Kavach Installation on Mumbai-Delhi-Kolkata Route Extended to Dec ’25
ECONOMY & POLICY

Kavach Installation on Mumbai-Delhi-Kolkata Route Extended to Dec ’25

The Railway Board has extended the deadline for the installation of the Automatic Train Protection (ATP) system, Kavach, on the Delhi-Mumbai and Delhi-Kolkata routes from March to December 2025. According to the revised railway budget estimates for 2025-26, track-side equipment for Kavach Version 4.0 will be installed across the 3,000 km stretch by the end of 2025, with work progressing on the remaining sections.

Indian Railways adopted Kavach as the national ATP system in 2020, with the latest specification for Version 4.0 approved in July 2024. The project includes the installation of Kavach on 10,000 locomotives, which is already underway. The technology comprises multiple components such as RFID tags along the tracks, telecom towers, optical fibre cables, and Loco Kavach installed on each locomotive. Given its complexity, the installation process is time-consuming but is advancing at a faster pace compared to similar systems in developed countries.

Efforts to deploy Kavach have been on-going across the Indian railway network in a mission-driven approach. The Research Design and Standards Organization (RDSO) approved Kavach Version 4.0 in July 2024, incorporating advanced safety features. The Railway Minister recently stated that the entire rail network is expected to be covered by Kavach within the next six years.

Field trials for the system began in February 2016, leading to the approval of three firms for supplying Kavach Version 3.2 in 2018-19. The system was initially deployed across 1,465 RKm on South Central Railway, generating valuable insights that contributed to the development of Version 4.0. This upgraded version enhances safety measures and is designed to cater to the vast and diverse railway network in India.

News source: The Print

The Railway Board has extended the deadline for the installation of the Automatic Train Protection (ATP) system, Kavach, on the Delhi-Mumbai and Delhi-Kolkata routes from March to December 2025. According to the revised railway budget estimates for 2025-26, track-side equipment for Kavach Version 4.0 will be installed across the 3,000 km stretch by the end of 2025, with work progressing on the remaining sections. Indian Railways adopted Kavach as the national ATP system in 2020, with the latest specification for Version 4.0 approved in July 2024. The project includes the installation of Kavach on 10,000 locomotives, which is already underway. The technology comprises multiple components such as RFID tags along the tracks, telecom towers, optical fibre cables, and Loco Kavach installed on each locomotive. Given its complexity, the installation process is time-consuming but is advancing at a faster pace compared to similar systems in developed countries. Efforts to deploy Kavach have been on-going across the Indian railway network in a mission-driven approach. The Research Design and Standards Organization (RDSO) approved Kavach Version 4.0 in July 2024, incorporating advanced safety features. The Railway Minister recently stated that the entire rail network is expected to be covered by Kavach within the next six years. Field trials for the system began in February 2016, leading to the approval of three firms for supplying Kavach Version 3.2 in 2018-19. The system was initially deployed across 1,465 RKm on South Central Railway, generating valuable insights that contributed to the development of Version 4.0. This upgraded version enhances safety measures and is designed to cater to the vast and diverse railway network in India. News source: The Print

Next Story
Equipment

Schwing Stetter India Unveils New Innovations at Excon 2025

Schwing Stetter India unveiled more than 20 new machines at Excon 2025, marking one of its most significant showcases and introducing several India-first technologies to the construction equipment sector. The company launched the country’s first 56-metre boom pump designed and manufactured in India, the first fully electric truck mixer, the first CNG mixer variant and the first hybrid boom pump. Executives said the launch portfolio was engineered to support India’s move toward faster, greener and more vertically oriented infrastructure through advanced engineering, clean-energy solutions a..

Next Story
Infrastructure Energy

SEPC Resolves Hindustan Copper Dispute, Wins Rs 725 Mn Order

Engineering, procurement and construction firm SEPC Ltd has recently settled a dispute with Hindustan Copper Ltd (HCL) and secured a mining infrastructure order valued at Rs 725 million from the state-owned company. SEPC informed the stock exchanges that it has executed a settlement deed with HCL, bringing closure to all inter-se claims and counterclaims arising from arbitration proceedings. As part of the settlement, SEPC will receive Rs 304.5 million as full and final payment, marking the resolution of all pending disputes between the two entities. The company also stated that Hindustan Co..

Next Story
Infrastructure Energy

20% Ethanol Blending Cuts India’s CO2 Emissions by 73.6 Mn Tonnes

Union Road Transport and Highways Minister Nitin Gadkari recently said that India has reduced carbon dioxide emissions by 73.6 million metric tonnes due to the adoption of 20 per cent ethanol blending in petrol. He made the statement while replying to supplementary questions during the Question Hour in the Lok Sabha. Describing ethanol as a green fuel, the minister said it plays a key role in reducing pollution while also supporting higher incomes for farmers. He underlined that ethanol blending contributes both to environmental sustainability and rural economic growth. Nitin Gadkari also po..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App