The tunnel boring machine (TBM) DIVYA has completed a breakthrough at Victoria metro station, marking the end of the drive between Khidderpore and Victoria on the Joka-Esplanade Metro Corridor. The drive covered one point seven two kilometre (km) beneath central Kolkata and advances the construction of the Purple Line. The milestone follows successive tunnelling stages that linked key stretches of the route and prepares the alignment for station fit-outs and system installations.

The tunnel boring machine measured 95 metre (m) in length and weighed around 600 tonne (t) when assembled. Its outer diameter was six point six metre (m) with a finished tunnel diameter of five point eight metre (m). Precast segments specified at grade M50 and thickness 275 millimetre (mm) were used to line the bore, and two TBMs are being deployed to create twin tube tunnels along the corridor.

Key construction works included a launching shaft excavated inside St Thomas School at Khidderpore measuring 37 metre by 22 metre and 17 metre deep, which served as the lowering and assembly site for the machine. The TBM was manufactured in Chennai and mobilised to Kolkata in March 2025 for assembling and lowering, after which it proceeded beneath urban infrastructure. The tunnelling method transitions to conventional cut and cover beyond Park Street where surface conditions allow.

Earth pressure balancing technology was employed to contend with a high ground water table and soft soil strata typical of the city, with safety systems such as an inflatable seal, pressure transducers and dedicated TSG lines plus a backup TSG pump incorporated into the design. Project authorities described the breakthrough as a significant milestone that accelerates work on station completion and systems integration ahead of planned commissioning phases. The progress is expected to enhance connectivity along the Purple Line and support urban transit capacity once services commence.

The tunnel boring machine (TBM) DIVYA has completed a breakthrough at Victoria metro station, marking the end of the drive between Khidderpore and Victoria on the Joka-Esplanade Metro Corridor. The drive covered one point seven two kilometre (km) beneath central Kolkata and advances the construction of the Purple Line. The milestone follows successive tunnelling stages that linked key stretches of the route and prepares the alignment for station fit-outs and system installations. The tunnel boring machine measured 95 metre (m) in length and weighed around 600 tonne (t) when assembled. Its outer diameter was six point six metre (m) with a finished tunnel diameter of five point eight metre (m). Precast segments specified at grade M50 and thickness 275 millimetre (mm) were used to line the bore, and two TBMs are being deployed to create twin tube tunnels along the corridor. Key construction works included a launching shaft excavated inside St Thomas School at Khidderpore measuring 37 metre by 22 metre and 17 metre deep, which served as the lowering and assembly site for the machine. The TBM was manufactured in Chennai and mobilised to Kolkata in March 2025 for assembling and lowering, after which it proceeded beneath urban infrastructure. The tunnelling method transitions to conventional cut and cover beyond Park Street where surface conditions allow. Earth pressure balancing technology was employed to contend with a high ground water table and soft soil strata typical of the city, with safety systems such as an inflatable seal, pressure transducers and dedicated TSG lines plus a backup TSG pump incorporated into the design. Project authorities described the breakthrough as a significant milestone that accelerates work on station completion and systems integration ahead of planned commissioning phases. The progress is expected to enhance connectivity along the Purple Line and support urban transit capacity once services commence.

Related Stories

Gold Stories

Next Story
Technology

UniSteps Launches BcStep for Construction Industry

UniSteps Consulting has launched BcStep, a Business Operating Network (BON) designed to bring project information, communication, tasks and workflows onto a single digital platform for the construction industry.The platform is aimed at connecting developers, architects, consultants, project management consultants, contractors, suppliers and internal teams. BcStep integrates enterprise resource planning (ERP), human resource management (HRM), chat, email and task management within one ecosystem.The company said the platform is designed to reduce time spent searching across multiple systems, man..

Next Story
Equipment

bauma ConExpo Exclusive: We are building an ecosystem around the machine: Rentease

- Inputs by Meghraj Singh, Chairman and Managing Director, RenteaseHow has RentEase evolved from a rental company into a manufacturing business?RentEase started as a rental company in 2017, after we acquired a Bangalore-based company with around 70–75 machines. Over the years, our experience on the ground helped us understand what customers actually need. We realised that they are not simply looking for a machine but for a complete equipment ecosystem.This led us to develop our own machines under the RE brand, with the concept of ‘Make it easy for our customers’. We are designing eq..

Next Story
Equipment

bauma ConExpo Exclusive: Vector can deliver a floor in five to seven days: Eastman

-Inputs by Ashish Dhir, Chief Operating Officer, Eastman ImpexWhat were the key products showcased by Eastman Impex at Bauma CONEXPO India 2026?As we celebrate 30 years of the Eastman Group, we are expanding our scaffolding and formwork portfolio with the launch of Vector, our brand for aluminium monolithic formwork systems.The system addresses the growing demand from high-rise residential projects, particularly in Tier 1 and Tier 2 cities. With more high-rise developments coming up, there is a strong need for formwork systems that enable faster construction.What differentiates Vector from con..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code