CERC Reinstates Connectivity For 196.8 MW Hybrid Project In Madhya Pradesh
ECONOMY & POLICY

CERC Reinstates Connectivity For 196.8 MW Hybrid Project In Madhya Pradesh

The Central Electricity Regulatory Commission has allowed VEH Jayin Renewables Private Limited to restore connectivity approval for its hybrid renewable energy project in Madhya Pradesh. The order, issued on 7 May 2026, resolves a dispute over delayed submission of mandatory financial guarantees and clears the way for the project to move towards commissioning. The installation has a combined capacity of 196.8 megawatt (MW), comprising a 151.8 MW wind element and a 45 MW solar component.

The dispute followed regulatory amendments introduced in September 2025 that required developers to submit two connectivity bank guarantees, Conn-BG1 and Conn-BG3, by 8 November 2025. The total value of the guarantees was approximately Rs 14 million (mn); the developer submitted the instruments on 8 December 2025, one month after the deadline. VEH Jayin said the delay arose from internal administrative procedures and approvals involving its Australia-based investors and was not an intention to abandon or defer the project.

The Central Transmission Utility of India Limited rejected the late submission and revoked connectivity for the 45 MW solar component in March 2026 on the basis that timelines in the regulations were mandatory. VEH Jayin petitioned the Commission, arguing that the project had reached advanced stages of commissioning and that cancellation would create significant financial and operational hardship. The Commission found the delay unintentional, noted that the guarantees had been submitted and invoked its power to relax provisions to avoid undue hardship.

The regulator nevertheless imposed a financial penalty and directed the developer to pay Rs 0.7 million (mn), equal to five per cent of the required bank guarantee amount, within 30 days. After receipt of the payment, CTUIL was instructed to restore connectivity within one week and to process the necessary technical data so that the hybrid plant can proceed towards operations and planned captive renewable power supply. The order aims to balance regulatory discipline with practical facilitation of renewable capacity.

The Central Electricity Regulatory Commission has allowed VEH Jayin Renewables Private Limited to restore connectivity approval for its hybrid renewable energy project in Madhya Pradesh. The order, issued on 7 May 2026, resolves a dispute over delayed submission of mandatory financial guarantees and clears the way for the project to move towards commissioning. The installation has a combined capacity of 196.8 megawatt (MW), comprising a 151.8 MW wind element and a 45 MW solar component. The dispute followed regulatory amendments introduced in September 2025 that required developers to submit two connectivity bank guarantees, Conn-BG1 and Conn-BG3, by 8 November 2025. The total value of the guarantees was approximately Rs 14 million (mn); the developer submitted the instruments on 8 December 2025, one month after the deadline. VEH Jayin said the delay arose from internal administrative procedures and approvals involving its Australia-based investors and was not an intention to abandon or defer the project. The Central Transmission Utility of India Limited rejected the late submission and revoked connectivity for the 45 MW solar component in March 2026 on the basis that timelines in the regulations were mandatory. VEH Jayin petitioned the Commission, arguing that the project had reached advanced stages of commissioning and that cancellation would create significant financial and operational hardship. The Commission found the delay unintentional, noted that the guarantees had been submitted and invoked its power to relax provisions to avoid undue hardship. The regulator nevertheless imposed a financial penalty and directed the developer to pay Rs 0.7 million (mn), equal to five per cent of the required bank guarantee amount, within 30 days. After receipt of the payment, CTUIL was instructed to restore connectivity within one week and to process the necessary technical data so that the hybrid plant can proceed towards operations and planned captive renewable power supply. The order aims to balance regulatory discipline with practical facilitation of renewable capacity.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code