269 projects worth Rs 12.30 trillion reviewed under the government’s PRAGATI platform
OIL & GAS

269 projects worth Rs 12.30 trillion reviewed under the government’s PRAGATI platform

This January, Prime Minister Narendra Modi chaired the 32nd interaction of PRAGATI—the ICT-based, multimodal platform for Pro-Active Governance and Timely Implementation, involving the Centre and state governments. Nine delayed projects worth Rs 240 billion were reviewed in the meeting. These projects are spread across nine states: Odisha, Telangana, Maharashtra, Jharkhand, Bihar, Karnataka, Andhra Pradesh, Kerala and Uttar Pradesh—and three Union Territories. The projects include three from the Ministry of Railways, five from the Ministry of Road Transport and Highways and one from the Ministry of Petroleum and Natural Gas. Further, in the previous 31 PRAGATI interactions, a total of 269 projects with a total investment of Rs 12.30 trillion were reviewed by the Prime Minister.That said, despite CW’s continuous efforts, data on these projects was not made available.

Effective mechanism?
While the delay saga continues, PRAGATI has helped fast-track of stuck projects, leading to cost and time savings. “Many projects stuck for years have achieved completion, such as the Eastern and Western Peripheral Expressway around Delhi, Pakyong Airport in Sikkim, the Panipat Jalandhar six-lane project and Phase 1 of the Delhi-Meerut Expressway,” observes Vijay Agrawal, Executive Director, Equirus Capital.

“The platform has reviewed and taken steps to remove bottlenecks in multiple projects covering an investment of over Rs 12 trillion,” says Shubham Jain, Group Head & Senior Vice-President, Corporate Ratings, ICRA. “While it would be difficult to quantify the impact of PRAGATI on project execution, it is certainly a positive initiative that can help resolve bottlenecks in some large projects.”

The PRAGATI mechanism for monitoring is an ongoing process. “After its implementation and until March 2018, cost overruns remained under 15 per cent,” according to Siva Subramanian, Director, Infrastructure & Project Finance, India Ratings & Research (Fitch Group).Given that projects are added and dropped over the years, he believes cost overrun is not the only metric to be measured. “Project completion is an important aspect for the assessment of success.”

From the perspective of a construction contracting company, Yogesh Kumar Jain, Managing Director, PNC Infratech, says, “PRAGATI is an effective and expedient project-monitoring framework mechanism reviewed monthly at the highest levels of both the Centre and state governments. It is learnt that several big-ticket infrastructure projects that have been stuck for years could be accomplished through this platform during the past five years. A programme of this nature and enormity will certainly instil confidence in any infrastructure implementation company like us in successful delivery of big-ticket projects.”

TABLE
Current status of some of the 269 projects reviewed under PRAGATI

Region

Project Name

State

Sector

Responsibility

Current Status

CentralIndia

Nigahi expansion project

Madhya Pradesh

Coal

M/o Coal

Completed

Central India

Transmission system of Raipur-Wardha

Chhattisgarh

Power

M/o Power

Completed

East India

Rail-cum-road bridge across Ganga

Bihar

Railways

M/o Railways

Rail section completed. Road section partially completed

East India

Rail-cum-road bridge across Ganga at Munger

 

Bihar

Railways

M/o Railways

Rail section completed. Road section to be completed by September 2021

East India

Doubling of Bhubaneshwar-Delang-PuriRail

Odissa

Railways

M/o Railways

Completed

East India

Paradip-Raipur-Ranchi Pipeline

Chhattisgarh, Odisha & Jharkhand

Oil & Gas

MoPNG

Under construction

East India

Four-lane Bhubaneshwar-Puri section of NH203

Odissa

Roads

MoRTH

Completed

South India

Strategic crude oil reserves of ISPRL

 

Andhra Pradesh & Karnataka

Oil & Gas

MoPNG

Completed

Northeast India

Gauge conversion (rail line connectivity Lumding-Silchar)

Assam

Railways

Railways

Completed

Northeast India

Pare Hydroelectric Project (110 mw) of NEEPCO

Arunachal Pradesh

Power

Power

Completed

North India

Six-lane highway Panipat-Jalandhar section of NH1 (291 km)

Haryana & Punjab

Roads

MoRTH

Completed

North India

Six-lane Eastern Peripheral Expressway (135 km)

Uttar Pradesh & Haryana

Roads

MoRTH

Completed

North India

330- mw KishangangaHydroelectric Project

Jammu & Kashmir

Power

Power

Completed

Southeast Asia

Construction of parliament building and salmadam in Afghanistan

Afghanistan

International

MEA

Completed

Southeast Asia

Kaladan multimodal transit transport &RihTedimroad projects

Myanmar

International

MEA

Under construction 

South India

42-km Bangalore Metro Rail (BMRP) Phase 1

Karnataka

Urban Affairs

MoHUA

Completed

South India

KudgiSuper Thermal Power Plant Stage 1 (3× 800 mw)

Karnataka

Power

Power

Completed

West India

102-mw wind power project

Rajasthan

Renewables

MoPNG

Completed

West India

Indore to Gujarat-MP border section Of NH59

Gujarat & Madhya Pradesh

Roads

MoRTH

Completed

Source: Equirus Capital


This January, Prime Minister Narendra Modi chaired the 32nd interaction of PRAGATI—the ICT-based, multimodal platform for Pro-Active Governance and Timely Implementation, involving the Centre and state governments. Nine delayed projects worth Rs 240 billion were reviewed in the meeting. These projects are spread across nine states: Odisha, Telangana, Maharashtra, Jharkhand, Bihar, Karnataka, Andhra Pradesh, Kerala and Uttar Pradesh—and three Union Territories. The projects include three from the Ministry of Railways, five from the Ministry of Road Transport and Highways and one from the Ministry of Petroleum and Natural Gas. Further, in the previous 31 PRAGATI interactions, a total of 269 projects with a total investment of Rs 12.30 trillion were reviewed by the Prime Minister.That said, despite CW’s continuous efforts, data on these projects was not made available.Effective mechanism?While the delay saga continues, PRAGATI has helped fast-track of stuck projects, leading to cost and time savings. “Many projects stuck for years have achieved completion, such as the Eastern and Western Peripheral Expressway around Delhi, Pakyong Airport in Sikkim, the Panipat Jalandhar six-lane project and Phase 1 of the Delhi-Meerut Expressway,” observes Vijay Agrawal, Executive Director, Equirus Capital.“The platform has reviewed and taken steps to remove bottlenecks in multiple projects covering an investment of over Rs 12 trillion,” says Shubham Jain, Group Head & Senior Vice-President, Corporate Ratings, ICRA. “While it would be difficult to quantify the impact of PRAGATI on project execution, it is certainly a positive initiative that can help resolve bottlenecks in some large projects.”The PRAGATI mechanism for monitoring is an ongoing process. “After its implementation and until March 2018, cost overruns remained under 15 per cent,” according to Siva Subramanian, Director, Infrastructure & Project Finance, India Ratings & Research (Fitch Group).Given that projects are added and dropped over the years, he believes cost overrun is not the only metric to be measured. “Project completion is an important aspect for the assessment of success.”From the perspective of a construction contracting company, Yogesh Kumar Jain, Managing Director, PNC Infratech, says, “PRAGATI is an effective and expedient project-monitoring framework mechanism reviewed monthly at the highest levels of both the Centre and state governments. It is learnt that several big-ticket infrastructure projects that have been stuck for years could be accomplished through this platform during the past five years. A programme of this nature and enormity will certainly instil confidence in any infrastructure implementation company like us in successful delivery of big-ticket projects.”TABLECurrent status of some of the 269 projects reviewed under PRAGATIRegionProject NameStateSectorResponsibilityCurrent StatusCentralIndiaNigahi expansion projectMadhya PradeshCoalM/o CoalCompletedCentral IndiaTransmission system of Raipur-WardhaChhattisgarhPowerM/o PowerCompletedEast IndiaRail-cum-road bridge across GangaBiharRailwaysM/o RailwaysRail section completed. Road section partially completedEast IndiaRail-cum-road bridge across Ganga at Munger BiharRailwaysM/o RailwaysRail section completed. Road section to be completed by September 2021East IndiaDoubling of Bhubaneshwar-Delang-PuriRailOdissaRailwaysM/o RailwaysCompletedEast IndiaParadip-Raipur-Ranchi PipelineChhattisgarh, Odisha & JharkhandOil & GasMoPNGUnder constructionEast IndiaFour-lane Bhubaneshwar-Puri section of NH203OdissaRoadsMoRTHCompletedSouth IndiaStrategic crude oil reserves of ISPRL Andhra Pradesh & KarnatakaOil & GasMoPNGCompletedNortheast IndiaGauge conversion (rail line connectivity Lumding-Silchar)AssamRailwaysRailwaysCompletedNortheast IndiaPare Hydroelectric Project (110 mw) of NEEPCOArunachal PradeshPowerPowerCompletedNorth IndiaSix-lane highway Panipat-Jalandhar section of NH1 (291 km)Haryana & PunjabRoadsMoRTHCompletedNorth IndiaSix-lane Eastern Peripheral Expressway (135 km)Uttar Pradesh & HaryanaRoadsMoRTHCompletedNorth India330- mw KishangangaHydroelectric ProjectJammu & KashmirPowerPowerCompletedSoutheast AsiaConstruction of parliament building and salmadam in AfghanistanAfghanistanInternationalMEACompletedSoutheast AsiaKaladan multimodal transit transport &RihTedimroad projectsMyanmarInternationalMEAUnder construction South India42-km Bangalore Metro Rail (BMRP) Phase 1KarnatakaUrban AffairsMoHUACompletedSouth IndiaKudgiSuper Thermal Power Plant Stage 1 (3× 800 mw)KarnatakaPowerPowerCompletedWest India102-mw wind power projectRajasthanRenewablesMoPNGCompletedWest IndiaIndore to Gujarat-MP border section Of NH59Gujarat & Madhya PradeshRoadsMoRTHCompletedSource: Equirus Capital

