Chennai-Bengaluru Highway Expansion Delayed Until August 2027
ROADS & HIGHWAYS

Chennai-Bengaluru Highway Expansion Delayed Until August 2027

The six-laning of the 34.5-km Sriperumbudur-Karaipettai section of the Chennai-Bengaluru highway remains incomplete eight years after work began, causing severe hardship for commuters. The National Highways Authority of India (NHAI) has missed several deadlines and has completed only eight of the 17 planned flyovers, bridges and vehicular underpasses. The agency has set August 2027 as the revised completion deadline.

The existing 15 m carriageway narrows to 7.5 m over nearly 3.5 km, where traffic is diverted to service lanes to enable construction of underpasses at Mambakkam and near SIPCOT in Sriperumbudur. Vehicles take between 60 and 90 minutes to cover the 10 km stretch between Sriperumbudur and Sunguvarchathiram, with conditions worsening during weekends and festival periods.

During the recent Deepavali period, queues extended up to 9 km between Sunguvarchathiram and Sriperumbudur from November 5 to 10. Commuters reported that congestion persisted throughout the day despite the highway being tolled, while diversions and damaged surfaces in Sriperumbudur affected traffic movement and increased dust for bus passengers and two-wheeler riders.

NHAI officials from the Kancheepuram project unit said underpasses and flyovers at Sunguvarchathiram East and West, Santhavellore, Senthamangalam, Rajakulam, Vedal, Anna Cancer Institute and Ponnerikarai junctions had been completed and opened to traffic. Pending work at SIPCOT, Mambakkam, Enathur, Meenakshi Medical College junction, Beemanthangal and other locations is at various stages, with limited road closures permitted by the police affecting construction progress.

Officials said minor soil procurement issues had affected the project and retaining walls had been built at two locations. Of the 34.5 km covered by the pending works, 23.3 km had been completed and the remaining 11.22 km is scheduled for completion by August 2027. The wider six-laning project covering 70 km between Sriperumbudur and Walajahpet began towards the end of 2018 at a cost of Rs. 11.88 bn.

The six-laning of the 34.5-km Sriperumbudur-Karaipettai section of the Chennai-Bengaluru highway remains incomplete eight years after work began, causing severe hardship for commuters. The National Highways Authority of India (NHAI) has missed several deadlines and has completed only eight of the 17 planned flyovers, bridges and vehicular underpasses. The agency has set August 2027 as the revised completion deadline. The existing 15 m carriageway narrows to 7.5 m over nearly 3.5 km, where traffic is diverted to service lanes to enable construction of underpasses at Mambakkam and near SIPCOT in Sriperumbudur. Vehicles take between 60 and 90 minutes to cover the 10 km stretch between Sriperumbudur and Sunguvarchathiram, with conditions worsening during weekends and festival periods. During the recent Deepavali period, queues extended up to 9 km between Sunguvarchathiram and Sriperumbudur from November 5 to 10. Commuters reported that congestion persisted throughout the day despite the highway being tolled, while diversions and damaged surfaces in Sriperumbudur affected traffic movement and increased dust for bus passengers and two-wheeler riders. NHAI officials from the Kancheepuram project unit said underpasses and flyovers at Sunguvarchathiram East and West, Santhavellore, Senthamangalam, Rajakulam, Vedal, Anna Cancer Institute and Ponnerikarai junctions had been completed and opened to traffic. Pending work at SIPCOT, Mambakkam, Enathur, Meenakshi Medical College junction, Beemanthangal and other locations is at various stages, with limited road closures permitted by the police affecting construction progress. Officials said minor soil procurement issues had affected the project and retaining walls had been built at two locations. Of the 34.5 km covered by the pending works, 23.3 km had been completed and the remaining 11.22 km is scheduled for completion by August 2027. The wider six-laning project covering 70 km between Sriperumbudur and Walajahpet began towards the end of 2018 at a cost of Rs. 11.88 bn.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Goyal & Co. invests Rs 8.2 bn in Bengaluru's Titanium Tech Park

Goyal & Co. has invested approximately Rs 8.2 billion in Titanium Tech Park, a large-scale commercial development in Bengaluru's Whitefield Technology Corridor. Spread across 25 acres, the project has a total development potential of 5 million sq ft, with global companies Airbus and Caterpillar among its key occupiers.The development is planned in multiple phases, featuring Grade A office infrastructure, modern building systems and integrated employee amenities. Phase 1 comprises two operational G+15 office blocks offering 880,000 sq ft and 622,000 sq ft, respectively. Phase 2 will include..

Next Story
Infrastructure Urban

Tata Motors appoints GAMCO as commercial vehicle distributor in Syria

Tata Motors has signed a distribution agreement with Ghassan Aboud Automotive, appointing its subsidiary, Grand Auto & Machinery Co. (GAMCO), as the official distributor of Tata Motors commercial vehicles in Syria. The partnership aims to strengthen transportation, logistics and construction operations across the country while supporting its economic recovery and reconstruction.Under the agreement, GAMCO will introduce Tata Motors' commercial vehicle portfolio to the Syrian market, including cargo vehicles with capacities ranging from under one tonne to 60 tonnes and passenger transport so..

Next Story
Infrastructure Urban

EUROBOND sales rise 17.15% to Rs 1.52 bn in Q2 FY27

EUROBOND, the flagship brand of Euro Panel Products, reported a 17.15 per cent year-on-year increase in net sales to Rs 1.52 billion for the second quarter ended September 30, 2026. The company also registered a 27 per cent sequential growth in sales, supported by increasing order volumes and demand from the infrastructure and commercial construction sectors.Profit before tax stood at Rs 68.3 million during the quarter, reflecting the company's continued business expansion.The company recorded metal panel sales of 383,324 sq m in Q2 FY27, representing a 22.68 per cent increase compared to 312,..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code