+
Dealing with Delays
Real Estate

Dealing with Delays

Delays have beleaguered many a construction project in India, hampering the country from building to its ability and potential, and leading to additional costs incurred by the contractor. The reasons for delayIn India, delays mainly occur owing to obtaini...

Delays have beleaguered many a construction project in India, hampering the country from building to its ability and potential, and leading to additional costs incurred by the contractor. The reasons for delayIn India, delays mainly occur owing to obtaining statutory approvals, non-provisioning of right of way, utility diversion and approval of drawings and design. Delays are broadly classified based on responsibility and effect. Excusable delays arise from factors beyond the contractor’s control, such as force majeure events or employer-induced delays. These delays generally entitle the contractor to an extension of time (EoT); and in some cases, EOT costs, if there were no concurrent delays on account of the contractor. Conversely, non-excusable delays such as lack of resource mobilisation by the contractor lead to imposition of liquidated damages.Concurrent delays involve causes attributable to both the employer and contractor, necessitating forensic analysis to determine entitlements based on contractual terms. In National Highways Authority of India v. Sayedabad Tea Co. Pvt Ltd, (2019) SCC Online SC 1102, the Supreme Court of India discussed the role of expert witnesses in construction arbitration concerning delay analysis. The court emphasised the importance of expert evidence in assessing delays, analysing causation and determining liability in construction disputes. In Union of India v. Simplex Infrastructure Ltd, AIR 2017 Supreme Court 2119, the Apex Court emphasised the significance of expert evidence in construction disputes.Claim entitlements and legal considerationsVarious claims arise from construction delays, with their entitlements determined by the nature and impact of the delay. Principle 20 of the SCL Protocol (2nd edition) states: “The objective of a compensatory regime is to put the Contractor in the same financial position it would have been if the Employer Risk Event had not occurred.” Courts have also established some key principles regarding the burden of proof in delay claims. In Walter Lilly & Co. Ltd. v. Giles Patrick Cyril Mackay, [2012] EWHC 1773 (TCC), the court held that damages must be proven on the balance of probabilities under English law. In the US, in Florafax Intern, Inc v. GTE Market Resources, 22 Ill.1997 OK 7, 933 P.2d 282, it was held that delay claims required proof by a preponderance of evidence. In Bhagheeratha Engineering Ltd. v. NHAI, O.M.P. (COMM) 85/2019 and 88/2019, the Delhi High Court upheld the award of overhead expenses, relying on the MoRTH Standard Data Book and Chartered Accountant certificates. In NHAI v. Oriental Structures Engineers Pvt Ltd - Gammon India Ltd (JV), AIR 2013 Delhi 67, the court held that award of the additional cost towards machinery and overheads in the extended period is perfectly valid in terms of the contractual provisions when the delay has been found to be on the part of the employer. The Supreme Court has ruled that loss of profit is compensable once a breach is established, without requiring strict proof of actual loss ((i) A.T. Brij Paul Singh v. State of Gujarat, AIR 1984 SC 1703 (ii) Dwaraka Das v. State of M.P., 1999 (3) SCC 500). Whereas, in Unibros v. All India Radio & Anr, 2023 SCC Online SC 1366, and Batliboi Environmental Engineers Ltd v. HPCL-Mittal Energy Ltd, 2023 SCC Online SC 1208, the Supreme Court held that loss of profit claims require clear proof of delay not attributable to the contractor, lost opportunities and financial impact.In J G Engineers Pvt Ltd v. UOI, AIR 2011 SC 2477, the court duly examined the issue whether the contractor would be entitled to price escalation despite being it conditional in the terms of the contract for the extended period of contract, wherein the delay was attributable to the employer. The court reiterated the arbitrator’s view and held the contractor was not responsible for the delay and the price escalation automatically becomes payable.Disruption claims address productivity losses caused by employer-driven factors such as late approval of drawings or site constraints. The measured mile method is employed to calculate disruption claims.Acceleration claims arise when a contractor is required to expedite work due to the employer’s instruction (directed acceleration) or refusal to grant an EoT (constructive acceleration). Acceleration costs include additional labour, equipment and material procurement, assessed using the extra resource cost method.Apart from the above, costs of maintenance of bank guarantee and insurance policies during the EoT and financing charges form part of the EoT claims. Coming up!In upcoming months, a series of articles on delay analysis methods, calculation of overhead costs, idling claims, loss of profit, loss of productivity, disruption claim, acceleration claims and interest costs will be covered in detail with relevant judicial pronouncements. About the author: Ronak Desai is a construction lawyer and heads International Construction Law Offices, Mumbai. Email: rd@constructionlawoffices.com

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App