Jammu And Kashmir To Build 646 Rural Roads Under PMGSY IV
ROADS & HIGHWAYS

Jammu And Kashmir To Build 646 Rural Roads Under PMGSY IV

Jammu and Kashmir is to construct 646 rural roads covering 3,381 kilometres at an estimated cost of Rs 77,900 million (mn) under the first two batches of Pradhan Mantri Gram Sadak Yojana IV, which is expected to provide all?weather road connectivity to 792 habitations across the Union Territory. The programme is described as the largest rural road connectivity initiative undertaken in the region. The projects form part of efforts to strengthen links to markets, education, healthcare, tourism and employment.

The details emerged during a high?level review meeting chaired by Chief Secretary Atal Dulloo, who assessed progress of PMGSY phases one to three and reviewed the implementation strategy for PMGSY IV. Officials presented technical and financial schedules for the first two batches and outlined timelines for statutory clearances. The meeting emphasised coordination among departments to expedite execution.

Batch one for 2025?26 comprises 316 roads with a total length of 1,781 kilometres at a sanctioned cost of Rs 42,240 mn. Of these, 235 works have commenced and expenditure of nearly Rs 2,700 mn has been incurred to date. The second batch for 2026?27 comprises 330 sanctioned roads, all of which have received technical approval and are at an advanced stage of tendering.

The Chief Secretary noted that the programme would significantly improve access to remote habitations and directed the Public Works Roads and Buildings Department to ensure timely execution of projects. He asked the department to remove bottlenecks related to forest clearances, land acquisition, utility shifting and other statutory approvals through coordinated efforts with Divisional Commissioners, Deputy Commissioners and the Forest Department. Administrative measures were outlined to monitor compliance and address impediments swiftly.

Dulloo further instructed Deputy Commissioners to closely monitor works in their respective districts and to ensure that pending projects under earlier phases are completed within stipulated deadlines while maintaining implementation pace under PMGSY IV. District authorities were advised to provide regular progress updates and to prioritise actions that would accelerate delivery of all?weather connectivity.

Jammu and Kashmir is to construct 646 rural roads covering 3,381 kilometres at an estimated cost of Rs 77,900 million (mn) under the first two batches of Pradhan Mantri Gram Sadak Yojana IV, which is expected to provide all?weather road connectivity to 792 habitations across the Union Territory. The programme is described as the largest rural road connectivity initiative undertaken in the region. The projects form part of efforts to strengthen links to markets, education, healthcare, tourism and employment. The details emerged during a high?level review meeting chaired by Chief Secretary Atal Dulloo, who assessed progress of PMGSY phases one to three and reviewed the implementation strategy for PMGSY IV. Officials presented technical and financial schedules for the first two batches and outlined timelines for statutory clearances. The meeting emphasised coordination among departments to expedite execution. Batch one for 2025?26 comprises 316 roads with a total length of 1,781 kilometres at a sanctioned cost of Rs 42,240 mn. Of these, 235 works have commenced and expenditure of nearly Rs 2,700 mn has been incurred to date. The second batch for 2026?27 comprises 330 sanctioned roads, all of which have received technical approval and are at an advanced stage of tendering. The Chief Secretary noted that the programme would significantly improve access to remote habitations and directed the Public Works Roads and Buildings Department to ensure timely execution of projects. He asked the department to remove bottlenecks related to forest clearances, land acquisition, utility shifting and other statutory approvals through coordinated efforts with Divisional Commissioners, Deputy Commissioners and the Forest Department. Administrative measures were outlined to monitor compliance and address impediments swiftly. Dulloo further instructed Deputy Commissioners to closely monitor works in their respective districts and to ensure that pending projects under earlier phases are completed within stipulated deadlines while maintaining implementation pace under PMGSY IV. District authorities were advised to provide regular progress updates and to prioritise actions that would accelerate delivery of all?weather connectivity.

Related Stories

Gold Stories

Next Story
Real Estate

LML Realty Sells Out Jhirka Valley Industrial Park in Haryana

LML Realty, the real estate arm of LML Group, recently announced the complete sell-out of its Jhirka Valley Industrial Park in Haryana, with over 1.17 million sq ft of industrial space acquired by more than 50 companies. With utilities and internal infrastructure in place, the company has commenced plot handovers, enabling buyers to begin construction and establish their operations.The industrial park has attracted companies across diverse sectors, including chemicals, metals and alloys, textiles, electrical equipment, energy, logistics, construction, polymers and engineering. Key buyers inclu..

Next Story
Real Estate

WSB Real Estate Partners Exits Six Housing Investments

WSB Real Estate Partners recently announced the successful exit of six residential investments across Bengaluru, Mumbai Metropolitan Region (MMR) and National Capital Region (NCR), delivering an average internal rate of return (IRR) of 19–21 per cent and an overall investment return of 1.4 times.The real estate-focused investment firm invested approximately Rs 7 billion across six mid-affordable housing projects over the past four years. All six investments were fully repaid between April and November 2026, several months ahead of their original investment tenures.WSB collaborated with sever..

Next Story
Infrastructure Transport

Aluminium Industry Seeks Policy Support for Rs 4 Trillion Investment

The Aluminium Association of India (AAI) has recently urged the government to introduce supportive policy measures to safeguard the sector’s proposed Rs 4 trillion investment pipeline. The association highlighted the need for a predictable policy framework to strengthen domestic manufacturing, expand production capacity and reduce import dependence.AAI submitted its recommendations for the Union Budget 2027-28 to the Ministries of Finance, Commerce and Industry, and Mines, along with the Department for Promotion of Industry and Internal Trade (DPIIT).India’s aluminium demand is projected t..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code