CERC Reinstates Connectivity For 196.8 MW Hybrid Project In Madhya Pradesh
ECONOMY & POLICY

CERC Reinstates Connectivity For 196.8 MW Hybrid Project In Madhya Pradesh

The Central Electricity Regulatory Commission has allowed VEH Jayin Renewables Private Limited to restore connectivity approval for its hybrid renewable energy project in Madhya Pradesh. The order, issued on 7 May 2026, resolves a dispute over delayed submission of mandatory financial guarantees and clears the way for the project to move towards commissioning. The installation has a combined capacity of 196.8 megawatt (MW), comprising a 151.8 MW wind element and a 45 MW solar component.

The dispute followed regulatory amendments introduced in September 2025 that required developers to submit two connectivity bank guarantees, Conn-BG1 and Conn-BG3, by 8 November 2025. The total value of the guarantees was approximately Rs 14 million (mn); the developer submitted the instruments on 8 December 2025, one month after the deadline. VEH Jayin said the delay arose from internal administrative procedures and approvals involving its Australia-based investors and was not an intention to abandon or defer the project.

The Central Transmission Utility of India Limited rejected the late submission and revoked connectivity for the 45 MW solar component in March 2026 on the basis that timelines in the regulations were mandatory. VEH Jayin petitioned the Commission, arguing that the project had reached advanced stages of commissioning and that cancellation would create significant financial and operational hardship. The Commission found the delay unintentional, noted that the guarantees had been submitted and invoked its power to relax provisions to avoid undue hardship.

The regulator nevertheless imposed a financial penalty and directed the developer to pay Rs 0.7 million (mn), equal to five per cent of the required bank guarantee amount, within 30 days. After receipt of the payment, CTUIL was instructed to restore connectivity within one week and to process the necessary technical data so that the hybrid plant can proceed towards operations and planned captive renewable power supply. The order aims to balance regulatory discipline with practical facilitation of renewable capacity.

The Central Electricity Regulatory Commission has allowed VEH Jayin Renewables Private Limited to restore connectivity approval for its hybrid renewable energy project in Madhya Pradesh. The order, issued on 7 May 2026, resolves a dispute over delayed submission of mandatory financial guarantees and clears the way for the project to move towards commissioning. The installation has a combined capacity of 196.8 megawatt (MW), comprising a 151.8 MW wind element and a 45 MW solar component. The dispute followed regulatory amendments introduced in September 2025 that required developers to submit two connectivity bank guarantees, Conn-BG1 and Conn-BG3, by 8 November 2025. The total value of the guarantees was approximately Rs 14 million (mn); the developer submitted the instruments on 8 December 2025, one month after the deadline. VEH Jayin said the delay arose from internal administrative procedures and approvals involving its Australia-based investors and was not an intention to abandon or defer the project. The Central Transmission Utility of India Limited rejected the late submission and revoked connectivity for the 45 MW solar component in March 2026 on the basis that timelines in the regulations were mandatory. VEH Jayin petitioned the Commission, arguing that the project had reached advanced stages of commissioning and that cancellation would create significant financial and operational hardship. The Commission found the delay unintentional, noted that the guarantees had been submitted and invoked its power to relax provisions to avoid undue hardship. The regulator nevertheless imposed a financial penalty and directed the developer to pay Rs 0.7 million (mn), equal to five per cent of the required bank guarantee amount, within 30 days. After receipt of the payment, CTUIL was instructed to restore connectivity within one week and to process the necessary technical data so that the hybrid plant can proceed towards operations and planned captive renewable power supply. The order aims to balance regulatory discipline with practical facilitation of renewable capacity.

Next Story
Technology

AI-Enabled Workflows Lift Profitability and Productivity

Organisations modernising frontline workflows with artificial intelligence, automation and real-time data are reporting stronger financial performance, higher productivity and improved employee engagement, according to a global study by Zebra Technologies and Oxford Economics.The research covered 1,000 senior leaders across retail, manufacturing, transportation and logistics in the US, Mexico, the UK, Germany, India, Japan, Australia and New Zealand.In transportation and logistics, 54 per cent of companies that improved picking and packing operations reported faster operational performance, wh..

Next Story
Real Estate

India Leads Global AI Readiness but Implementation Lags

Indian companies lead global averages across all eight artificial intelligence readiness indicators tracked by JLL, but only 19 per cent have started making changes to their workplaces, according to the JLL 2026 Future of Work Survey.The study found that 77 per cent of Indian business leaders expect AI to change their office requirements, creating a 58-percentage-point gap between awareness and implementation. The survey covered more than 2,200 CEOs, CFOs and real estate leaders across 21 countries during the first quarter of 2026.Despite concerns over automation, 58 per cent of Indian leaders..

Next Story
Equipment

Three WOLFF Cranes Build Riyadh Cable-Stayed Bridges

Three WOLFF 180 B luffing jib cranes are supporting the construction of two cable-stayed bridges alongside the existing Wadi Laban Bridge in Riyadh, Saudi Arabia. The project is being developed for the Royal Commission for Riyadh City and executed by the ICRC joint venture comprising IC Ictas and Al Rashid Trading & Contracting Company.The cranes are handling lifting operations including formwork, reinforcement, concrete placement, work platforms, surveying equipment and other construction materials. Each crane is fitted with a 40 m jib, reaches a hook height of 157 m and offers a maximum ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement