the lowering and assembly site for the machine. The TBM was manufactured in Chennai and mobilised to Kolkata in March 2025 for assembling and lowering, after which it proceeded beneath urban infrastructure. The tunnelling method transitions to conventional cut and cover beyond Park Street where surface conditions allow.

Earth pressure balancing technology was employed to contend with a high ground water table and soft soil strata typical of the city, with safety systems such as an inflatable seal, pressure transducers and dedicated TSG lines plus a backup TSG pump incorporated into the design. Project authorities described the breakthrough as a significant milestone that accelerates work on station completion and systems integration ahead of planned commissioning phases. The progress is expected to enhance connectivity along the Purple Line and support urban transit capacity once services commence.

The tunnel boring machine (TBM) DIVYA has completed a breakthrough at Victoria metro station, marking the end of the drive between Khidderpore and Victoria on the Joka-Esplanade Metro Corridor. The drive covered one point seven two kilometre (km) beneath central Kolkata and advances the construction of the Purple Line. The milestone follows successive tunnelling stages that linked key stretches of the route and prepares the alignment for station fit-outs and system installations. The tunnel boring machine measured 95 metre (m) in length and weighed around 600 tonne (t) when assembled. Its outer diameter was six point six metre (m) with a finished tunnel diameter of five point eight metre (m). Precast segments specified at grade M50 and thickness 275 millimetre (mm) were used to line the bore, and two TBMs are being deployed to create twin tube tunnels along the corridor. Key construction works included a launching shaft excavated inside St Thomas School at Khidderpore measuring 37 metre by 22 metre and 17 metre deep, which served as the lowering and assembly site for the machine. The TBM was manufactured in Chennai and mobilised to Kolkata in March 2025 for assembling and lowering, after which it proceeded beneath urban infrastructure. The tunnelling method transitions to conventional cut and cover beyond Park Street where surface conditions allow. Earth pressure balancing technology was employed to contend with a high ground water table and soft soil strata typical of the city, with safety systems such as an inflatable seal, pressure transducers and dedicated TSG lines plus a backup TSG pump incorporated into the design. Project authorities described the breakthrough as a significant milestone that accelerates work on station completion and systems integration ahead of planned commissioning phases. The progress is expected to enhance connectivity along the Purple Line and support urban transit capacity once services commence.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Panel Urges Zone-Wise Freight Plans and Crew Strengthening

A Parliamentary Standing Committee has urged the Railway Ministry to prepare zone-wise plans to enhance freight traffic in regions with limited mineral movement and industrial activity, according to its ninth report tabled in Parliament on 10 August. The Committee commended efforts to augment network capacity through multitracking, operationalisation of Dedicated Freight Corridors (DFC) and modernisation of yards. It noted that the Ministry has said periodic data-driven assessments are carried out with inputs from Zonal Railways, Divisional Railways and Business Development Units to support po..

Next Story
Infrastructure Urban

Coal India Weighs Buying Wealth Minerals Unit For Chile Lithium

Coal India Limited is evaluating a proposal to acquire the Chilean lithium assets held by the Wealth Minerals unit in Canada as part of a strategic move into battery materials. The company is assessing the asset portfolio, regulatory landscape and integration challenges while retaining coal operations as its core business. The potential interest reflects a shift by a state-owned miner towards minerals critical to the low emission transition. Wealth Minerals, a Canada-based exploration company, holds licences and exploration agreements in Chile that involve hard rock and brine lithium prospects..

Next Story
Infrastructure Energy

Bajel Projects Wins Ultra?Mega Transmission Line Contract

Bajel Projects Limited has secured an Ultra?Mega engineering, procurement and construction order for a transmission line package TL05 from PowerGrid Corporation of India Limited on behalf of its special purpose vehicle. The award forms part of the Western Region–Eastern Region inter?regional network expansion scheme Part A procured under the tariff based competitive bidding route. The contract covers construction of a 765 kV double circuit transmission line. The scope includes bypassing of the Raigarh (Tamnar)–Dharamjaygarh (Sec?B) 765 kV double circuit line and reconfiguration to form the..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement