Kerala NH 66 Stretch Set For Completion In 2028
ROADS & HIGHWAYS

Kerala NH 66 Stretch Set For Completion In 2028

Construction of the 645 km-long Kerala stretch of National Highway 66 (NH 66) that will run along the coastline and link Thalapady on the Karnataka border to Karode on the Tamil Nadu border is scheduled for completion by May 2028. The Road Transport and Highways Minister replied in the Lok Sabha that main road works will finish by 30 April 2027, with viaduct construction requiring another year. The project is expected to reduce travel times between major cities and ease congestion while supporting logistics, industry and tourism.

Apart from the Thalapady-Chengala and Vengalam-Ramanattukara corridors inaugurated in March, about 85 per cent of works have been completed in seven key stretches. The Kappirikadavu-Thalikulam, Thalikulam-Kodungallur and Kollam Bypass-Kadambattukonam spans are nearly 95 per cent complete, while the Taliparamba-Muzhuppilangad reach is 84 per cent and Azhiyur-Vengalam is 68 per cent. Contractors have had to source materials from neighbouring states owing to local shortages.

NHAI engineers attributed delays to the non-availability of rock aggregate and suitable earth within the state, and a recent ban on cross-border transportation of rock aggregate by Tamil Nadu further affected progress. The Public Works Department minister conducted three review meetings with NHAI officials to raise scarcity of materials, shortage of labour and monsoon-related slowdowns, and the chief minister has taken up the ban with neighbouring authorities in hopes of a resolution. Labour shortages were aggravated after many migrant workers from West Bengal left for state elections in March and have not returned, and local protests seeking underpasses have disrupted work at certain sites.

Inadequate drainage leading to severe water seepage caused structural failures and collapse of retaining walls at several locations, and investigations found shortcomings in subsoil and geotechnical surveys, earth-wall designs and monitoring. The ministry appointed an expert committee that recommended fresh geotechnical investigations, pullout tests on reinforced earth walls, reverification of ground conditions after improvement and stability analyses. Based on the panel's findings, NHAI has implemented rectification measures and imposed financial penalties worth multiple million (mn) Rs and temporary debarment on some major concessionaires.

Construction of the 645 km-long Kerala stretch of National Highway 66 (NH 66) that will run along the coastline and link Thalapady on the Karnataka border to Karode on the Tamil Nadu border is scheduled for completion by May 2028. The Road Transport and Highways Minister replied in the Lok Sabha that main road works will finish by 30 April 2027, with viaduct construction requiring another year. The project is expected to reduce travel times between major cities and ease congestion while supporting logistics, industry and tourism. Apart from the Thalapady-Chengala and Vengalam-Ramanattukara corridors inaugurated in March, about 85 per cent of works have been completed in seven key stretches. The Kappirikadavu-Thalikulam, Thalikulam-Kodungallur and Kollam Bypass-Kadambattukonam spans are nearly 95 per cent complete, while the Taliparamba-Muzhuppilangad reach is 84 per cent and Azhiyur-Vengalam is 68 per cent. Contractors have had to source materials from neighbouring states owing to local shortages. NHAI engineers attributed delays to the non-availability of rock aggregate and suitable earth within the state, and a recent ban on cross-border transportation of rock aggregate by Tamil Nadu further affected progress. The Public Works Department minister conducted three review meetings with NHAI officials to raise scarcity of materials, shortage of labour and monsoon-related slowdowns, and the chief minister has taken up the ban with neighbouring authorities in hopes of a resolution. Labour shortages were aggravated after many migrant workers from West Bengal left for state elections in March and have not returned, and local protests seeking underpasses have disrupted work at certain sites. Inadequate drainage leading to severe water seepage caused structural failures and collapse of retaining walls at several locations, and investigations found shortcomings in subsoil and geotechnical surveys, earth-wall designs and monitoring. The ministry appointed an expert committee that recommended fresh geotechnical investigations, pullout tests on reinforced earth walls, reverification of ground conditions after improvement and stability analyses. Based on the panel's findings, NHAI has implemented rectification measures and imposed financial penalties worth multiple million (mn) Rs and temporary debarment on some major concessionaires.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

TransIndia Launches World View Collection at Meridian

TransIndia Group has recently launched ‘The World View Collection’ at TransIndia Meridian, its residential development in Mumbai’s Sion-Matunga Corridor. The campaign introduces residences located on the 22nd floor and above, offering expansive views of the cityscape, Eastern Bay and the sea.The collection positions elevation as an integral part of the living experience, with the higher-floor homes designed around openness, changing skylines and wider city views. Rather than focusing only on floor height, the campaign highlights how elevated residences can offer a different perspective o..

Next Story
Real Estate

Villaro Design Studio Opens on MG Road in Delhi

Furniture designer Yuvraj Vohra has recently launched the new Villaro Design Studio on MG Road, Delhi, introducing a furniture brand built around an architectural approach to design, materiality and craftsmanship.Trained as an architect, Vohra approaches furniture as an integral part of the spatial experience rather than as standalone objects. Villaro's design philosophy focuses on proportion, material expression and the relationship between furniture and its surrounding architecture.The collection explores combinations of stone, marble, wood, metal and upholstery, with materials treated as st..

Next Story
Infrastructure Urban

India-Belgium Trade Shows Signs of Recovery in FY2026

India-Belgium economic relations are gaining renewed momentum following Belgian Prime Minister Bart De Wever’s three-day official visit to India from September 2–4, 2026. The visit, the first by a Belgian Prime Minister to India in two decades, focused on strengthening cooperation across trade, investment, defence, technology, connectivity and logistics.Belgium is an important European investment and trading partner for India, with cumulative foreign direct investment inflows of around $4.25 billion between April 2000 and March 2026. The country is a major European manufacturing, trade and..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code