Related Stories

Gold Stories

Next Story
Real Estate

LML Realty Sells Out Jhirka Valley Industrial Park in Haryana

LML Realty, the real estate arm of LML Group, recently announced the complete sell-out of its Jhirka Valley Industrial Park in Haryana, with over 1.17 million sq ft of industrial space acquired by more than 50 companies. With utilities and internal infrastructure in place, the company has commenced plot handovers, enabling buyers to begin construction and establish their operations.The industrial park has attracted companies across diverse sectors, including chemicals, metals and alloys, textiles, electrical equipment, energy, logistics, construction, polymers and engineering. Key buyers inclu..

Next Story
Real Estate

WSB Real Estate Partners Exits Six Housing Investments

WSB Real Estate Partners recently announced the successful exit of six residential investments across Bengaluru, Mumbai Metropolitan Region (MMR) and National Capital Region (NCR), delivering an average internal rate of return (IRR) of 19–21 per cent and an overall investment return of 1.4 times.The real estate-focused investment firm invested approximately Rs 7 billion across six mid-affordable housing projects over the past four years. All six investments were fully repaid between April and November 2026, several months ahead of their original investment tenures.WSB collaborated with sever..

Next Story
Infrastructure Transport

Aluminium Industry Seeks Policy Support for Rs 4 Trillion Investment

The Aluminium Association of India (AAI) has recently urged the government to introduce supportive policy measures to safeguard the sector’s proposed Rs 4 trillion investment pipeline. The association highlighted the need for a predictable policy framework to strengthen domestic manufacturing, expand production capacity and reduce import dependence.AAI submitted its recommendations for the Union Budget 2027-28 to the Ministries of Finance, Commerce and Industry, and Mines, along with the Department for Promotion of Industry and Internal Trade (DPIIT).India’s aluminium demand is projected t..