14 National Highway Projects Miss Deadlines In Nagaland
ROADS & HIGHWAYS

14 National Highway Projects Miss Deadlines In Nagaland

Kohima on July 24: The Centre told Parliament that 14 National Highway projects in Nagaland have missed their original completion deadlines, placing the state among the poorest performers in the Northeast for road delivery. The information was provided in a written reply to the Lok Sabha.

Union Road Transport and Highways Minister Nitin Gadkari said the delayed projects were sanctioned during the last five financial years and exclude proposals for termination or foreclosure. Nagaland had the second-highest number of delayed schemes in the region, behind Assam with 23, followed by Manipur with 13, Sikkim four, Tripura four, Arunachal three, Meghalaya three and Mizoram two.

Gadkari attributed delays to land acquisition bottlenecks, pending statutory clearances, utility shifting, encroachment removal, law and order issues, poor contractor performance and force majeure such as the COVID-19 pandemic. He said National Highway projects are normally scheduled for completion within two to three years but timelines are extended when delays occur beyond contractors' control.

The minister clarified delayed execution does not necessarily cause cost overruns; where contractors are not at fault contractual provisions allow price escalation, while contractor-caused delays attract penalties and prevent extra costs falling on the government. The ministry imposed penalties of around Rs 27.32 billion (bn) over the past three financial years and has recovered nearly Rs seven point eight billion (bn) so far through enhanced monitoring.

The disclosure comes amid concern over centrally funded projects in Nagaland; earlier this year the state refunded Rs 320 mn due to implementation delays and the Ministry of Development of North Eastern Region foreclosed 12 projects worth over Rs one bn because of prolonged delays. The latest data is likely to intensify calls for stronger project monitoring, quicker clearances and better coordination to prevent further delays and safeguard central funding for infrastructure projects.

Kohima on July 24: The Centre told Parliament that 14 National Highway projects in Nagaland have missed their original completion deadlines, placing the state among the poorest performers in the Northeast for road delivery. The information was provided in a written reply to the Lok Sabha. Union Road Transport and Highways Minister Nitin Gadkari said the delayed projects were sanctioned during the last five financial years and exclude proposals for termination or foreclosure. Nagaland had the second-highest number of delayed schemes in the region, behind Assam with 23, followed by Manipur with 13, Sikkim four, Tripura four, Arunachal three, Meghalaya three and Mizoram two. Gadkari attributed delays to land acquisition bottlenecks, pending statutory clearances, utility shifting, encroachment removal, law and order issues, poor contractor performance and force majeure such as the COVID-19 pandemic. He said National Highway projects are normally scheduled for completion within two to three years but timelines are extended when delays occur beyond contractors' control. The minister clarified delayed execution does not necessarily cause cost overruns; where contractors are not at fault contractual provisions allow price escalation, while contractor-caused delays attract penalties and prevent extra costs falling on the government. The ministry imposed penalties of around Rs 27.32 billion (bn) over the past three financial years and has recovered nearly Rs seven point eight billion (bn) so far through enhanced monitoring. The disclosure comes amid concern over centrally funded projects in Nagaland; earlier this year the state refunded Rs 320 mn due to implementation delays and the Ministry of Development of North Eastern Region foreclosed 12 projects worth over Rs one bn because of prolonged delays. The latest data is likely to intensify calls for stronger project monitoring, quicker clearances and better coordination to prevent further delays and safeguard central funding for infrastructure projects.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train’s Surat-Vapi Section Set for 2027

The first section of the Mumbai-Ahmedabad Bullet Train corridor, linking Surat and Vapi, is targeted to begin services in 2027. Construction is expected to be completed by December 2026, while Railway Minister Ashwini Vaishnaw has indicated that an inauguration could take place around the middle of 2027. The National High Speed Rail Corporation (NHSRCL) said the train being manufactured in India is expected to reach the tracks around April or May 2027. The train will undergo extensive testing before the section is opened for passenger services. The project began construction in 2021 and includ..

Next Story
Infrastructure Transport

Indian Railways Approves Four Projects Worth Rs. 7.36 bn Across Four States

Indian Railways has approved four projects with a combined value of Rs. 7.36 bn across Uttar Pradesh, Maharashtra, Andhra Pradesh and Gujarat. The programme covers train protection, signalling, electric traction supply and a road overbridge, with each project assigned to a different railway zone. In Uttar Pradesh, Rs. 2.52 bn has been approved to extend the Kavach 4.0 automatic train protection system across 607.7 km in the Lucknow Division of North Eastern Railway. The system monitors train movements and can apply the brakes if a driver fails to observe a signal or exceeds a safe speed. The w..

Next Story
Infrastructure Urban

Chandru Raheja Sells 1.49% Stake in Mindspace REIT for Rs. 5 bn

Billionaire Chandru Lachmandas Raheja has sold a 1.49 per cent holding in Mindspace Business Parks REIT for Rs. 5 bn through a bulk deal on the BSE. The transaction involved 9.9 mn units and was executed at an average price of Rs. 505 per unit, according to exchange data. Following the sale, units of Mindspace Business Parks REIT were trading 0.18 per cent lower at Rs. 504.05 on Tuesday. Exchange data did not identify the buyers involved in the transaction. Raheja is the chairman of real estate company K Raheja Corp. The sale involved 99,00,990 units, representing 1.49 per cent of the Mumbai-b..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code