+
Noida to Open HQ and Bhangel Flyover in Two Months
Real Estate

Noida to Open HQ and Bhangel Flyover in Two Months

The Noida Authority has announced plans to inaugurate its new administrative headquarters in Sector 96 and the Bhangel Elevated Road within the next two months. Both projects have faced repeated delays and budget overruns over the years.

“We have decided to open both projects within the next two months as they are now in the final stages. Staff have been instructed to accelerate the work to meet the revised timeline,” said Lokesh M, Chief Executive Officer of the Noida Authority.

The six-lane, 5.5-kilometre Bhangel Elevated Road has been constructed above the Dadri-Surajpur-Chhalera (DSC) road. Once operational, it will improve connectivity between Noida and Greater Noida, providing a direct link from Agahpur to the Noida Special Economic Zone (NSEZ) in Sector 82. The elevated corridor bypasses high-traffic areas such as Chhalera, Barola, and Bhangel markets, promising to reduce travel times for commuters.

Approved in 2013, the project was launched in June 2020 with an initial budget of Rs 4.68 billion. Due to structural changes and delays, the cost has risen to Rs 6.08 billion. Installation of nine 60-metre steel girders near Barola Crossing is expected to finish this week, followed by deck slab work over the next month. Traffic diversions were implemented last month to allow uninterrupted construction at Barola.

The project has missed several completion deadlines — originally December 2022, then December 2023, and later 31 December 2024 — largely due to a 90-metre bottleneck caused by two obstructing buildings requiring structural redesign.

Meanwhile, the Authority's new headquarters in Sector 96 is also nearing completion. Spread over six acres, the twin-tower complex was conceived in 2009 and construction began in 2015 with a budget of Rs 4.78 billion. However, following poor construction quality and a delay of over 450 days, the initial contractor was blacklisted in 2022. A new firm was hired after IIT Delhi’s 2023 structural audit identified flaws, including incorrect pillar placements. Corrective measures were undertaken, and the revised budget now stands at Rs 3.04 billion.

With both major developments now entering their final phase, the Authority aims to deliver long-pending civic upgrades to improve administrative efficiency and urban mobility in Noida.

The Noida Authority has announced plans to inaugurate its new administrative headquarters in Sector 96 and the Bhangel Elevated Road within the next two months. Both projects have faced repeated delays and budget overruns over the years.“We have decided to open both projects within the next two months as they are now in the final stages. Staff have been instructed to accelerate the work to meet the revised timeline,” said Lokesh M, Chief Executive Officer of the Noida Authority.The six-lane, 5.5-kilometre Bhangel Elevated Road has been constructed above the Dadri-Surajpur-Chhalera (DSC) road. Once operational, it will improve connectivity between Noida and Greater Noida, providing a direct link from Agahpur to the Noida Special Economic Zone (NSEZ) in Sector 82. The elevated corridor bypasses high-traffic areas such as Chhalera, Barola, and Bhangel markets, promising to reduce travel times for commuters.Approved in 2013, the project was launched in June 2020 with an initial budget of Rs 4.68 billion. Due to structural changes and delays, the cost has risen to Rs 6.08 billion. Installation of nine 60-metre steel girders near Barola Crossing is expected to finish this week, followed by deck slab work over the next month. Traffic diversions were implemented last month to allow uninterrupted construction at Barola.The project has missed several completion deadlines — originally December 2022, then December 2023, and later 31 December 2024 — largely due to a 90-metre bottleneck caused by two obstructing buildings requiring structural redesign.Meanwhile, the Authority's new headquarters in Sector 96 is also nearing completion. Spread over six acres, the twin-tower complex was conceived in 2009 and construction began in 2015 with a budget of Rs 4.78 billion. However, following poor construction quality and a delay of over 450 days, the initial contractor was blacklisted in 2022. A new firm was hired after IIT Delhi’s 2023 structural audit identified flaws, including incorrect pillar placements. Corrective measures were undertaken, and the revised budget now stands at Rs 3.04 billion.With both major developments now entering their final phase, the Authority aims to deliver long-pending civic upgrades to improve administrative efficiency and urban mobility in Noida.

Next Story
Infrastructure Transport

Rs 19.5 Billion Meerut–Nazibabad Rail Electrification Complete

The Rs 19.5 billion railway electrification of the Meerut–Nazibabad section has been completed, marking a major step towards improving connectivity in northern India. The project covers 132 kilometres of track and is expected to enhance operational efficiency while reducing travel time and fuel costs.Officials from the Ministry of Railways said the electrification will enable faster, more reliable train services and contribute to reduced carbon emissions. The initiative aligns with the government’s broader goal of achieving 100 per cent electrification of India’s railway network by 2030...

Next Story
Infrastructure Urban

AU Small Finance Bank Secures RBI Approval For Universal Bank

AU Small Finance Bank has received approval from the Reserve Bank of India (RBI) to transition into a universal bank. The move will allow the Jaipur-based lender to expand its range of financial services and compete directly with larger commercial banks.Founded in 1996 as a non-banking finance company, AU Small Finance Bank became a small finance bank in 2017. The transition to a universal bank will enable it to offer a broader portfolio, including enhanced corporate banking, treasury operations, and new retail products.Managing Director and CEO Sanjay Agarwal said the approval marks a signifi..

Next Story
Building Material

India Cements Q1 Loss Narrows To Rs 276 Million On Higher Sales

India Cements Ltd has reported a consolidated net loss of Rs 276 million for the quarter ended June 2025, narrowing from a loss of Rs 831 million a year earlier. Consolidated revenue from operations rose 20 per cent year-on-year to Rs 17.9 billion from Rs 14.9 billion.The company attributed the improvement to higher sales volumes and better price realisations, which offset some of the impact of elevated fuel and raw material costs. EBITDA turned positive at Rs 1.1 billion, compared with a loss in the same period last year.Vice Chairman and Managing Director N. Srinivasan said the company will ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?