BMC Seeks 216-Day Extension For Mulund Biomining Contract
ECONOMY & POLICY

BMC Seeks 216-Day Extension For Mulund Biomining Contract

The BMC administration has submitted a proposal to the Standing Committee seeking a 216-day extension of the Mulund dumping ground biomining and remediation contract, which would keep the agreement with M/s Bio Mining India Pvt Ltd in force until 19 April 2027. The request follows a contour survey and site assessment that identified an additional 0.7 million (mn) tonnes (t) of legacy waste requiring processing. The contractor had already completed seven mn t under the original scope.

At the existing contractual rate of Rs 798 per t the civic body estimates processing the additional waste will cost approximately Rs 558.6 mn. The original six-year contract, approved in June 2018, had been extended owing to disruptions caused by the Covid-19 pandemic, cyclones, heavy rainfall and fuel shortages and the tenure was last set to end on 27 May 2026. The administration argued that floating a fresh tender would delay work and increase expenditure.

Project management consultant May Mitcon Consultancy and Engineering Services Ltd assessed the site and stated the additional quantity can be processed using the contractor's existing machinery, manpower and infrastructure and described continuation as economically beneficial and in the public interest. A technical assessment by KPMG Advisory Services Pvt Ltd estimated the contractor's average productivity at 3,240 t per day. That rate implies roughly 216 days would be required to finish the extra material.

The proposal therefore seeks to extend an already extended contract and to award additional work worth Rs 558.6 mn to the incumbent without a fresh competitive process. The civic administration maintained that the existing rate is more economical than prevailing market rates for comparable work. The Standing Committee will consider the submission before making a decision.

The BMC administration has submitted a proposal to the Standing Committee seeking a 216-day extension of the Mulund dumping ground biomining and remediation contract, which would keep the agreement with M/s Bio Mining India Pvt Ltd in force until 19 April 2027. The request follows a contour survey and site assessment that identified an additional 0.7 million (mn) tonnes (t) of legacy waste requiring processing. The contractor had already completed seven mn t under the original scope. At the existing contractual rate of Rs 798 per t the civic body estimates processing the additional waste will cost approximately Rs 558.6 mn. The original six-year contract, approved in June 2018, had been extended owing to disruptions caused by the Covid-19 pandemic, cyclones, heavy rainfall and fuel shortages and the tenure was last set to end on 27 May 2026. The administration argued that floating a fresh tender would delay work and increase expenditure. Project management consultant May Mitcon Consultancy and Engineering Services Ltd assessed the site and stated the additional quantity can be processed using the contractor's existing machinery, manpower and infrastructure and described continuation as economically beneficial and in the public interest. A technical assessment by KPMG Advisory Services Pvt Ltd estimated the contractor's average productivity at 3,240 t per day. That rate implies roughly 216 days would be required to finish the extra material. The proposal therefore seeks to extend an already extended contract and to award additional work worth Rs 558.6 mn to the incumbent without a fresh competitive process. The civic administration maintained that the existing rate is more economical than prevailing market rates for comparable work. The Standing Committee will consider the submission before making a decision.

Related Stories

Gold Stories

Next Story
Real Estate

LML Realty Sells Out Jhirka Valley Industrial Park in Haryana

LML Realty, the real estate arm of LML Group, recently announced the complete sell-out of its Jhirka Valley Industrial Park in Haryana, with over 1.17 million sq ft of industrial space acquired by more than 50 companies. With utilities and internal infrastructure in place, the company has commenced plot handovers, enabling buyers to begin construction and establish their operations.The industrial park has attracted companies across diverse sectors, including chemicals, metals and alloys, textiles, electrical equipment, energy, logistics, construction, polymers and engineering. Key buyers inclu..

Next Story
Real Estate

WSB Real Estate Partners Exits Six Housing Investments

WSB Real Estate Partners recently announced the successful exit of six residential investments across Bengaluru, Mumbai Metropolitan Region (MMR) and National Capital Region (NCR), delivering an average internal rate of return (IRR) of 19–21 per cent and an overall investment return of 1.4 times.The real estate-focused investment firm invested approximately Rs 7 billion across six mid-affordable housing projects over the past four years. All six investments were fully repaid between April and November 2026, several months ahead of their original investment tenures.WSB collaborated with sever..

Next Story
Infrastructure Transport

Aluminium Industry Seeks Policy Support for Rs 4 Trillion Investment

The Aluminium Association of India (AAI) has recently urged the government to introduce supportive policy measures to safeguard the sector’s proposed Rs 4 trillion investment pipeline. The association highlighted the need for a predictable policy framework to strengthen domestic manufacturing, expand production capacity and reduce import dependence.AAI submitted its recommendations for the Union Budget 2027-28 to the Ministries of Finance, Commerce and Industry, and Mines, along with the Department for Promotion of Industry and Internal Trade (DPIIT).India’s aluminium demand is projected t..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code