Jammu And Kashmir To Build 646 Rural Roads Under PMGSY IV
ROADS & HIGHWAYS

Jammu And Kashmir To Build 646 Rural Roads Under PMGSY IV

Jammu and Kashmir is to construct 646 rural roads covering 3,381 kilometres at an estimated cost of Rs 77,900 million (mn) under the first two batches of Pradhan Mantri Gram Sadak Yojana IV, which is expected to provide all?weather road connectivity to 792 habitations across the Union Territory. The programme is described as the largest rural road connectivity initiative undertaken in the region. The projects form part of efforts to strengthen links to markets, education, healthcare, tourism and employment.

The details emerged during a high?level review meeting chaired by Chief Secretary Atal Dulloo, who assessed progress of PMGSY phases one to three and reviewed the implementation strategy for PMGSY IV. Officials presented technical and financial schedules for the first two batches and outlined timelines for statutory clearances. The meeting emphasised coordination among departments to expedite execution.

Batch one for 2025?26 comprises 316 roads with a total length of 1,781 kilometres at a sanctioned cost of Rs 42,240 mn. Of these, 235 works have commenced and expenditure of nearly Rs 2,700 mn has been incurred to date. The second batch for 2026?27 comprises 330 sanctioned roads, all of which have received technical approval and are at an advanced stage of tendering.

The Chief Secretary noted that the programme would significantly improve access to remote habitations and directed the Public Works Roads and Buildings Department to ensure timely execution of projects. He asked the department to remove bottlenecks related to forest clearances, land acquisition, utility shifting and other statutory approvals through coordinated efforts with Divisional Commissioners, Deputy Commissioners and the Forest Department. Administrative measures were outlined to monitor compliance and address impediments swiftly.

Dulloo further instructed Deputy Commissioners to closely monitor works in their respective districts and to ensure that pending projects under earlier phases are completed within stipulated deadlines while maintaining implementation pace under PMGSY IV. District authorities were advised to provide regular progress updates and to prioritise actions that would accelerate delivery of all?weather connectivity.

Jammu and Kashmir is to construct 646 rural roads covering 3,381 kilometres at an estimated cost of Rs 77,900 million (mn) under the first two batches of Pradhan Mantri Gram Sadak Yojana IV, which is expected to provide all?weather road connectivity to 792 habitations across the Union Territory. The programme is described as the largest rural road connectivity initiative undertaken in the region. The projects form part of efforts to strengthen links to markets, education, healthcare, tourism and employment. The details emerged during a high?level review meeting chaired by Chief Secretary Atal Dulloo, who assessed progress of PMGSY phases one to three and reviewed the implementation strategy for PMGSY IV. Officials presented technical and financial schedules for the first two batches and outlined timelines for statutory clearances. The meeting emphasised coordination among departments to expedite execution. Batch one for 2025?26 comprises 316 roads with a total length of 1,781 kilometres at a sanctioned cost of Rs 42,240 mn. Of these, 235 works have commenced and expenditure of nearly Rs 2,700 mn has been incurred to date. The second batch for 2026?27 comprises 330 sanctioned roads, all of which have received technical approval and are at an advanced stage of tendering. The Chief Secretary noted that the programme would significantly improve access to remote habitations and directed the Public Works Roads and Buildings Department to ensure timely execution of projects. He asked the department to remove bottlenecks related to forest clearances, land acquisition, utility shifting and other statutory approvals through coordinated efforts with Divisional Commissioners, Deputy Commissioners and the Forest Department. Administrative measures were outlined to monitor compliance and address impediments swiftly. Dulloo further instructed Deputy Commissioners to closely monitor works in their respective districts and to ensure that pending projects under earlier phases are completed within stipulated deadlines while maintaining implementation pace under PMGSY IV. District authorities were advised to provide regular progress updates and to prioritise actions that would accelerate delivery of all?weather connectivity.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

MMRDA Targets Completion of Projects by December 2028

The Mumbai Metropolitan Region Development Authority (MMRDA) is targeting the completion of all its ongoing infrastructure projects by December 2028, a year ahead of its December 2029 deadline, Metropolitan Commissioner Dr Sanjay Mukherjee has said.Speaking at the sixth edition of the Real Estate & Infrastructure Investors' Summit (REIIS) 2026 in Mumbai, Mukherjee said the authority was developing an integrated network of roads, tunnels, sea links and Metro corridors under its broader vision of “Mumbai in 59 Minutes”.The objective is to improve east-west and north-south connectivity an..

Next Story
Building Material

High-Performance Façades Gain Ground in Indian Buildings

High-performance façades are gaining greater importance in Indian architecture as developers and architects increasingly focus on energy efficiency, thermal comfort and building performance, according to Shankar Fenestrations & Glasses.The company said modern façade systems are increasingly being considered as part of a building's overall performance strategy rather than being used primarily as aesthetic elements.High-performance glass, curtain wall systems and structural glazing can contribute to thermal regulation, solar control, daylight management and indoor comfort. Their growing ad..

Next Story
Technology

SPML Infra's 104.4 kWh BESS Battery Pack Clears Global Tests

SPML Infra has announced that its proprietary 104.4 kWh Battery Energy Storage System (BESS) battery pack has completed key international safety, performance and transportation testing and certification requirements, marking a step towards its commercial deployment.Developed under the company's own intellectual property, the battery pack has completed requirements under UL9540A, IEC 62619, IEC 63056, IEC 60730, IEC 61000-6-2, IEC 61000-6-4 and UN38.3 standards.The testing covers areas including thermal runaway safety, battery performance, system functional safety, electromagnetic compatibility..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code