Ace Energy completes tunnelling across major rivers in Assam
OIL & GAS

Ace Energy completes tunnelling across major rivers in Assam

Ace Energy Infrastructure, a part of Mumbai based Ace Pipeline Group, completed a vital link in the Barauni-Guwahati Natural Gas Pipeline being executed by GAIL (India) as part of Pradhan Mantri Urja Ganga project, by completing tunnelling under the confluence of Kanamakra, Aie and Manas River in Chirang District in Assam, near Bongaigaon city.

The breakthrough of the micro-tunnel boring machine was achieved in the early morning hours of July 2, 2023. This marks the end of micro tunnelling in the project, with Ace Energy now having completed construction of a tunnel of diameter 1,600 mm across a total length of 1200 m at a depth of 11-12 m under the river bed, with strata consisting of extremely hard and abrasive boulders and a river flowing up to its brim for the past three months owing to the flooding in its upper reaches in Bhutan.

The construction crews are expected to install the 24-inch carbon steel pipeline to transport natural gas within this tunnel in the next few weeks. Once this is done, it will serve as a final link to complete a 1600 km network of gas pipelines from Barauni in Central India to Guwahati in North-East India, and further from Guwahati right upto Numaligarh crossing major rivers such as Subhansiri and Brhamapura as part of extension of Prime Minister Narendra Modi’s Urja Ganga Project which will bring natural gas connectivity from Guwahati to Numaligarh and all towns and cities of the North-east. Ranchi based MECON spearheaded the engineering efforts for the project having been appointed as Project Management Consultant to GAIL.

Speaking about this achievement, KB Singh, Executive Director (Eastern Region), GAIL (India), commented, "The break-through of a tunnel boring machine is a culmination of months of back-breaking hard work, with front line crew working 24 x 7 in rain and hail, and the efforts of project managers, designers, and countless other faces behind the scenes who ensured that the front-end crew would succeed.”

Speaking about this achievement, Ravneet Singh, Director, Ace Energy Infrastructure, commented, “This milestone is a remarkable achievement for all of us and we hope this is a forerunner for many more breakthroughs in India and also across the Globe.”

Ace Energy Infrastructure, a part of Mumbai based Ace Pipeline Group, completed a vital link in the Barauni-Guwahati Natural Gas Pipeline being executed by GAIL (India) as part of Pradhan Mantri Urja Ganga project, by completing tunnelling under the confluence of Kanamakra, Aie and Manas River in Chirang District in Assam, near Bongaigaon city.The breakthrough of the micro-tunnel boring machine was achieved in the early morning hours of July 2, 2023. This marks the end of micro tunnelling in the project, with Ace Energy now having completed construction of a tunnel of diameter 1,600 mm across a total length of 1200 m at a depth of 11-12 m under the river bed, with strata consisting of extremely hard and abrasive boulders and a river flowing up to its brim for the past three months owing to the flooding in its upper reaches in Bhutan.The construction crews are expected to install the 24-inch carbon steel pipeline to transport natural gas within this tunnel in the next few weeks. Once this is done, it will serve as a final link to complete a 1600 km network of gas pipelines from Barauni in Central India to Guwahati in North-East India, and further from Guwahati right upto Numaligarh crossing major rivers such as Subhansiri and Brhamapura as part of extension of Prime Minister Narendra Modi’s Urja Ganga Project which will bring natural gas connectivity from Guwahati to Numaligarh and all towns and cities of the North-east. Ranchi based MECON spearheaded the engineering efforts for the project having been appointed as Project Management Consultant to GAIL.Speaking about this achievement, KB Singh, Executive Director (Eastern Region), GAIL (India), commented, The break-through of a tunnel boring machine is a culmination of months of back-breaking hard work, with front line crew working 24 x 7 in rain and hail, and the efforts of project managers, designers, and countless other faces behind the scenes who ensured that the front-end crew would succeed.”Speaking about this achievement, Ravneet Singh, Director, Ace Energy Infrastructure, commented, “This milestone is a remarkable achievement for all of us and we hope this is a forerunner for many more breakthroughs in India and also across the Globe.”

Next Story
Infrastructure Urban

Mineral Auction Rules Amended To Speed Mine Operationalisation

The Ministry of Mines notified the Mineral (Auction) Second Amendment Rules, 2026 on 30 March 2026 to accelerate operationalisation of mines and improve ease of doing business in the mining sector. The amendment follows a prior change to the Mineral (Auction) Rules, 2015 effected on 17 October 2025 that introduced intermediary timelines between issuance of a letter of intent (LoI) and execution of the mining lease. The 2025 change provided that one per cent of performance security would be appropriated for each month of delay by the preferred bidder and introduced incentives for early operatio..

Next Story
Infrastructure Transport

Indian Railways Strengthens Telecom And AI Safety Systems

Indian Railways strengthened its telecom and digital infrastructure during 2025-26 with the aim of improving safety, operational efficiency and the passenger experience. The programme promoted modernisation through advanced technologies, robust communication systems and passenger-centric solutions. These measures were presented as part of a drive to build a digitally integrated rail ecosystem. A key development was the enhancement of the Internet Protocol Multi-Protocol Label Switching (IP MPLS) backbone, commissioned at 1,396 stations to meet bandwidth needs of mission-critical applications. ..

Next Story
Infrastructure Transport

NHAI Holds Workshop on Litigation Management and Coordination

The National Highways Authority of India (NHAI) organised a day-long workshop in New Delhi to strengthen capacity and interdepartmental synergy for faster execution of national highway projects. The event was held under Mission Karmayogi – Sadhana Saptah, an initiative of the Government of India to enhance governance through capacity building and improved processes. The workshop focused on structured and solution oriented deliberations to address implementation constraints. The session was chaired by the NHAI chairman Santosh Kumar Yadav and brought together senior officials from NHAI, the M..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement