CERC Reinstates Connectivity For 196.8 MW Hybrid Project In Madhya Pradesh
ECONOMY & POLICY

CERC Reinstates Connectivity For 196.8 MW Hybrid Project In Madhya Pradesh

The Central Electricity Regulatory Commission has allowed VEH Jayin Renewables Private Limited to restore connectivity approval for its hybrid renewable energy project in Madhya Pradesh. The order, issued on 7 May 2026, resolves a dispute over delayed submission of mandatory financial guarantees and clears the way for the project to move towards commissioning. The installation has a combined capacity of 196.8 megawatt (MW), comprising a 151.8 MW wind element and a 45 MW solar component.

The dispute followed regulatory amendments introduced in September 2025 that required developers to submit two connectivity bank guarantees, Conn-BG1 and Conn-BG3, by 8 November 2025. The total value of the guarantees was approximately Rs 14 million (mn); the developer submitted the instruments on 8 December 2025, one month after the deadline. VEH Jayin said the delay arose from internal administrative procedures and approvals involving its Australia-based investors and was not an intention to abandon or defer the project.

The Central Transmission Utility of India Limited rejected the late submission and revoked connectivity for the 45 MW solar component in March 2026 on the basis that timelines in the regulations were mandatory. VEH Jayin petitioned the Commission, arguing that the project had reached advanced stages of commissioning and that cancellation would create significant financial and operational hardship. The Commission found the delay unintentional, noted that the guarantees had been submitted and invoked its power to relax provisions to avoid undue hardship.

The regulator nevertheless imposed a financial penalty and directed the developer to pay Rs 0.7 million (mn), equal to five per cent of the required bank guarantee amount, within 30 days. After receipt of the payment, CTUIL was instructed to restore connectivity within one week and to process the necessary technical data so that the hybrid plant can proceed towards operations and planned captive renewable power supply. The order aims to balance regulatory discipline with practical facilitation of renewable capacity.

The Central Electricity Regulatory Commission has allowed VEH Jayin Renewables Private Limited to restore connectivity approval for its hybrid renewable energy project in Madhya Pradesh. The order, issued on 7 May 2026, resolves a dispute over delayed submission of mandatory financial guarantees and clears the way for the project to move towards commissioning. The installation has a combined capacity of 196.8 megawatt (MW), comprising a 151.8 MW wind element and a 45 MW solar component. The dispute followed regulatory amendments introduced in September 2025 that required developers to submit two connectivity bank guarantees, Conn-BG1 and Conn-BG3, by 8 November 2025. The total value of the guarantees was approximately Rs 14 million (mn); the developer submitted the instruments on 8 December 2025, one month after the deadline. VEH Jayin said the delay arose from internal administrative procedures and approvals involving its Australia-based investors and was not an intention to abandon or defer the project. The Central Transmission Utility of India Limited rejected the late submission and revoked connectivity for the 45 MW solar component in March 2026 on the basis that timelines in the regulations were mandatory. VEH Jayin petitioned the Commission, arguing that the project had reached advanced stages of commissioning and that cancellation would create significant financial and operational hardship. The Commission found the delay unintentional, noted that the guarantees had been submitted and invoked its power to relax provisions to avoid undue hardship. The regulator nevertheless imposed a financial penalty and directed the developer to pay Rs 0.7 million (mn), equal to five per cent of the required bank guarantee amount, within 30 days. After receipt of the payment, CTUIL was instructed to restore connectivity within one week and to process the necessary technical data so that the hybrid plant can proceed towards operations and planned captive renewable power supply. The order aims to balance regulatory discipline with practical facilitation of renewable capacity.

Next Story
Infrastructure Transport

Pathankot–Jogindernagar Rail Service Resumes After Four Years

The Pathankot–Jogindernagar rail service resumed on Tuesday, 9 June 2026, restoring a direct link between Pathankot in Punjab and Jogindernagar in Himachal Pradesh after four years. The service had been suspended following infrastructure work and rehabilitation, and the resumption marks the restoration of regular connectivity along the hill route. Railway officials said the reopening followed a phased programme of repairs and targeted maintenance across vulnerable sections of the line. Officials said the restarted services will cater to commuters, local traders and tourists who rely on rail ..

Next Story
Infrastructure Transport

Railways Approves Rs 2.38 Billion Safety Upgrade on Jammu Katra Route

The Railway Board approved a Rs 2.38 billion (bn) safety upgrade for the Jammu Katra rail section. The allocation of Rs 2.38 bn will be deployed to strengthen safety infrastructure along the route. The decision follows a review of corridor safety needs and aligns with a wider effort to modernise key regional links. The Jammu Katra corridor serves a high volume of passenger traffic, including pilgrimage travel to the town of Katra which is a gateway to a major shrine. The project is expected to address operational risks and improve reliability for commuters and visitors. Seasonal surges in dema..

Next Story
Infrastructure Transport

Rayagada Railway Division Begins Operations Under ECoR

The newly created Rayagada Railway Division of the East Coast Railway (ECoR) commenced operations on Monday and is led by Indian Railway Service of Electrical Engineers (IRSEE) officer Amitabh Singhal. ECoR said Singhal has been associated during his long railway career with several landmark rolling stock initiatives, including the Vande Bharat Express project, and will lead the division supported by officers and railway staff in strengthening operations, infrastructure development and service delivery across the region. The Ministry of Railways formally notified the creation of the Rayagada D..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement