Bihar has signed memoranda of understanding with NTPC and Nuclear Power Corporation of India (NPCIL) for two nuclear power projects with a combined investment of Rs. 1.4 tn. The proposals are part of six energy projects valued at Rs. 1.73 tn, which together involve 11,600 MW of generation capacity and 36,078 MWh of energy storage.

Under the agreement with NTPC, a 2,800 MW nuclear power plant will be established at Bhitiya in Banka district. The project involves an investment of Rs. 700 bn, will occupy 1,500 acres and require 160 mn cubic metres of water annually.

NPCIL will develop a second 2,800 MW nuclear power plant at Talhar in Raghunathpur, Siwan district. The project also carries an investment of Rs. 700 bn and will require 1,500 acres of land and 160 mn cubic metres of water each year.

The wider package includes four pumped-storage facilities alongside the nuclear plants. These projects will provide 36,078 MWh of energy storage, allowing electricity to be shifted between periods of lower and higher demand. The combination of firm nuclear generation and storage is intended to support Bihar’s expanding electricity requirements and greater integration of renewable power.

The proposed investments come as the Centre pursues a substantial increase in India’s nuclear capacity over the next two decades. The national target is 100 GW by 2047, compared with installed capacity of about 8.8 GW currently. Each Bihar plant represents an estimated capital requirement of about Rs. 250 mn per MW, although the figure may not reflect the final project cost. The developments could also reduce Bihar’s reliance on electricity sourced from outside the state while supporting future industrial growth.

Bihar has signed memoranda of understanding with NTPC and Nuclear Power Corporation of India (NPCIL) for two nuclear power projects with a combined investment of Rs. 1.4 tn. The proposals are part of six energy projects valued at Rs. 1.73 tn, which together involve 11,600 MW of generation capacity and 36,078 MWh of energy storage. Under the agreement with NTPC, a 2,800 MW nuclear power plant will be established at Bhitiya in Banka district. The project involves an investment of Rs. 700 bn, will occupy 1,500 acres and require 160 mn cubic metres of water annually. NPCIL will develop a second 2,800 MW nuclear power plant at Talhar in Raghunathpur, Siwan district. The project also carries an investment of Rs. 700 bn and will require 1,500 acres of land and 160 mn cubic metres of water each year. The wider package includes four pumped-storage facilities alongside the nuclear plants. These projects will provide 36,078 MWh of energy storage, allowing electricity to be shifted between periods of lower and higher demand. The combination of firm nuclear generation and storage is intended to support Bihar’s expanding electricity requirements and greater integration of renewable power. The proposed investments come as the Centre pursues a substantial increase in India’s nuclear capacity over the next two decades. The national target is 100 GW by 2047, compared with installed capacity of about 8.8 GW currently. Each Bihar plant represents an estimated capital requirement of about Rs. 250 mn per MW, although the figure may not reflect the final project cost. The developments could also reduce Bihar’s reliance on electricity sourced from outside the state while supporting future industrial growth.

Related Stories

Gold Stories

Next Story
Real Estate

WSB Real Estate Partners Exits Six Housing Investments

WSB Real Estate Partners recently announced the successful exit of six residential investments across Bengaluru, Mumbai Metropolitan Region (MMR) and National Capital Region (NCR), delivering an average internal rate of return (IRR) of 19–21 per cent and an overall investment return of 1.4 times.The real estate-focused investment firm invested approximately Rs 7 billion across six mid-affordable housing projects over the past four years. All six investments were fully repaid between April and November 2026, several months ahead of their original investment tenures.WSB collaborated with sever..

Next Story
Infrastructure Transport

Aluminium Industry Seeks Policy Support for Rs 4 Trillion Investment

The Aluminium Association of India (AAI) has recently urged the government to introduce supportive policy measures to safeguard the sector’s proposed Rs 4 trillion investment pipeline. The association highlighted the need for a predictable policy framework to strengthen domestic manufacturing, expand production capacity and reduce import dependence.AAI submitted its recommendations for the Union Budget 2027-28 to the Ministries of Finance, Commerce and Industry, and Mines, along with the Department for Promotion of Industry and Internal Trade (DPIIT).India’s aluminium demand is projected t..

Next Story
Technology

ABB Unveils Intelligent Motor to Accelerate Industrial AI Adoption

ABB recently launched Intelleqt, which it describes as the world’s first low-voltage motor with factory-integrated intelligence, at the SPS trade fair in Germany. Designed to deliver real-time operational insights from its first rotation, the motor enables industrial operators to integrate equipment-level data into existing digital platforms while retaining full ownership of their data.The launch addresses growing challenges in scaling artificial intelligence (AI) across industrial operations, particularly data quality and availability. According to Deloitte, while 84 per cent of manufacture..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code