Gadkari Calls for Better DPR Planning to Curb Highway Delays

Union Minister for Road Transport and Highways Nitin Gadkari has called for stronger preparation at the Detailed Project Report (DPR) stage to prevent delays and cost escalation in highway projects. He made the remarks while inaugurating a two-day national conclave on highway infrastructure at Ekta Nagar in Gujarat’s Narmada district.

Gadkari said project surveys, alignment planning, land acquisition, utility shifting and statutory clearances needed to be addressed before construction began. Better preparation at the initial stage, he said, would support smoother implementation and help ensure timely project delivery.

The conclave, titled Chintan Shivir 2026 – A National Conclave on Highway Infrastructure, is being held under the theme Gatishakti se Pragati. It brings together transport and Public Works Department (PWD) ministers from states, senior officials, implementing agencies and other stakeholders to examine challenges affecting highway development and infrastructure delivery.

The minister called for successful practices from individual states to be shared, assessed and replicated where suitable. He said highway development needed to focus on quality, safety, speed and world-class standards, with road safety integrated into planning and design from the outset. Accident-prone locations should be identified during planning so that suitable safeguards could be incorporated during construction.

Gadkari also highlighted the economic importance of seamless highway links connecting cities, towns, ports, markets and industrial centres. The conclave’s sessions cover PM GatiShakti and integrated infrastructure planning, land acquisition, Model Concession Agreements, safe and green highway design, road safety, toll reforms, quality assurance and project monitoring.

He urged wider adoption of new technologies, innovative construction methods and cost-effective materials to improve quality and reduce construction and maintenance expenses. Discussions will also address environmental sustainability, wildlife protection and recycled materials. An Environment and Wildlife Mitigation Measures document and a BRICS Compendium on Perspectives in Sustainable Transport were launched at the inaugural session. Technology-led tolling reforms, including the FASTag Annual Pass and Multi-Lane Free Flow (MLFF), are also being discussed.

Union Minister for Road Transport and Highways Nitin Gadkari has called for stronger preparation at the Detailed Project Report (DPR) stage to prevent delays and cost escalation in highway projects. He made the remarks while inaugurating a two-day national conclave on highway infrastructure at Ekta Nagar in Gujarat’s Narmada district. Gadkari said project surveys, alignment planning, land acquisition, utility shifting and statutory clearances needed to be addressed before construction began. Better preparation at the initial stage, he said, would support smoother implementation and help ensure timely project delivery. The conclave, titled Chintan Shivir 2026 – A National Conclave on Highway Infrastructure, is being held under the theme Gatishakti se Pragati. It brings together transport and Public Works Department (PWD) ministers from states, senior officials, implementing agencies and other stakeholders to examine challenges affecting highway development and infrastructure delivery. The minister called for successful practices from individual states to be shared, assessed and replicated where suitable. He said highway development needed to focus on quality, safety, speed and world-class standards, with road safety integrated into planning and design from the outset. Accident-prone locations should be identified during planning so that suitable safeguards could be incorporated during construction. Gadkari also highlighted the economic importance of seamless highway links connecting cities, towns, ports, markets and industrial centres. The conclave’s sessions cover PM GatiShakti and integrated infrastructure planning, land acquisition, Model Concession Agreements, safe and green highway design, road safety, toll reforms, quality assurance and project monitoring. He urged wider adoption of new technologies, innovative construction methods and cost-effective materials to improve quality and reduce construction and maintenance expenses. Discussions will also address environmental sustainability, wildlife protection and recycled materials. An Environment and Wildlife Mitigation Measures document and a BRICS Compendium on Perspectives in Sustainable Transport were launched at the inaugural session. Technology-led tolling reforms, including the FASTag Annual Pass and Multi-Lane Free Flow (MLFF), are also being discussed.

Related Stories

Gold Stories

Next Story
Technology

Where Infrastructure Meets Intelligence: Inside Bentley's Year inc

Oct 28, 2026  @Tanveer PadodeA first-hand account of Bentley’s 2026 awards, where AI, digital twins and engineering innovation are reshaping infrastructure delivery.- By Tanveer Padode, CEO, IMPACCT: A first-hand account of Bentley’s 2026 awards, where AI, digital twins and engineering innovation are reshaping infrastructure delivery.Two days in SingaporeConstruction is won or lost in two places: how a project is designed and how it is delivered. Technology has promised to improve both for years, and the question I carried into Bentley's Year in Infrastructure, held at the Fairmont Si..

Next Story
Infrastructure Transport

Vaishnaw Inaugurates Two Rail Sections in Madhya Pradesh

Railway Minister Ashwini Vaishnaw on October 24 inaugurated the Satna-Devendranagar and Rewa-Churhat rail sections under the Lalitpur-Singrauli Railway Project in Madhya Pradesh. He also flagged off the new Devendranagar-Churhat passenger train service through video conferencing. Chief Minister Dr Mohan Yadav attended the event. The new Rewa-Churhat railway line, which extends approximately 65 km, was built at a cost of over Rs. 10 bn. The 53 km Satna-Devendranagar line was constructed at a cost of over Rs. 8 bn. The passenger service is expected to provide improved rail access to residents in..

Next Story
Infrastructure Transport

Railways Minister to Inaugurate New Rail Sections Covering 118 km

Railways Minister Ashwini Vaishnaw will inaugurate the Satna-Devendra Nagar and Rewa-Churhat rail sections in Madhya Pradesh on October 24. The two sections have a combined length of 118 km and are intended to improve passenger and freight connectivity across the region. Vaishnaw will also flag off a new train service between Devendra Nagar and Churhat. Madhya Pradesh Chief Minister Mohan Yadav will attend the inauguration programme, according to information released by the Ministry of Railways. The 53-km Satna-Devendra Nagar section is expected to improve rail access to Satna, Nagod, Devendra..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code