SCCL Plans Daily Supply of 75,500 t of Coal to TGGENCO Plants
COAL & MINING

SCCL Plans Daily Supply of 75,500 t of Coal to TGGENCO Plants

Singareni Collieries Company (SCCL) and Telangana GENCO (TGGENCO) have prepared an action plan to ensure the daily supply of 75,500 t of coal to thermal power plants amid rising electricity demand and complaints about inadequate supply and frequent outages. The plan combines railway and road transportation from mines in Telangana and Odisha.

Officials of both organisations reviewed the requirements of each plant during a video conference on Tuesday. Discussions covered current supplies, coal quality, railway rake availability, loading and unloading operations, and transportation difficulties affecting deliveries.

Under the plan, 56,000 t of coal will be transported daily through 14 railway rakes, while another 19,500 t will be moved by road. Plant-wise requirements were assessed at 24,000 t a day for Kothagudem, 4,500 t for Kakatiya, 15,000 t for Bhadradri and 34,000 t for Yadadri.

For Yadadri, the plan provides for 8,000 t a day through two rakes from the Naini coal block in Odisha and 36,000 t through six rakes from SCCL’s local mines. SCCL officials said measures were being taken to increase supplies from Naini, according to a press release issued by the company.

SCCL’s Marketing Department reported that 1.5 mn t of coal had been supplied to TGGENCO power plants through road and rail transport up to September 28. The corresponding figure for the same period last year was 1.14 mn t. TGGENCO officials attributed the increase in electricity demand to dry conditions associated with El Niño and said additional coal was needed to support higher generation. The meeting instructed area general managers and chief engineers to coordinate closely to resolve issues involving supply, transportation and receipt of coal.

Singareni Collieries Company (SCCL) and Telangana GENCO (TGGENCO) have prepared an action plan to ensure the daily supply of 75,500 t of coal to thermal power plants amid rising electricity demand and complaints about inadequate supply and frequent outages. The plan combines railway and road transportation from mines in Telangana and Odisha. Officials of both organisations reviewed the requirements of each plant during a video conference on Tuesday. Discussions covered current supplies, coal quality, railway rake availability, loading and unloading operations, and transportation difficulties affecting deliveries. Under the plan, 56,000 t of coal will be transported daily through 14 railway rakes, while another 19,500 t will be moved by road. Plant-wise requirements were assessed at 24,000 t a day for Kothagudem, 4,500 t for Kakatiya, 15,000 t for Bhadradri and 34,000 t for Yadadri. For Yadadri, the plan provides for 8,000 t a day through two rakes from the Naini coal block in Odisha and 36,000 t through six rakes from SCCL’s local mines. SCCL officials said measures were being taken to increase supplies from Naini, according to a press release issued by the company. SCCL’s Marketing Department reported that 1.5 mn t of coal had been supplied to TGGENCO power plants through road and rail transport up to September 28. The corresponding figure for the same period last year was 1.14 mn t. TGGENCO officials attributed the increase in electricity demand to dry conditions associated with El Niño and said additional coal was needed to support higher generation. The meeting instructed area general managers and chief engineers to coordinate closely to resolve issues involving supply, transportation and receipt of coal.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

VECV Sales Rise 49.6% to 11,396 Units in September

VE Commercial Vehicles Ltd (VECV), a joint venture between Volvo Group and Eicher Motors, recorded sales of 11,396 units in September 2026, up 49.6 per cent from 7,619 units in September 2025.The total included 11,146 units under the Eicher brand and 250 units under the Volvo brand.Eicher-branded trucks and buses recorded sales of 11,146 units during the month, compared with 7,352 units in September 2025, registering growth of 51.6 per cent.In the domestic commercial vehicle market, Eicher trucks and buses reported sales of 10,479 units, up 57.5 per cent from 6,652 units in the corresponding p..

Next Story
Infrastructure Urban

"Agentic AI set to transform supply chain decision-making."

Interview with: Lalit Das, Founder & CEO, Agentra AIWhy the next phase of supply chain technology will be about AI that acts, not just advises?Supply chains no longer have a visibility problem. They have a decision-latency problem. It takes about 8.7 hours to detect a disruption and more than 40 more to understand its impact, all before anyone acts. Meanwhile, disruption costs the global economy an estimated $184 billion a year.Enterprises already own excellent systems of record. What they lack is a system of action. Copilots don't fix that, they just give faster answers about a broken pro..

Next Story
Real Estate

BNW Developments Opens Sydney Office to Target UAE Investors

BNW Developments has expanded its international presence with the opening of a new office in Sydney, Australia, aimed at strengthening engagement with Australian investors interested in the UAE residential property market.The Sydney office will serve as a local platform for investors, wealth advisers, brokerage firms and real estate professionals exploring opportunities in Dubai and Ras Al Khaimah.Headquartered in Dubai, BNW Developments has launched 13 projects and has another 16 projects in its pipeline, representing a combined gross development value of around AED 32 billion (USD 8.7 billio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code