CERC Reinstates Connectivity For 196.8 MW Hybrid Project In Madhya Pradesh
ECONOMY & POLICY

CERC Reinstates Connectivity For 196.8 MW Hybrid Project In Madhya Pradesh

The Central Electricity Regulatory Commission has allowed VEH Jayin Renewables Private Limited to restore connectivity approval for its hybrid renewable energy project in Madhya Pradesh. The order, issued on 7 May 2026, resolves a dispute over delayed submission of mandatory financial guarantees and clears the way for the project to move towards commissioning. The installation has a combined capacity of 196.8 megawatt (MW), comprising a 151.8 MW wind element and a 45 MW solar component.

The dispute followed regulatory amendments introduced in September 2025 that required developers to submit two connectivity bank guarantees, Conn-BG1 and Conn-BG3, by 8 November 2025. The total value of the guarantees was approximately Rs 14 million (mn); the developer submitted the instruments on 8 December 2025, one month after the deadline. VEH Jayin said the delay arose from internal administrative procedures and approvals involving its Australia-based investors and was not an intention to abandon or defer the project.

The Central Transmission Utility of India Limited rejected the late submission and revoked connectivity for the 45 MW solar component in March 2026 on the basis that timelines in the regulations were mandatory. VEH Jayin petitioned the Commission, arguing that the project had reached advanced stages of commissioning and that cancellation would create significant financial and operational hardship. The Commission found the delay unintentional, noted that the guarantees had been submitted and invoked its power to relax provisions to avoid undue hardship.

The regulator nevertheless imposed a financial penalty and directed the developer to pay Rs 0.7 million (mn), equal to five per cent of the required bank guarantee amount, within 30 days. After receipt of the payment, CTUIL was instructed to restore connectivity within one week and to process the necessary technical data so that the hybrid plant can proceed towards operations and planned captive renewable power supply. The order aims to balance regulatory discipline with practical facilitation of renewable capacity.

The Central Electricity Regulatory Commission has allowed VEH Jayin Renewables Private Limited to restore connectivity approval for its hybrid renewable energy project in Madhya Pradesh. The order, issued on 7 May 2026, resolves a dispute over delayed submission of mandatory financial guarantees and clears the way for the project to move towards commissioning. The installation has a combined capacity of 196.8 megawatt (MW), comprising a 151.8 MW wind element and a 45 MW solar component. The dispute followed regulatory amendments introduced in September 2025 that required developers to submit two connectivity bank guarantees, Conn-BG1 and Conn-BG3, by 8 November 2025. The total value of the guarantees was approximately Rs 14 million (mn); the developer submitted the instruments on 8 December 2025, one month after the deadline. VEH Jayin said the delay arose from internal administrative procedures and approvals involving its Australia-based investors and was not an intention to abandon or defer the project. The Central Transmission Utility of India Limited rejected the late submission and revoked connectivity for the 45 MW solar component in March 2026 on the basis that timelines in the regulations were mandatory. VEH Jayin petitioned the Commission, arguing that the project had reached advanced stages of commissioning and that cancellation would create significant financial and operational hardship. The Commission found the delay unintentional, noted that the guarantees had been submitted and invoked its power to relax provisions to avoid undue hardship. The regulator nevertheless imposed a financial penalty and directed the developer to pay Rs 0.7 million (mn), equal to five per cent of the required bank guarantee amount, within 30 days. After receipt of the payment, CTUIL was instructed to restore connectivity within one week and to process the necessary technical data so that the hybrid plant can proceed towards operations and planned captive renewable power supply. The order aims to balance regulatory discipline with practical facilitation of renewable capacity.

Related Stories

Gold Stories

Next Story
Real Estate

Adani begins construction of Dharavi rehabilitation homes

Construction of rehabilitation homes for eligible Dharavi residents has commenced at the 22-acre Matunga railway site, following a Bhoomi Poojan ceremony performed by Pranav Adani, Director, Adani Enterprises (AEL). The project, being implemented by Adani Navbharat Developers (ANDPL), envisages 10 towers comprising 10,432 rehabilitation apartments and 1,379 commercial and industrial units.Under the in-situ rehabilitation scheme, eligible residents will receive homes measuring 350 sq ft. Residents from Sectors 6 and 1 will be accommodated at Matunga first, followed by nearly 4,500 apartments fo..

Next Story
Real Estate

Adani begins construction of Dharavi rehabilitation homes

Construction of rehabilitation homes for eligible Dharavi residents has commenced at the 22-acre Matunga railway site, following a Bhoomi Poojan ceremony performed by Pranav Adani, Director, Adani Enterprises (AEL). The project, being implemented by Adani Navbharat Developers (ANDPL), envisages 10 towers comprising 10,432 rehabilitation apartments and 1,379 commercial and industrial units.Under the in-situ rehabilitation scheme, eligible residents will receive homes measuring 350 sq ft. Residents from Sectors 6 and 1 will be accommodated at Matunga first, followed by nearly 4,500 apartments fo..

Next Story
Equipment

Seven Propel 470 HEV electric tippers go to work on coal haulage in Chhattisgarh

Propel EV, the electric mobility division of Propel Industries and India's No. 1 electric tipper brand, has deployed seven 470 HEV electric trucks with a leading coal-haulage contractor at one of India's largest opencast coal mines in Chhattisgarh. The trucks are in daily operation, moving coal on continuous haul cycles in one of the most demanding applications in Indian mining.Why Electric - and Why CoalCoal haulage runs round the clock: heavy loads, long haul cycles, steep ramps and abrasive dust. It is also where diesel hurts most. Engines run continuously, fuel is the largest single operat..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code