BMC Seeks 216-Day Extension For Mulund Biomining Contract
ECONOMY & POLICY

BMC Seeks 216-Day Extension For Mulund Biomining Contract

The BMC administration has submitted a proposal to the Standing Committee seeking a 216-day extension of the Mulund dumping ground biomining and remediation contract, which would keep the agreement with M/s Bio Mining India Pvt Ltd in force until 19 April 2027. The request follows a contour survey and site assessment that identified an additional 0.7 million (mn) tonnes (t) of legacy waste requiring processing. The contractor had already completed seven mn t under the original scope.

At the existing contractual rate of Rs 798 per t the civic body estimates processing the additional waste will cost approximately Rs 558.6 mn. The original six-year contract, approved in June 2018, had been extended owing to disruptions caused by the Covid-19 pandemic, cyclones, heavy rainfall and fuel shortages and the tenure was last set to end on 27 May 2026. The administration argued that floating a fresh tender would delay work and increase expenditure.

Project management consultant May Mitcon Consultancy and Engineering Services Ltd assessed the site and stated the additional quantity can be processed using the contractor's existing machinery, manpower and infrastructure and described continuation as economically beneficial and in the public interest. A technical assessment by KPMG Advisory Services Pvt Ltd estimated the contractor's average productivity at 3,240 t per day. That rate implies roughly 216 days would be required to finish the extra material.

The proposal therefore seeks to extend an already extended contract and to award additional work worth Rs 558.6 mn to the incumbent without a fresh competitive process. The civic administration maintained that the existing rate is more economical than prevailing market rates for comparable work. The Standing Committee will consider the submission before making a decision.

The BMC administration has submitted a proposal to the Standing Committee seeking a 216-day extension of the Mulund dumping ground biomining and remediation contract, which would keep the agreement with M/s Bio Mining India Pvt Ltd in force until 19 April 2027. The request follows a contour survey and site assessment that identified an additional 0.7 million (mn) tonnes (t) of legacy waste requiring processing. The contractor had already completed seven mn t under the original scope. At the existing contractual rate of Rs 798 per t the civic body estimates processing the additional waste will cost approximately Rs 558.6 mn. The original six-year contract, approved in June 2018, had been extended owing to disruptions caused by the Covid-19 pandemic, cyclones, heavy rainfall and fuel shortages and the tenure was last set to end on 27 May 2026. The administration argued that floating a fresh tender would delay work and increase expenditure. Project management consultant May Mitcon Consultancy and Engineering Services Ltd assessed the site and stated the additional quantity can be processed using the contractor's existing machinery, manpower and infrastructure and described continuation as economically beneficial and in the public interest. A technical assessment by KPMG Advisory Services Pvt Ltd estimated the contractor's average productivity at 3,240 t per day. That rate implies roughly 216 days would be required to finish the extra material. The proposal therefore seeks to extend an already extended contract and to award additional work worth Rs 558.6 mn to the incumbent without a fresh competitive process. The civic administration maintained that the existing rate is more economical than prevailing market rates for comparable work. The Standing Committee will consider the submission before making a decision.

Related Stories

Gold Stories

Next Story
Real Estate

BMC OC Amnesty Scheme Requires Key Approvals from Mumbai Societies

The Brihanmumbai Municipal Corporation (BMC) has clarified that housing societies applying under its Occupation Certificate (OC) amnesty scheme must possess key approvals linked to the original construction. The requirements include a valid Intimation of Disapproval (IOD), an approved building plan and a Commencement Certificate (CC), along with a No Objection Certificate (NOC) from the developer or original construction applicant. The Standard Operating Procedure (SOP) makes clear that the absence of an OC alone will not qualify a building for relief. Societies must establish that their build..

Next Story
Real Estate

Gurugram Emerges as Luxury Senior Living Hub

Gurugram is emerging as a potential hub for luxury senior living, supported by available land, healthcare infrastructure, connectivity and a concentration of affluent professionals, high-net-worth individuals and non-resident Indians. These factors could give the city an advantage over land-constrained metros such as Mumbai. A report by the Association of Senior Living India (ASLI) and JLL estimates that India’s organised senior living market could represent a $10.1 bn opportunity by 2030. The sector had about 25,050 organised units as of June 2026, while penetration stood at only 1.5 per ce..

Next Story
Real Estate

Corrosion Costs India’s Infrastructure Rs. 142 bn Annually

Corrosion costs India an estimated Rs. 1.42 tn annually, equivalent to 4.3 per cent of gross domestic product, according to a report by the Confederation of Indian Industry and the National Research Institute. Infrastructure accounts for Rs. 142 bn of the annual burden, making it the sector with the largest absolute cost among those examined. The report, presented at the CII Annual Infrastructure Summit 2026, said the infrastructure-sector cost equals about 2.9 per cent of the sector’s gross domestic product. It estimated that effective measures could generate maximum savings of Rs. 495.8 bn..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code