14 National Highway Projects Miss Deadlines In Nagaland
ROADS & HIGHWAYS

14 National Highway Projects Miss Deadlines In Nagaland

Kohima on July 24: The Centre told Parliament that 14 National Highway projects in Nagaland have missed their original completion deadlines, placing the state among the poorest performers in the Northeast for road delivery. The information was provided in a written reply to the Lok Sabha.

Union Road Transport and Highways Minister Nitin Gadkari said the delayed projects were sanctioned during the last five financial years and exclude proposals for termination or foreclosure. Nagaland had the second-highest number of delayed schemes in the region, behind Assam with 23, followed by Manipur with 13, Sikkim four, Tripura four, Arunachal three, Meghalaya three and Mizoram two.

Gadkari attributed delays to land acquisition bottlenecks, pending statutory clearances, utility shifting, encroachment removal, law and order issues, poor contractor performance and force majeure such as the COVID-19 pandemic. He said National Highway projects are normally scheduled for completion within two to three years but timelines are extended when delays occur beyond contractors' control.

The minister clarified delayed execution does not necessarily cause cost overruns; where contractors are not at fault contractual provisions allow price escalation, while contractor-caused delays attract penalties and prevent extra costs falling on the government. The ministry imposed penalties of around Rs 27.32 billion (bn) over the past three financial years and has recovered nearly Rs seven point eight billion (bn) so far through enhanced monitoring.

The disclosure comes amid concern over centrally funded projects in Nagaland; earlier this year the state refunded Rs 320 mn due to implementation delays and the Ministry of Development of North Eastern Region foreclosed 12 projects worth over Rs one bn because of prolonged delays. The latest data is likely to intensify calls for stronger project monitoring, quicker clearances and better coordination to prevent further delays and safeguard central funding for infrastructure projects.

Kohima on July 24: The Centre told Parliament that 14 National Highway projects in Nagaland have missed their original completion deadlines, placing the state among the poorest performers in the Northeast for road delivery. The information was provided in a written reply to the Lok Sabha. Union Road Transport and Highways Minister Nitin Gadkari said the delayed projects were sanctioned during the last five financial years and exclude proposals for termination or foreclosure. Nagaland had the second-highest number of delayed schemes in the region, behind Assam with 23, followed by Manipur with 13, Sikkim four, Tripura four, Arunachal three, Meghalaya three and Mizoram two. Gadkari attributed delays to land acquisition bottlenecks, pending statutory clearances, utility shifting, encroachment removal, law and order issues, poor contractor performance and force majeure such as the COVID-19 pandemic. He said National Highway projects are normally scheduled for completion within two to three years but timelines are extended when delays occur beyond contractors' control. The minister clarified delayed execution does not necessarily cause cost overruns; where contractors are not at fault contractual provisions allow price escalation, while contractor-caused delays attract penalties and prevent extra costs falling on the government. The ministry imposed penalties of around Rs 27.32 billion (bn) over the past three financial years and has recovered nearly Rs seven point eight billion (bn) so far through enhanced monitoring. The disclosure comes amid concern over centrally funded projects in Nagaland; earlier this year the state refunded Rs 320 mn due to implementation delays and the Ministry of Development of North Eastern Region foreclosed 12 projects worth over Rs one bn because of prolonged delays. The latest data is likely to intensify calls for stronger project monitoring, quicker clearances and better coordination to prevent further delays and safeguard central funding for infrastructure projects.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code