+
Noida to Open HQ and Bhangel Flyover in Two Months
Real Estate

Noida to Open HQ and Bhangel Flyover in Two Months

The Noida Authority has announced plans to inaugurate its new administrative headquarters in Sector 96 and the Bhangel Elevated Road within the next two months. Both projects have faced repeated delays and budget overruns over the years.

“We have decided to open both projects within the next two months as they are now in the final stages. Staff have been instructed to accelerate the work to meet the revised timeline,” said Lokesh M, Chief Executive Officer of the Noida Authority.

The six-lane, 5.5-kilometre Bhangel Elevated Road has been constructed above the Dadri-Surajpur-Chhalera (DSC) road. Once operational, it will improve connectivity between Noida and Greater Noida, providing a direct link from Agahpur to the Noida Special Economic Zone (NSEZ) in Sector 82. The elevated corridor bypasses high-traffic areas such as Chhalera, Barola, and Bhangel markets, promising to reduce travel times for commuters.

Approved in 2013, the project was launched in June 2020 with an initial budget of Rs 4.68 billion. Due to structural changes and delays, the cost has risen to Rs 6.08 billion. Installation of nine 60-metre steel girders near Barola Crossing is expected to finish this week, followed by deck slab work over the next month. Traffic diversions were implemented last month to allow uninterrupted construction at Barola.

The project has missed several completion deadlines — originally December 2022, then December 2023, and later 31 December 2024 — largely due to a 90-metre bottleneck caused by two obstructing buildings requiring structural redesign.

Meanwhile, the Authority's new headquarters in Sector 96 is also nearing completion. Spread over six acres, the twin-tower complex was conceived in 2009 and construction began in 2015 with a budget of Rs 4.78 billion. However, following poor construction quality and a delay of over 450 days, the initial contractor was blacklisted in 2022. A new firm was hired after IIT Delhi’s 2023 structural audit identified flaws, including incorrect pillar placements. Corrective measures were undertaken, and the revised budget now stands at Rs 3.04 billion.

With both major developments now entering their final phase, the Authority aims to deliver long-pending civic upgrades to improve administrative efficiency and urban mobility in Noida.

The Noida Authority has announced plans to inaugurate its new administrative headquarters in Sector 96 and the Bhangel Elevated Road within the next two months. Both projects have faced repeated delays and budget overruns over the years.“We have decided to open both projects within the next two months as they are now in the final stages. Staff have been instructed to accelerate the work to meet the revised timeline,” said Lokesh M, Chief Executive Officer of the Noida Authority.The six-lane, 5.5-kilometre Bhangel Elevated Road has been constructed above the Dadri-Surajpur-Chhalera (DSC) road. Once operational, it will improve connectivity between Noida and Greater Noida, providing a direct link from Agahpur to the Noida Special Economic Zone (NSEZ) in Sector 82. The elevated corridor bypasses high-traffic areas such as Chhalera, Barola, and Bhangel markets, promising to reduce travel times for commuters.Approved in 2013, the project was launched in June 2020 with an initial budget of Rs 4.68 billion. Due to structural changes and delays, the cost has risen to Rs 6.08 billion. Installation of nine 60-metre steel girders near Barola Crossing is expected to finish this week, followed by deck slab work over the next month. Traffic diversions were implemented last month to allow uninterrupted construction at Barola.The project has missed several completion deadlines — originally December 2022, then December 2023, and later 31 December 2024 — largely due to a 90-metre bottleneck caused by two obstructing buildings requiring structural redesign.Meanwhile, the Authority's new headquarters in Sector 96 is also nearing completion. Spread over six acres, the twin-tower complex was conceived in 2009 and construction began in 2015 with a budget of Rs 4.78 billion. However, following poor construction quality and a delay of over 450 days, the initial contractor was blacklisted in 2022. A new firm was hired after IIT Delhi’s 2023 structural audit identified flaws, including incorrect pillar placements. Corrective measures were undertaken, and the revised budget now stands at Rs 3.04 billion.With both major developments now entering their final phase, the Authority aims to deliver long-pending civic upgrades to improve administrative efficiency and urban mobility in Noida.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App