GERC Grants Interim Relief for Cleanmax’s 10 MW Hybrid Project
POWER & RENEWABLE ENERGY

GERC Grants Interim Relief for Cleanmax’s 10 MW Hybrid Project

The Gujarat Electricity Regulatory Commission (GERC) has granted conditional approval to Cleanmax Vayu Private Limited to begin power generation from part of its 10 megawatt (MW) wind-solar hybrid project in Rajkot district. The order provides interim relief in an ongoing legal dispute between the renewable energy developer and the Gujarat Energy Transmission Corporation Limited (GETCO).
The case centres on the commissioning timeline for the project and the interpretation of the applicable connectivity procedure. Cleanmax Vayu received Stage-II connectivity approval for the project on 31 May 2024, with GETCO stipulating that the entire capacity be commissioned by 31 May 2025.
However, the developer argued that the procedure allows up to two years from the charging of the evacuation system to commission the remaining capacity. By 28 May 2025, the company had completed the evacuation infrastructure and commissioned 6.6 MW, exceeding the minimum 10 per cent requirement within the deadline.
Despite being ready to commission the remaining 3.3 MW, the process was delayed when GETCO declined to sign the Long-Term Open Access (LTOA) agreement, preventing the firm from executing the Wheeling and Banking Agreement with the state’s distribution companies. Cleanmax Vayu said this stranded capacity—worth about Rs 35 crore—was causing financial strain due to rising interest and holding costs.
After reviewing submissions, GERC noted that Cleanmax Vayu had met key requirements and that the refusal to grant LTOA was the main obstacle. The Commission therefore issued an interim order on 3 November 2025, directing GETCO, GEDA, and DGVCL to grant conditional approval for power generation from the remaining 3.3 MW.
This temporary permission will remain effective until the Commission issues a final ruling. Cleanmax Vayu has provided a written undertaking that, if the final verdict goes against it, the energy generated during this period will be treated as inadvertent, with no financial burden on the state utility.
The main petition remains under review, with GERC to issue its final decision after examining further submissions from both parties.

The Gujarat Electricity Regulatory Commission (GERC) has granted conditional approval to Cleanmax Vayu Private Limited to begin power generation from part of its 10 megawatt (MW) wind-solar hybrid project in Rajkot district. The order provides interim relief in an ongoing legal dispute between the renewable energy developer and the Gujarat Energy Transmission Corporation Limited (GETCO).The case centres on the commissioning timeline for the project and the interpretation of the applicable connectivity procedure. Cleanmax Vayu received Stage-II connectivity approval for the project on 31 May 2024, with GETCO stipulating that the entire capacity be commissioned by 31 May 2025.However, the developer argued that the procedure allows up to two years from the charging of the evacuation system to commission the remaining capacity. By 28 May 2025, the company had completed the evacuation infrastructure and commissioned 6.6 MW, exceeding the minimum 10 per cent requirement within the deadline.Despite being ready to commission the remaining 3.3 MW, the process was delayed when GETCO declined to sign the Long-Term Open Access (LTOA) agreement, preventing the firm from executing the Wheeling and Banking Agreement with the state’s distribution companies. Cleanmax Vayu said this stranded capacity—worth about Rs 35 crore—was causing financial strain due to rising interest and holding costs.After reviewing submissions, GERC noted that Cleanmax Vayu had met key requirements and that the refusal to grant LTOA was the main obstacle. The Commission therefore issued an interim order on 3 November 2025, directing GETCO, GEDA, and DGVCL to grant conditional approval for power generation from the remaining 3.3 MW.This temporary permission will remain effective until the Commission issues a final ruling. Cleanmax Vayu has provided a written undertaking that, if the final verdict goes against it, the energy generated during this period will be treated as inadvertent, with no financial burden on the state utility.The main petition remains under review, with GERC to issue its final decision after examining further submissions from both parties.

Next Story
Infrastructure Transport

Surya Roshni delivers customised lighting for NCRTC RRTS stations

Surya Roshni has supplied customised indoor lighting solutions for 18 elevated stations on the National Capital Region Transport Corporation's (NCRTC) Rapid Rail Transit System (RRTS), strengthening its presence in India's infrastructure lighting segment.The project involved the design and deployment of lighting systems for platforms, concourses, foot overbridges (FOBs) and back-of-house (BOH) areas. According to the company, the luminaires were developed specifically to meet NCRTC's design, operational and performance requirements rather than using standard products.Surya introduced two custo..

Next Story
Real Estate

Hilton debuts Tapestry Collection brand in Vietnam

Hilton has opened NHAAN Resort & Spa Hoi An, Tapestry Collection by Hilton, marking the debut of the Tapestry Collection brand in Vietnam and expanding its lifestyle hospitality portfolio in Southeast Asia.Located along the Co Co River in Cam Thanh village, the 174-key resort provides access to Hoi An Ancient Town, Cua Dai Beach and the Cam Thanh Nipa Forest. The property has been designed by Vietnamese architect Vo Trong Nghia, incorporating biophilic architecture, locally sourced materials and riverfront landscapes.The resort offers a mix of guest rooms and suites, including family-frien..

Next Story
Building Material

Electrent expands lithium energy storage system portfolio

Electrent Energy has expanded its lithium-based energy storage portfolio with the launch of the ESS 850 and ESS 1050, targeting compact and maintenance-free power backup solutions for Indian homes.The new systems integrate a Home UPS and a LiFePO4 lithium battery into a single unit, extending the company's product range following the launch of its ESS 1350 and ESS 2500 models.Designed for apartments and smaller homes, the ESS 850 provides up to 1 hour 15 minutes of backup, while the ESS 1050 offers up to 1 hour 45 minutes on a typical 400 W household load. The systems can power essential appli..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement