GERC Grants Interim Relief for Cleanmax’s 10 MW Hybrid Project
POWER & RENEWABLE ENERGY

GERC Grants Interim Relief for Cleanmax’s 10 MW Hybrid Project

The Gujarat Electricity Regulatory Commission (GERC) has granted conditional approval to Cleanmax Vayu Private Limited to begin power generation from part of its 10 megawatt (MW) wind-solar hybrid project in Rajkot district. The order provides interim relief in an ongoing legal dispute between the renewable energy developer and the Gujarat Energy Transmission Corporation Limited (GETCO).
The case centres on the commissioning timeline for the project and the interpretation of the applicable connectivity procedure. Cleanmax Vayu received Stage-II connectivity approval for the project on 31 May 2024, with GETCO stipulating that the entire capacity be commissioned by 31 May 2025.
However, the developer argued that the procedure allows up to two years from the charging of the evacuation system to commission the remaining capacity. By 28 May 2025, the company had completed the evacuation infrastructure and commissioned 6.6 MW, exceeding the minimum 10 per cent requirement within the deadline.
Despite being ready to commission the remaining 3.3 MW, the process was delayed when GETCO declined to sign the Long-Term Open Access (LTOA) agreement, preventing the firm from executing the Wheeling and Banking Agreement with the state’s distribution companies. Cleanmax Vayu said this stranded capacity—worth about Rs 35 crore—was causing financial strain due to rising interest and holding costs.
After reviewing submissions, GERC noted that Cleanmax Vayu had met key requirements and that the refusal to grant LTOA was the main obstacle. The Commission therefore issued an interim order on 3 November 2025, directing GETCO, GEDA, and DGVCL to grant conditional approval for power generation from the remaining 3.3 MW.
This temporary permission will remain effective until the Commission issues a final ruling. Cleanmax Vayu has provided a written undertaking that, if the final verdict goes against it, the energy generated during this period will be treated as inadvertent, with no financial burden on the state utility.
The main petition remains under review, with GERC to issue its final decision after examining further submissions from both parties.

The Gujarat Electricity Regulatory Commission (GERC) has granted conditional approval to Cleanmax Vayu Private Limited to begin power generation from part of its 10 megawatt (MW) wind-solar hybrid project in Rajkot district. The order provides interim relief in an ongoing legal dispute between the renewable energy developer and the Gujarat Energy Transmission Corporation Limited (GETCO).The case centres on the commissioning timeline for the project and the interpretation of the applicable connectivity procedure. Cleanmax Vayu received Stage-II connectivity approval for the project on 31 May 2024, with GETCO stipulating that the entire capacity be commissioned by 31 May 2025.However, the developer argued that the procedure allows up to two years from the charging of the evacuation system to commission the remaining capacity. By 28 May 2025, the company had completed the evacuation infrastructure and commissioned 6.6 MW, exceeding the minimum 10 per cent requirement within the deadline.Despite being ready to commission the remaining 3.3 MW, the process was delayed when GETCO declined to sign the Long-Term Open Access (LTOA) agreement, preventing the firm from executing the Wheeling and Banking Agreement with the state’s distribution companies. Cleanmax Vayu said this stranded capacity—worth about Rs 35 crore—was causing financial strain due to rising interest and holding costs.After reviewing submissions, GERC noted that Cleanmax Vayu had met key requirements and that the refusal to grant LTOA was the main obstacle. The Commission therefore issued an interim order on 3 November 2025, directing GETCO, GEDA, and DGVCL to grant conditional approval for power generation from the remaining 3.3 MW.This temporary permission will remain effective until the Commission issues a final ruling. Cleanmax Vayu has provided a written undertaking that, if the final verdict goes against it, the energy generated during this period will be treated as inadvertent, with no financial burden on the state utility.The main petition remains under review, with GERC to issue its final decision after examining further submissions from both parties.

Next Story
Equipment

Powering India’s Infra Future

Excon 2025, South Asia’s largest construction equipment exhibition, is set to return in a grand 13th edition from 9-13 December 2025 at the Bangalore International Exhibition Centre (BIEC), Bengaluru. Organised by the Confederation of Indian Industry (CII) and supported by the Indian Construction Equipment Manufacturers’ Association (ICEMA), the mega event is expected to reinforce its position as the premier marketplace for construction technologies, equipment and infrastructure solutions. The event will host over 1,250 exhibitors, including 160+ international participants, and attract mor..

Next Story
Infrastructure Urban

India will be a strategic part of our growth to 2028

Smiley Monroe is strengthening its footprint in India as a key growth market for its conveyor belts and engineered components business. In this interaction, Prabhu Gopinath, Operations Director, outlines the company’s expansion roadmap, quality focus, and sustainability commitments driving future scale.Can you share Smiley Monroe's journey and its core mission?Smiley Monroe was started in Northern Ireland in 1979, supplying conveyor belts to local quarries. Since then, the company has grown to become a global leader in the supply of endless belts and CNC-cut rubber and plastic part..

Next Story
Equipment

Infra Engineers India Pvt Ltd Accelerates Hybrid Excavation

Infra Engineers India Pvt Ltd (IEPL), headquartered in Chennai, has emerged as a trusted name in the used construction equipment business for nearly a decade. What sets IEPL apart is its commitment to research and development, consistently pushing the boundaries of innovation to deliver cutting-edge solutions to the industry.A first-of-its-kind hybrid excavatorAmong IEPL’s most significant achievements is the development of the pioneering Dual Electric & Diesel Hybrid Excavator—the first of its kind in the construction equipment industry, a breakthrough that even major OEMs have yet to..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Get CW App