14 National Highway Projects Miss Deadlines In Nagaland
ROADS & HIGHWAYS

14 National Highway Projects Miss Deadlines In Nagaland

Kohima on July 24: The Centre told Parliament that 14 National Highway projects in Nagaland have missed their original completion deadlines, placing the state among the poorest performers in the Northeast for road delivery. The information was provided in a written reply to the Lok Sabha.

Union Road Transport and Highways Minister Nitin Gadkari said the delayed projects were sanctioned during the last five financial years and exclude proposals for termination or foreclosure. Nagaland had the second-highest number of delayed schemes in the region, behind Assam with 23, followed by Manipur with 13, Sikkim four, Tripura four, Arunachal three, Meghalaya three and Mizoram two.

Gadkari attributed delays to land acquisition bottlenecks, pending statutory clearances, utility shifting, encroachment removal, law and order issues, poor contractor performance and force majeure such as the COVID-19 pandemic. He said National Highway projects are normally scheduled for completion within two to three years but timelines are extended when delays occur beyond contractors' control.

The minister clarified delayed execution does not necessarily cause cost overruns; where contractors are not at fault contractual provisions allow price escalation, while contractor-caused delays attract penalties and prevent extra costs falling on the government. The ministry imposed penalties of around Rs 27.32 billion (bn) over the past three financial years and has recovered nearly Rs seven point eight billion (bn) so far through enhanced monitoring.

The disclosure comes amid concern over centrally funded projects in Nagaland; earlier this year the state refunded Rs 320 mn due to implementation delays and the Ministry of Development of North Eastern Region foreclosed 12 projects worth over Rs one bn because of prolonged delays. The latest data is likely to intensify calls for stronger project monitoring, quicker clearances and better coordination to prevent further delays and safeguard central funding for infrastructure projects.

Kohima on July 24: The Centre told Parliament that 14 National Highway projects in Nagaland have missed their original completion deadlines, placing the state among the poorest performers in the Northeast for road delivery. The information was provided in a written reply to the Lok Sabha. Union Road Transport and Highways Minister Nitin Gadkari said the delayed projects were sanctioned during the last five financial years and exclude proposals for termination or foreclosure. Nagaland had the second-highest number of delayed schemes in the region, behind Assam with 23, followed by Manipur with 13, Sikkim four, Tripura four, Arunachal three, Meghalaya three and Mizoram two. Gadkari attributed delays to land acquisition bottlenecks, pending statutory clearances, utility shifting, encroachment removal, law and order issues, poor contractor performance and force majeure such as the COVID-19 pandemic. He said National Highway projects are normally scheduled for completion within two to three years but timelines are extended when delays occur beyond contractors' control. The minister clarified delayed execution does not necessarily cause cost overruns; where contractors are not at fault contractual provisions allow price escalation, while contractor-caused delays attract penalties and prevent extra costs falling on the government. The ministry imposed penalties of around Rs 27.32 billion (bn) over the past three financial years and has recovered nearly Rs seven point eight billion (bn) so far through enhanced monitoring. The disclosure comes amid concern over centrally funded projects in Nagaland; earlier this year the state refunded Rs 320 mn due to implementation delays and the Ministry of Development of North Eastern Region foreclosed 12 projects worth over Rs one bn because of prolonged delays. The latest data is likely to intensify calls for stronger project monitoring, quicker clearances and better coordination to prevent further delays and safeguard central funding for infrastructure projects.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Ingram Micro India Earns Sixth Great Place to Work Certification

Ingram Micro India has recently received its sixth consecutive Great Place to Work® certification, recognising the company’s efforts to build a workplace culture centred on trust, collaboration and employee development.The company said the recognition reflects its continued focus on strengthening organisational culture and improving employee experience. Over the past year, Ingram Micro India has worked on employee engagement, encouraging open dialogue, building leadership capabilities and expanding learning and development opportunities.As part of its “Elevate – Soar Higher” programme..

Next Story
Infrastructure Urban

Genesys International Appoints Nikhil Alulkar as CEO

Genesys International Corporation has appointed Nikhil Alulkar as Chief Executive Officer as the geospatial technology company enters its next phase of growth across enterprise, government and international markets.Alulkar will lead company-wide operations, business execution and growth. His responsibilities will include scaling Genesys’ AI-native mapping and Digital Twin platforms, expanding its enterprise and B2B presence, strengthening government and institutional relationships, and developing the operating structure required for international expansion.The appointment comes as Genesys lo..

Next Story
Real Estate

B-Right Real Estate Targets 4.7 Mn Sq Ft Mumbai Growth by 2033

B-Right Real Estate Group has outlined plans to develop approximately 4.7 million sq ft of real estate in Mumbai by 2033 as part of its long-term Vision 2033 roadmap. The company said its expansion strategy will remain focused on Mumbai, with redevelopment-led projects forming a key part of its portfolio.Founded in 2007, B-Right Real Estate has been involved in redevelopment and Slum Rehabilitation Authority (SRA) projects across Mumbai. Its Vision 2033 strategy focuses on financial discipline, governance, design and community-oriented development as it expands its project pipeline.Founder, Ch..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement