BMC Seeks 216-Day Extension For Mulund Biomining Contract
ECONOMY & POLICY

BMC Seeks 216-Day Extension For Mulund Biomining Contract

The BMC administration has submitted a proposal to the Standing Committee seeking a 216-day extension of the Mulund dumping ground biomining and remediation contract, which would keep the agreement with M/s Bio Mining India Pvt Ltd in force until 19 April 2027. The request follows a contour survey and site assessment that identified an additional 0.7 million (mn) tonnes (t) of legacy waste requiring processing. The contractor had already completed seven mn t under the original scope.

At the existing contractual rate of Rs 798 per t the civic body estimates processing the additional waste will cost approximately Rs 558.6 mn. The original six-year contract, approved in June 2018, had been extended owing to disruptions caused by the Covid-19 pandemic, cyclones, heavy rainfall and fuel shortages and the tenure was last set to end on 27 May 2026. The administration argued that floating a fresh tender would delay work and increase expenditure.

Project management consultant May Mitcon Consultancy and Engineering Services Ltd assessed the site and stated the additional quantity can be processed using the contractor's existing machinery, manpower and infrastructure and described continuation as economically beneficial and in the public interest. A technical assessment by KPMG Advisory Services Pvt Ltd estimated the contractor's average productivity at 3,240 t per day. That rate implies roughly 216 days would be required to finish the extra material.

The proposal therefore seeks to extend an already extended contract and to award additional work worth Rs 558.6 mn to the incumbent without a fresh competitive process. The civic administration maintained that the existing rate is more economical than prevailing market rates for comparable work. The Standing Committee will consider the submission before making a decision.

The BMC administration has submitted a proposal to the Standing Committee seeking a 216-day extension of the Mulund dumping ground biomining and remediation contract, which would keep the agreement with M/s Bio Mining India Pvt Ltd in force until 19 April 2027. The request follows a contour survey and site assessment that identified an additional 0.7 million (mn) tonnes (t) of legacy waste requiring processing. The contractor had already completed seven mn t under the original scope. At the existing contractual rate of Rs 798 per t the civic body estimates processing the additional waste will cost approximately Rs 558.6 mn. The original six-year contract, approved in June 2018, had been extended owing to disruptions caused by the Covid-19 pandemic, cyclones, heavy rainfall and fuel shortages and the tenure was last set to end on 27 May 2026. The administration argued that floating a fresh tender would delay work and increase expenditure. Project management consultant May Mitcon Consultancy and Engineering Services Ltd assessed the site and stated the additional quantity can be processed using the contractor's existing machinery, manpower and infrastructure and described continuation as economically beneficial and in the public interest. A technical assessment by KPMG Advisory Services Pvt Ltd estimated the contractor's average productivity at 3,240 t per day. That rate implies roughly 216 days would be required to finish the extra material. The proposal therefore seeks to extend an already extended contract and to award additional work worth Rs 558.6 mn to the incumbent without a fresh competitive process. The civic administration maintained that the existing rate is more economical than prevailing market rates for comparable work. The Standing Committee will consider the submission before making a decision.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Madhya Pradesh Plans Airport Every 150 Km, Airstrip Every 75 Km

The Madhya Pradesh government plans to establish an airport every 150 km, an airstrip every 75 km and a helipad every 45 km, according to the state aviation department. Airports being developed in Ujjain and Shivpuri are expected to take the state’s airport count to 10. The government stated that Madhya Pradesh currently has eight airports in eight cities. The locations named by the department include Indore, Bhopal, Jabalpur, Gwalior, Khajuraho, Rewa and Satna. The state also has more than 20 airstrips and 220 helipads, while permanent helipads are planned in all 230 Assembly constituencies..

Next Story
Infrastructure Transport

West Bengal Plans Four Airports for 2028 Completion Under UDAN

West Bengal will develop four new airports under an agreement signed between the Union Civil Aviation Ministry and the state government, with all facilities targeted for completion by 2028. Union Civil Aviation Minister K Rammohan Naidu said the airports would be located at Charra in Purulia, Kalaikunda in Paschim Medinipur, Balurghat in Dakshin Dinajpur and Hasimara in Alipurduar. The project is part of the Centre’s regional connectivity UDAN programme. The Union government has committed Rs. 290 bn for West Bengal’s aviation sector over the next decade, while the state government will pro..

Next Story
Infrastructure Transport

Mumbai Airport Bars Russian Airlines as Agent Seeks Ministry Intervention

Mumbai airport has stopped accepting cargo booked on Russian flag carrier Aeroflot, disrupting shipments and prompting the airline’s cargo sales agent, Delmos Aviation, to seek intervention from the Ministry of Civil Aviation. The restrictions also affect cargo booked on Volga-Dnepr Airlines, according to a letter submitted by Delmos Aviation to the ministry on September 30. Aeroflot operates daily flights between Moscow and Delhi and runs a winter seasonal service to Goa. Bonded cargo from Mumbai and other cities is transported by road to Delhi before being flown to Russia. The agent said t..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code