+
Bangladesh Court Halts Adani Arbitration Pending Probe
POWER & RENEWABLE ENERGY

Bangladesh Court Halts Adani Arbitration Pending Probe

Bangladesh’s High Court on Thursday ordered India’s Adani Group to halt its planned international arbitration in Singapore over a payment dispute with the state-run Bangladesh Power Development Board (BPDB). The suspension will remain in place until an investigation into Adani’s power supply agreement is completed.

Court officials said a two-judge bench directed that arbitration be paused until a committee appointed by the court submits its findings on the power purchase agreement and any potential irregularities. The order followed a petition seeking judicial intervention to review and scrap the BPDB–Adani deal, which the petitioner described as “one-sided” and signed during the tenure of former prime minister Sheikh Hasina.

The petition argued that Adani’s tariff was significantly higher than regional benchmarks — with electricity from Indian state-owned firms priced at 5.5 taka per unit, from other private Indian firms at 8.5 taka, and from Nepal at 8 taka, compared with more than 14 taka per unit for Adani’s supply.

The injunction comes even as BPDB and Adani continue negotiations over payment disputes. Bangladesh’s interim administration led by Professor Muhammad Yunus has previously accused Adani of breaching the power purchase agreement by withholding tax benefits received for the Godda plant in India. Bangladesh paid Adani 14.87 taka (USD 0.122) per unit in the fiscal year ending 30 June 2024 — well above the 9.57 taka average paid to other Indian suppliers.

Earlier this month, Adani Power said it had opted for international arbitration to resolve disagreements over unpaid dues under the 2017 contract. “There are disagreements in the way certain cost elements are calculated and billed… both partners have agreed to invoke the dispute resolution process,” an Adani spokesperson said.

Bangladesh’s energy adviser, Muhammad Fouzul Kabir Khan, confirmed that negotiations were ongoing and suggested arbitration could still be an option, but the High Court order has temporarily blocked that route. Petitioner Abdul Kaiyum argued that allowing arbitration to proceed before the investigative report is released would undermine the inquiry’s significance.

Adani Power supplies electricity from its 1,600-megawatt coal-fired Godda plant in eastern India, which meets nearly one-tenth of Bangladesh’s total power demand.

Bangladesh’s High Court on Thursday ordered India’s Adani Group to halt its planned international arbitration in Singapore over a payment dispute with the state-run Bangladesh Power Development Board (BPDB). The suspension will remain in place until an investigation into Adani’s power supply agreement is completed. Court officials said a two-judge bench directed that arbitration be paused until a committee appointed by the court submits its findings on the power purchase agreement and any potential irregularities. The order followed a petition seeking judicial intervention to review and scrap the BPDB–Adani deal, which the petitioner described as “one-sided” and signed during the tenure of former prime minister Sheikh Hasina. The petition argued that Adani’s tariff was significantly higher than regional benchmarks — with electricity from Indian state-owned firms priced at 5.5 taka per unit, from other private Indian firms at 8.5 taka, and from Nepal at 8 taka, compared with more than 14 taka per unit for Adani’s supply. The injunction comes even as BPDB and Adani continue negotiations over payment disputes. Bangladesh’s interim administration led by Professor Muhammad Yunus has previously accused Adani of breaching the power purchase agreement by withholding tax benefits received for the Godda plant in India. Bangladesh paid Adani 14.87 taka (USD 0.122) per unit in the fiscal year ending 30 June 2024 — well above the 9.57 taka average paid to other Indian suppliers. Earlier this month, Adani Power said it had opted for international arbitration to resolve disagreements over unpaid dues under the 2017 contract. “There are disagreements in the way certain cost elements are calculated and billed… both partners have agreed to invoke the dispute resolution process,” an Adani spokesperson said. Bangladesh’s energy adviser, Muhammad Fouzul Kabir Khan, confirmed that negotiations were ongoing and suggested arbitration could still be an option, but the High Court order has temporarily blocked that route. Petitioner Abdul Kaiyum argued that allowing arbitration to proceed before the investigative report is released would undermine the inquiry’s significance. Adani Power supplies electricity from its 1,600-megawatt coal-fired Godda plant in eastern India, which meets nearly one-tenth of Bangladesh’s total power demand.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App