Kavach Installation on Mumbai-Delhi-Kolkata Route Extended to Dec ’25
ECONOMY & POLICY

Kavach Installation on Mumbai-Delhi-Kolkata Route Extended to Dec ’25

The Railway Board has extended the deadline for the installation of the Automatic Train Protection (ATP) system, Kavach, on the Delhi-Mumbai and Delhi-Kolkata routes from March to December 2025. According to the revised railway budget estimates for 2025-26, track-side equipment for Kavach Version 4.0 will be installed across the 3,000 km stretch by the end of 2025, with work progressing on the remaining sections.

Indian Railways adopted Kavach as the national ATP system in 2020, with the latest specification for Version 4.0 approved in July 2024. The project includes the installation of Kavach on 10,000 locomotives, which is already underway. The technology comprises multiple components such as RFID tags along the tracks, telecom towers, optical fibre cables, and Loco Kavach installed on each locomotive. Given its complexity, the installation process is time-consuming but is advancing at a faster pace compared to similar systems in developed countries.

Efforts to deploy Kavach have been on-going across the Indian railway network in a mission-driven approach. The Research Design and Standards Organization (RDSO) approved Kavach Version 4.0 in July 2024, incorporating advanced safety features. The Railway Minister recently stated that the entire rail network is expected to be covered by Kavach within the next six years.

Field trials for the system began in February 2016, leading to the approval of three firms for supplying Kavach Version 3.2 in 2018-19. The system was initially deployed across 1,465 RKm on South Central Railway, generating valuable insights that contributed to the development of Version 4.0. This upgraded version enhances safety measures and is designed to cater to the vast and diverse railway network in India.

News source: The Print

The Railway Board has extended the deadline for the installation of the Automatic Train Protection (ATP) system, Kavach, on the Delhi-Mumbai and Delhi-Kolkata routes from March to December 2025. According to the revised railway budget estimates for 2025-26, track-side equipment for Kavach Version 4.0 will be installed across the 3,000 km stretch by the end of 2025, with work progressing on the remaining sections. Indian Railways adopted Kavach as the national ATP system in 2020, with the latest specification for Version 4.0 approved in July 2024. The project includes the installation of Kavach on 10,000 locomotives, which is already underway. The technology comprises multiple components such as RFID tags along the tracks, telecom towers, optical fibre cables, and Loco Kavach installed on each locomotive. Given its complexity, the installation process is time-consuming but is advancing at a faster pace compared to similar systems in developed countries. Efforts to deploy Kavach have been on-going across the Indian railway network in a mission-driven approach. The Research Design and Standards Organization (RDSO) approved Kavach Version 4.0 in July 2024, incorporating advanced safety features. The Railway Minister recently stated that the entire rail network is expected to be covered by Kavach within the next six years. Field trials for the system began in February 2016, leading to the approval of three firms for supplying Kavach Version 3.2 in 2018-19. The system was initially deployed across 1,465 RKm on South Central Railway, generating valuable insights that contributed to the development of Version 4.0. This upgraded version enhances safety measures and is designed to cater to the vast and diverse railway network in India. News source: The Print

Next Story
Infrastructure Urban

APCRDA Approves Rs 9.04 Bn to Upgrade Infrastructure in 29 Amaravati Villages

The Andhra Pradesh Capital Region Development Authority (APCRDA), chaired by Chief Minister N Chandrababu Naidu, has approved Rs 9.04 billion for addressing key infrastructure gaps in 29 villages within Amaravati’s greenfield capital area, announced Municipal Administration Minister P. Narayana at the 51st CRDA meeting.The funds will be used to upgrade critical facilities including roads, drains, drinking water supply, sewerage systems, and street lighting. A detailed assessment revealed a 30 per cent shortfall in water supply, a total absence of sewerage infrastructure, a 40 per cent defici..

Next Story
Infrastructure Transport

Cabinet Approves Phase-1B of Lucknow Metro Rail Project Worth Rs 58.01 Bn

The Union Cabinet, led by Prime Minister Narendra Modi, has approved Phase-1B of the Lucknow Metro Rail Project in Uttar Pradesh. This phase covers an 11.165 km corridor with 12 stations—7 underground and 5 elevated—extending the city’s metro network to 34 km upon completion.Phase-1B targets the dense, historic parts of Lucknow, enhancing connectivity across key commercial, healthcare, tourist, and culinary hubs. Important areas served include Aminabad, Yahiyaganj, Pandeyganj, Chowk, King George’s Medical University, and landmarks like Bara Imambara and Rumi Darwaza.This expansion prom..

Next Story
Infrastructure Transport

Major Upgrades Planned for Tamil Nadu’s National Waterways

Tamil Nadu is poised for significant infrastructure upgrades across its National Waterways (NWs), with a focus on developing jetties, cargo hubs, and cruise tourism circuits, according to the Ministry of Ports, Shipping and Waterways. These projects aim to promote sustainable inland water transport and boost regional economic activity.Key projects include the development of Buckingham Canal (part of NW-4), with jetties planned at the following locations:Mahabalipuram to Ediyur BridgeCooum River near Marina BeachPulicat LakeEnnore Port to ETPS, specifically for cargo operationsOther National Wa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?