GERC Grants Interim Relief for Cleanmax’s 10 MW Hybrid Project
POWER & RENEWABLE ENERGY

GERC Grants Interim Relief for Cleanmax’s 10 MW Hybrid Project

The Gujarat Electricity Regulatory Commission (GERC) has granted conditional approval to Cleanmax Vayu Private Limited to begin power generation from part of its 10 megawatt (MW) wind-solar hybrid project in Rajkot district. The order provides interim relief in an ongoing legal dispute between the renewable energy developer and the Gujarat Energy Transmission Corporation Limited (GETCO).
The case centres on the commissioning timeline for the project and the interpretation of the applicable connectivity procedure. Cleanmax Vayu received Stage-II connectivity approval for the project on 31 May 2024, with GETCO stipulating that the entire capacity be commissioned by 31 May 2025.
However, the developer argued that the procedure allows up to two years from the charging of the evacuation system to commission the remaining capacity. By 28 May 2025, the company had completed the evacuation infrastructure and commissioned 6.6 MW, exceeding the minimum 10 per cent requirement within the deadline.
Despite being ready to commission the remaining 3.3 MW, the process was delayed when GETCO declined to sign the Long-Term Open Access (LTOA) agreement, preventing the firm from executing the Wheeling and Banking Agreement with the state’s distribution companies. Cleanmax Vayu said this stranded capacity—worth about Rs 35 crore—was causing financial strain due to rising interest and holding costs.
After reviewing submissions, GERC noted that Cleanmax Vayu had met key requirements and that the refusal to grant LTOA was the main obstacle. The Commission therefore issued an interim order on 3 November 2025, directing GETCO, GEDA, and DGVCL to grant conditional approval for power generation from the remaining 3.3 MW.
This temporary permission will remain effective until the Commission issues a final ruling. Cleanmax Vayu has provided a written undertaking that, if the final verdict goes against it, the energy generated during this period will be treated as inadvertent, with no financial burden on the state utility.
The main petition remains under review, with GERC to issue its final decision after examining further submissions from both parties.

The Gujarat Electricity Regulatory Commission (GERC) has granted conditional approval to Cleanmax Vayu Private Limited to begin power generation from part of its 10 megawatt (MW) wind-solar hybrid project in Rajkot district. The order provides interim relief in an ongoing legal dispute between the renewable energy developer and the Gujarat Energy Transmission Corporation Limited (GETCO).The case centres on the commissioning timeline for the project and the interpretation of the applicable connectivity procedure. Cleanmax Vayu received Stage-II connectivity approval for the project on 31 May 2024, with GETCO stipulating that the entire capacity be commissioned by 31 May 2025.However, the developer argued that the procedure allows up to two years from the charging of the evacuation system to commission the remaining capacity. By 28 May 2025, the company had completed the evacuation infrastructure and commissioned 6.6 MW, exceeding the minimum 10 per cent requirement within the deadline.Despite being ready to commission the remaining 3.3 MW, the process was delayed when GETCO declined to sign the Long-Term Open Access (LTOA) agreement, preventing the firm from executing the Wheeling and Banking Agreement with the state’s distribution companies. Cleanmax Vayu said this stranded capacity—worth about Rs 35 crore—was causing financial strain due to rising interest and holding costs.After reviewing submissions, GERC noted that Cleanmax Vayu had met key requirements and that the refusal to grant LTOA was the main obstacle. The Commission therefore issued an interim order on 3 November 2025, directing GETCO, GEDA, and DGVCL to grant conditional approval for power generation from the remaining 3.3 MW.This temporary permission will remain effective until the Commission issues a final ruling. Cleanmax Vayu has provided a written undertaking that, if the final verdict goes against it, the energy generated during this period will be treated as inadvertent, with no financial burden on the state utility.The main petition remains under review, with GERC to issue its final decision after examining further submissions from both parties.

Next Story
Infrastructure Urban

VECV Sales Rise 7.8 Per Cent In May 2026

VE Commercial Vehicles recorded sales of 7,978 units in May 2026, compared to 7,401 units in May 2025, registering growth of 7.8 per cent. This included 7,789 units from the Eicher brand and 189 units from the Volvo brand.Eicher branded trucks and buses reported sales of 7,789 units during the month, up 7.3 per cent from 7,258 units a year earlier. In the domestic commercial vehicle market, Eicher sales rose 9.1 per cent to 7,375 units from 6,758 units in May 2025.Exports declined 17.2 per cent to 414 units from 500 units in the corresponding month last year. Volvo Trucks and Volvo Buses recor..

Next Story
Infrastructure Urban

Table Space Strengthens DESYN Leadership Team

Table Space has announced strategic leadership appointments within DESYN, its integrated Design and Build business, as it looks to strengthen operations across key enterprise and GCC markets in India. DESYN was launched as a strategic extension of Table Space’s workspace solutions portfolio to meet rising demand for agile, high-quality and rapidly deployable enterprise workspaces.Shruti Ookabhoy has joined DESYN as Executive Director and will lead the Design vertical, focusing on design capability, operational excellence and team development across markets. She brings over 22 years of experi..

Next Story
Infrastructure Transport

Concord Associate Bags Rs 2.79 Bn Kavach Order

Concord Control Systems said its associate company, Progota India, has received a Rs 2.79 bn domestic order from Indian Railways for the supply, installation, testing and commissioning of on-board Kavach 4.0 loco equipment.The order is scheduled for execution within 12 months and strengthens Concord’s role in India’s railway safety and signalling ecosystem. Kavach is India’s indigenous automatic train protection system, designed to improve operational safety by helping prevent signal passing at danger and reducing collision risks.Gaurav Lath, Joint Managing Director, Concord Control Syst..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement