Kavach Installation on Mumbai-Delhi-Kolkata Route Extended to Dec ’25
ECONOMY & POLICY

Kavach Installation on Mumbai-Delhi-Kolkata Route Extended to Dec ’25

The Railway Board has extended the deadline for the installation of the Automatic Train Protection (ATP) system, Kavach, on the Delhi-Mumbai and Delhi-Kolkata routes from March to December 2025. According to the revised railway budget estimates for 2025-26, track-side equipment for Kavach Version 4.0 will be installed across the 3,000 km stretch by the end of 2025, with work progressing on the remaining sections.

Indian Railways adopted Kavach as the national ATP system in 2020, with the latest specification for Version 4.0 approved in July 2024. The project includes the installation of Kavach on 10,000 locomotives, which is already underway. The technology comprises multiple components such as RFID tags along the tracks, telecom towers, optical fibre cables, and Loco Kavach installed on each locomotive. Given its complexity, the installation process is time-consuming but is advancing at a faster pace compared to similar systems in developed countries.

Efforts to deploy Kavach have been on-going across the Indian railway network in a mission-driven approach. The Research Design and Standards Organization (RDSO) approved Kavach Version 4.0 in July 2024, incorporating advanced safety features. The Railway Minister recently stated that the entire rail network is expected to be covered by Kavach within the next six years.

Field trials for the system began in February 2016, leading to the approval of three firms for supplying Kavach Version 3.2 in 2018-19. The system was initially deployed across 1,465 RKm on South Central Railway, generating valuable insights that contributed to the development of Version 4.0. This upgraded version enhances safety measures and is designed to cater to the vast and diverse railway network in India.

News source: The Print

The Railway Board has extended the deadline for the installation of the Automatic Train Protection (ATP) system, Kavach, on the Delhi-Mumbai and Delhi-Kolkata routes from March to December 2025. According to the revised railway budget estimates for 2025-26, track-side equipment for Kavach Version 4.0 will be installed across the 3,000 km stretch by the end of 2025, with work progressing on the remaining sections. Indian Railways adopted Kavach as the national ATP system in 2020, with the latest specification for Version 4.0 approved in July 2024. The project includes the installation of Kavach on 10,000 locomotives, which is already underway. The technology comprises multiple components such as RFID tags along the tracks, telecom towers, optical fibre cables, and Loco Kavach installed on each locomotive. Given its complexity, the installation process is time-consuming but is advancing at a faster pace compared to similar systems in developed countries. Efforts to deploy Kavach have been on-going across the Indian railway network in a mission-driven approach. The Research Design and Standards Organization (RDSO) approved Kavach Version 4.0 in July 2024, incorporating advanced safety features. The Railway Minister recently stated that the entire rail network is expected to be covered by Kavach within the next six years. Field trials for the system began in February 2016, leading to the approval of three firms for supplying Kavach Version 3.2 in 2018-19. The system was initially deployed across 1,465 RKm on South Central Railway, generating valuable insights that contributed to the development of Version 4.0. This upgraded version enhances safety measures and is designed to cater to the vast and diverse railway network in India. News source: The Print

Next Story
Infrastructure Urban

InsideFPV Delivers ₹10 Crore Kamikaze Drone Order Under MoD’s EPR Route

InsideFPV, a Surat-based drone technology manufacturer, has successfully executed a ₹10 crore defence contract to supply indigenous kamikaze drones under the Ministry of Defence’s Emergency Procurement Route (EPR). The company completed the delivery of hundreds of FPV kamikaze drone platforms within a rapid two-month timeframe, highlighting its ability to meet urgent military procurement timelines.The supply orders were fulfilled under the emergency procurement mechanism, which is aimed at fast-tracking acquisitions for immediate operational needs. InsideFPV’s quick execution reflects it..

Next Story
Infrastructure Energy

Vedanta Resources Secures Fitch Upgrade to ‘BB-’, Best Rating Since 2015

Vedanta Resources Limited (VRL), a global player in metals, oil & gas, critical minerals, power and technology, has received a credit rating upgrade from Fitch Ratings, marking its strongest bond rating in over a decade.Fitch has raised Vedanta Resources’ Long-Term Foreign-Currency Issuer Default Rating (IDR) to ‘BB-’ from ‘B+’, while maintaining a Stable Outlook. The agency also upgraded VRL’s senior unsecured rating, along with the ratings of US dollar-denominated bonds issued by Vedanta Resources Finance II Plc and guaranteed by VRL, to ‘BB-’.The upgrade represents Vedan..

Next Story
Real Estate

NAREDCO NextGen NCR Chapter Launched

The NAREDCO NextGen NCR Chapter was recently launched at Excelerate 2026 in Mumbai, marking a key step towards integrating emerging real estate leaders from the National Capital Region with the national platform. The initiative aims to promote sustainable and responsible urban development through collaboration and knowledge exchange.The event brought together young developers, entrepreneurs, and professionals from across NCR, including Noida, Gurugram, Ghaziabad, Faridabad, Bhiwadi, and Meerut. Discussions focused on urban development, finance, sustainability, innovation, and policy, emphasisi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement