CERC Reinstates Connectivity For 196.8 MW Hybrid Project In Madhya Pradesh
ECONOMY & POLICY

CERC Reinstates Connectivity For 196.8 MW Hybrid Project In Madhya Pradesh

The Central Electricity Regulatory Commission has allowed VEH Jayin Renewables Private Limited to restore connectivity approval for its hybrid renewable energy project in Madhya Pradesh. The order, issued on 7 May 2026, resolves a dispute over delayed submission of mandatory financial guarantees and clears the way for the project to move towards commissioning. The installation has a combined capacity of 196.8 megawatt (MW), comprising a 151.8 MW wind element and a 45 MW solar component.

The dispute followed regulatory amendments introduced in September 2025 that required developers to submit two connectivity bank guarantees, Conn-BG1 and Conn-BG3, by 8 November 2025. The total value of the guarantees was approximately Rs 14 million (mn); the developer submitted the instruments on 8 December 2025, one month after the deadline. VEH Jayin said the delay arose from internal administrative procedures and approvals involving its Australia-based investors and was not an intention to abandon or defer the project.

The Central Transmission Utility of India Limited rejected the late submission and revoked connectivity for the 45 MW solar component in March 2026 on the basis that timelines in the regulations were mandatory. VEH Jayin petitioned the Commission, arguing that the project had reached advanced stages of commissioning and that cancellation would create significant financial and operational hardship. The Commission found the delay unintentional, noted that the guarantees had been submitted and invoked its power to relax provisions to avoid undue hardship.

The regulator nevertheless imposed a financial penalty and directed the developer to pay Rs 0.7 million (mn), equal to five per cent of the required bank guarantee amount, within 30 days. After receipt of the payment, CTUIL was instructed to restore connectivity within one week and to process the necessary technical data so that the hybrid plant can proceed towards operations and planned captive renewable power supply. The order aims to balance regulatory discipline with practical facilitation of renewable capacity.

The Central Electricity Regulatory Commission has allowed VEH Jayin Renewables Private Limited to restore connectivity approval for its hybrid renewable energy project in Madhya Pradesh. The order, issued on 7 May 2026, resolves a dispute over delayed submission of mandatory financial guarantees and clears the way for the project to move towards commissioning. The installation has a combined capacity of 196.8 megawatt (MW), comprising a 151.8 MW wind element and a 45 MW solar component. The dispute followed regulatory amendments introduced in September 2025 that required developers to submit two connectivity bank guarantees, Conn-BG1 and Conn-BG3, by 8 November 2025. The total value of the guarantees was approximately Rs 14 million (mn); the developer submitted the instruments on 8 December 2025, one month after the deadline. VEH Jayin said the delay arose from internal administrative procedures and approvals involving its Australia-based investors and was not an intention to abandon or defer the project. The Central Transmission Utility of India Limited rejected the late submission and revoked connectivity for the 45 MW solar component in March 2026 on the basis that timelines in the regulations were mandatory. VEH Jayin petitioned the Commission, arguing that the project had reached advanced stages of commissioning and that cancellation would create significant financial and operational hardship. The Commission found the delay unintentional, noted that the guarantees had been submitted and invoked its power to relax provisions to avoid undue hardship. The regulator nevertheless imposed a financial penalty and directed the developer to pay Rs 0.7 million (mn), equal to five per cent of the required bank guarantee amount, within 30 days. After receipt of the payment, CTUIL was instructed to restore connectivity within one week and to process the necessary technical data so that the hybrid plant can proceed towards operations and planned captive renewable power supply. The order aims to balance regulatory discipline with practical facilitation of renewable capacity.

Next Story
Infrastructure Energy

Allu Cinemas Installs 727 kW Solar System with Freyr

Allu Cinemas, Kokapet, has partnered with Freyr Energy to commission a 727 kW rooftop solar power system at its cinema facility in Hyderabad with an investment of Rs 22.76 million.The installation is expected to meet nearly 60 per cent of the cinema’s energy requirements, making it one of the largest solar deployments for a cinema complex in the region.According to the companies, the project is expected to reduce annual electricity expenses from around Rs 5.2 million to nearly Rs 0.5 million, generating estimated yearly savings of Rs 7.7–8 million.The solar installation is also projected t..

Next Story
Technology

Kaizen AI Discusses Real Estate AI Adoption Across Projects

Real estate developers, architects and technology firms discussed the growing implementation of artificial intelligence across active projects in India, Dubai and the United States during a media interaction held in Mumbai this week.The discussion focused on how AI-driven systems are increasingly being used in live real estate projects to evaluate planning, parking, efficiency, cost and constructability at a scale beyond conventional workflows.Kaizen AI, which has worked on more than 200 projects globally, showcased how AI-led optimisation systems are being integrated into developments across ..

Next Story
Real Estate

Sanghvi Palazzo Gets OC Ahead of RERA Timeline

Sanghvi Realty has received the Occupation Certificate (OC) for its residential project Sanghvi Palazzo in Andheri West, Mumbai, around 18 months ahead of its RERA possession deadline of December 2027.Located on Jai Bhavani Mata Road, Ambivali, the project comprises a G+9 residential development with 41 apartments, including 1, 2 and 3 BHK configurations ranging from 358 sq. ft. to 770 sq. ft. carpet area.The company said the receipt of the OC marks the completion of all regulatory approvals and construction activities for the project.Pakshal Sanghvi, Director, Sanghvi Realty, said timely deli..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement