+
GERC Grants Interim Relief for Cleanmax’s 10 MW Hybrid Project
POWER & RENEWABLE ENERGY

GERC Grants Interim Relief for Cleanmax’s 10 MW Hybrid Project

The Gujarat Electricity Regulatory Commission (GERC) has granted conditional approval to Cleanmax Vayu Private Limited to begin power generation from part of its 10 megawatt (MW) wind-solar hybrid project in Rajkot district. The order provides interim relief in an ongoing legal dispute between the renewable energy developer and the Gujarat Energy Transmission Corporation Limited (GETCO).
The case centres on the commissioning timeline for the project and the interpretation of the applicable connectivity procedure. Cleanmax Vayu received Stage-II connectivity approval for the project on 31 May 2024, with GETCO stipulating that the entire capacity be commissioned by 31 May 2025.
However, the developer argued that the procedure allows up to two years from the charging of the evacuation system to commission the remaining capacity. By 28 May 2025, the company had completed the evacuation infrastructure and commissioned 6.6 MW, exceeding the minimum 10 per cent requirement within the deadline.
Despite being ready to commission the remaining 3.3 MW, the process was delayed when GETCO declined to sign the Long-Term Open Access (LTOA) agreement, preventing the firm from executing the Wheeling and Banking Agreement with the state’s distribution companies. Cleanmax Vayu said this stranded capacity—worth about Rs 35 crore—was causing financial strain due to rising interest and holding costs.
After reviewing submissions, GERC noted that Cleanmax Vayu had met key requirements and that the refusal to grant LTOA was the main obstacle. The Commission therefore issued an interim order on 3 November 2025, directing GETCO, GEDA, and DGVCL to grant conditional approval for power generation from the remaining 3.3 MW.
This temporary permission will remain effective until the Commission issues a final ruling. Cleanmax Vayu has provided a written undertaking that, if the final verdict goes against it, the energy generated during this period will be treated as inadvertent, with no financial burden on the state utility.
The main petition remains under review, with GERC to issue its final decision after examining further submissions from both parties.

The Gujarat Electricity Regulatory Commission (GERC) has granted conditional approval to Cleanmax Vayu Private Limited to begin power generation from part of its 10 megawatt (MW) wind-solar hybrid project in Rajkot district. The order provides interim relief in an ongoing legal dispute between the renewable energy developer and the Gujarat Energy Transmission Corporation Limited (GETCO).The case centres on the commissioning timeline for the project and the interpretation of the applicable connectivity procedure. Cleanmax Vayu received Stage-II connectivity approval for the project on 31 May 2024, with GETCO stipulating that the entire capacity be commissioned by 31 May 2025.However, the developer argued that the procedure allows up to two years from the charging of the evacuation system to commission the remaining capacity. By 28 May 2025, the company had completed the evacuation infrastructure and commissioned 6.6 MW, exceeding the minimum 10 per cent requirement within the deadline.Despite being ready to commission the remaining 3.3 MW, the process was delayed when GETCO declined to sign the Long-Term Open Access (LTOA) agreement, preventing the firm from executing the Wheeling and Banking Agreement with the state’s distribution companies. Cleanmax Vayu said this stranded capacity—worth about Rs 35 crore—was causing financial strain due to rising interest and holding costs.After reviewing submissions, GERC noted that Cleanmax Vayu had met key requirements and that the refusal to grant LTOA was the main obstacle. The Commission therefore issued an interim order on 3 November 2025, directing GETCO, GEDA, and DGVCL to grant conditional approval for power generation from the remaining 3.3 MW.This temporary permission will remain effective until the Commission issues a final ruling. Cleanmax Vayu has provided a written undertaking that, if the final verdict goes against it, the energy generated during this period will be treated as inadvertent, with no financial burden on the state utility.The main petition remains under review, with GERC to issue its final decision after examining further submissions from both parties.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App