Gurugram Plans Rs. 7.76 bn Elevated Corridor to Vatika Chowk
ROADS & HIGHWAYS

Gurugram Plans Rs. 7.76 bn Elevated Corridor to Vatika Chowk

Gurugram is set to receive a 4.23 km elevated corridor along the Southern Peripheral Road (SPR) between NH-48 and Vatika Chowk. The project, estimated to cost Rs. 7.76 bn excluding GST, will include interchanges, loops and ramps, with construction scheduled over 30 months.

The Gurugram Metropolitan Development Authority (GMDA) has invited bids for the work under Package 1 of the SPR, covering km 0+000 to km 4+230. The tender opened on October 1, 2026, while the deadline for submitting bids is November 18, 2026. The project will be implemented through the Engineering, Procurement and Construction (EPC) model.

According to the tender documents, the 30-month period applies to construction and does not represent a confirmed opening date because the bidding process is still under way. The contract also includes a 10-year maintenance period. The tender has been assigned the identification number 2026_HRY_551863_1.

The corridor forms part of wider road infrastructure improvements around Gurugram and the NH-48 route. Earlier works on the Gurgaon-Kotputli-Jaipur section included the foundation stones for four flyovers and nine foot overbridges, alongside other engineering measures, at an estimated cost of Rs. 2.82 bn. These works were intended to improve safety and traffic movement in Gurgaon, Rewari and nearby areas while addressing congestion and waterlogging.

Further connectivity work is also under way in the wider region. In July 2026, the Union Cabinet approved an 8.1 km, six-lane tunnel linking the Dwarka Expressway with Nelson Mandela Marg in Vasant Kunj, Delhi, at a capital cost of Rs. 69.7 bn. The government said the project would improve links between West and South Delhi and support traffic movement from Gurugram, Dwarka, the Indira Gandhi International Airport and West Delhi towards South Delhi.

Gurugram is set to receive a 4.23 km elevated corridor along the Southern Peripheral Road (SPR) between NH-48 and Vatika Chowk. The project, estimated to cost Rs. 7.76 bn excluding GST, will include interchanges, loops and ramps, with construction scheduled over 30 months. The Gurugram Metropolitan Development Authority (GMDA) has invited bids for the work under Package 1 of the SPR, covering km 0+000 to km 4+230. The tender opened on October 1, 2026, while the deadline for submitting bids is November 18, 2026. The project will be implemented through the Engineering, Procurement and Construction (EPC) model. According to the tender documents, the 30-month period applies to construction and does not represent a confirmed opening date because the bidding process is still under way. The contract also includes a 10-year maintenance period. The tender has been assigned the identification number 2026_HRY_551863_1. The corridor forms part of wider road infrastructure improvements around Gurugram and the NH-48 route. Earlier works on the Gurgaon-Kotputli-Jaipur section included the foundation stones for four flyovers and nine foot overbridges, alongside other engineering measures, at an estimated cost of Rs. 2.82 bn. These works were intended to improve safety and traffic movement in Gurgaon, Rewari and nearby areas while addressing congestion and waterlogging. Further connectivity work is also under way in the wider region. In July 2026, the Union Cabinet approved an 8.1 km, six-lane tunnel linking the Dwarka Expressway with Nelson Mandela Marg in Vasant Kunj, Delhi, at a capital cost of Rs. 69.7 bn. The government said the project would improve links between West and South Delhi and support traffic movement from Gurugram, Dwarka, the Indira Gandhi International Airport and West Delhi towards South Delhi.

Related Stories

Gold Stories

Next Story
Technology

Where Infrastructure Meets Intelligence: Inside Bentley's Year inc

Oct 28, 2026  @Tanveer PadodeA first-hand account of Bentley’s 2026 awards, where AI, digital twins and engineering innovation are reshaping infrastructure delivery.- By Tanveer Padode, CEO, IMPACCT: A first-hand account of Bentley’s 2026 awards, where AI, digital twins and engineering innovation are reshaping infrastructure delivery.Two days in SingaporeConstruction is won or lost in two places: how a project is designed and how it is delivered. Technology has promised to improve both for years, and the question I carried into Bentley's Year in Infrastructure, held at the Fairmont Si..

Next Story
Infrastructure Transport

Vaishnaw Inaugurates Two Rail Sections in Madhya Pradesh

Railway Minister Ashwini Vaishnaw on October 24 inaugurated the Satna-Devendranagar and Rewa-Churhat rail sections under the Lalitpur-Singrauli Railway Project in Madhya Pradesh. He also flagged off the new Devendranagar-Churhat passenger train service through video conferencing. Chief Minister Dr Mohan Yadav attended the event. The new Rewa-Churhat railway line, which extends approximately 65 km, was built at a cost of over Rs. 10 bn. The 53 km Satna-Devendranagar line was constructed at a cost of over Rs. 8 bn. The passenger service is expected to provide improved rail access to residents in..

Next Story
Infrastructure Transport

Railways Minister to Inaugurate New Rail Sections Covering 118 km

Railways Minister Ashwini Vaishnaw will inaugurate the Satna-Devendra Nagar and Rewa-Churhat rail sections in Madhya Pradesh on October 24. The two sections have a combined length of 118 km and are intended to improve passenger and freight connectivity across the region. Vaishnaw will also flag off a new train service between Devendra Nagar and Churhat. Madhya Pradesh Chief Minister Mohan Yadav will attend the inauguration programme, according to information released by the Ministry of Railways. The 53-km Satna-Devendra Nagar section is expected to improve rail access to Satna, Nagod, Devendra..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code