Kerala NH 66 Stretch Set For Completion In 2028
ROADS & HIGHWAYS

Kerala NH 66 Stretch Set For Completion In 2028

Construction of the 645 km-long Kerala stretch of National Highway 66 (NH 66) that will run along the coastline and link Thalapady on the Karnataka border to Karode on the Tamil Nadu border is scheduled for completion by May 2028. The Road Transport and Highways Minister replied in the Lok Sabha that main road works will finish by 30 April 2027, with viaduct construction requiring another year. The project is expected to reduce travel times between major cities and ease congestion while supporting logistics, industry and tourism.

Apart from the Thalapady-Chengala and Vengalam-Ramanattukara corridors inaugurated in March, about 85 per cent of works have been completed in seven key stretches. The Kappirikadavu-Thalikulam, Thalikulam-Kodungallur and Kollam Bypass-Kadambattukonam spans are nearly 95 per cent complete, while the Taliparamba-Muzhuppilangad reach is 84 per cent and Azhiyur-Vengalam is 68 per cent. Contractors have had to source materials from neighbouring states owing to local shortages.

NHAI engineers attributed delays to the non-availability of rock aggregate and suitable earth within the state, and a recent ban on cross-border transportation of rock aggregate by Tamil Nadu further affected progress. The Public Works Department minister conducted three review meetings with NHAI officials to raise scarcity of materials, shortage of labour and monsoon-related slowdowns, and the chief minister has taken up the ban with neighbouring authorities in hopes of a resolution. Labour shortages were aggravated after many migrant workers from West Bengal left for state elections in March and have not returned, and local protests seeking underpasses have disrupted work at certain sites.

Inadequate drainage leading to severe water seepage caused structural failures and collapse of retaining walls at several locations, and investigations found shortcomings in subsoil and geotechnical surveys, earth-wall designs and monitoring. The ministry appointed an expert committee that recommended fresh geotechnical investigations, pullout tests on reinforced earth walls, reverification of ground conditions after improvement and stability analyses. Based on the panel's findings, NHAI has implemented rectification measures and imposed financial penalties worth multiple million (mn) Rs and temporary debarment on some major concessionaires.

Construction of the 645 km-long Kerala stretch of National Highway 66 (NH 66) that will run along the coastline and link Thalapady on the Karnataka border to Karode on the Tamil Nadu border is scheduled for completion by May 2028. The Road Transport and Highways Minister replied in the Lok Sabha that main road works will finish by 30 April 2027, with viaduct construction requiring another year. The project is expected to reduce travel times between major cities and ease congestion while supporting logistics, industry and tourism. Apart from the Thalapady-Chengala and Vengalam-Ramanattukara corridors inaugurated in March, about 85 per cent of works have been completed in seven key stretches. The Kappirikadavu-Thalikulam, Thalikulam-Kodungallur and Kollam Bypass-Kadambattukonam spans are nearly 95 per cent complete, while the Taliparamba-Muzhuppilangad reach is 84 per cent and Azhiyur-Vengalam is 68 per cent. Contractors have had to source materials from neighbouring states owing to local shortages. NHAI engineers attributed delays to the non-availability of rock aggregate and suitable earth within the state, and a recent ban on cross-border transportation of rock aggregate by Tamil Nadu further affected progress. The Public Works Department minister conducted three review meetings with NHAI officials to raise scarcity of materials, shortage of labour and monsoon-related slowdowns, and the chief minister has taken up the ban with neighbouring authorities in hopes of a resolution. Labour shortages were aggravated after many migrant workers from West Bengal left for state elections in March and have not returned, and local protests seeking underpasses have disrupted work at certain sites. Inadequate drainage leading to severe water seepage caused structural failures and collapse of retaining walls at several locations, and investigations found shortcomings in subsoil and geotechnical surveys, earth-wall designs and monitoring. The ministry appointed an expert committee that recommended fresh geotechnical investigations, pullout tests on reinforced earth walls, reverification of ground conditions after improvement and stability analyses. Based on the panel's findings, NHAI has implemented rectification measures and imposed financial penalties worth multiple million (mn) Rs and temporary debarment on some major concessionaires.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train’s Surat-Vapi Section Set for 2027

The first section of the Mumbai-Ahmedabad Bullet Train corridor, linking Surat and Vapi, is targeted to begin services in 2027. Construction is expected to be completed by December 2026, while Railway Minister Ashwini Vaishnaw has indicated that an inauguration could take place around the middle of 2027. The National High Speed Rail Corporation (NHSRCL) said the train being manufactured in India is expected to reach the tracks around April or May 2027. The train will undergo extensive testing before the section is opened for passenger services. The project began construction in 2021 and includ..

Next Story
Infrastructure Transport

Indian Railways Approves Four Projects Worth Rs. 7.36 bn Across Four States

Indian Railways has approved four projects with a combined value of Rs. 7.36 bn across Uttar Pradesh, Maharashtra, Andhra Pradesh and Gujarat. The programme covers train protection, signalling, electric traction supply and a road overbridge, with each project assigned to a different railway zone. In Uttar Pradesh, Rs. 2.52 bn has been approved to extend the Kavach 4.0 automatic train protection system across 607.7 km in the Lucknow Division of North Eastern Railway. The system monitors train movements and can apply the brakes if a driver fails to observe a signal or exceeds a safe speed. The w..

Next Story
Infrastructure Urban

Chandru Raheja Sells 1.49% Stake in Mindspace REIT for Rs. 5 bn

Billionaire Chandru Lachmandas Raheja has sold a 1.49 per cent holding in Mindspace Business Parks REIT for Rs. 5 bn through a bulk deal on the BSE. The transaction involved 9.9 mn units and was executed at an average price of Rs. 505 per unit, according to exchange data. Following the sale, units of Mindspace Business Parks REIT were trading 0.18 per cent lower at Rs. 504.05 on Tuesday. Exchange data did not identify the buyers involved in the transaction. Raheja is the chairman of real estate company K Raheja Corp. The sale involved 99,00,990 units, representing 1.49 per cent of the Mumbai-b..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code