Mysuru to Reopen Three Arterial Roads Before Dasara
ROADS & HIGHWAYS

Mysuru to Reopen Three Arterial Roads Before Dasara

The Mysuru City Corporation (MCC) and the Public Works Department (PWD) will reopen three major arterial road stretches by October 5, 2026, to manage the expected increase in traffic during the Dasara celebrations. The roads are Manandavadi Road, Manipal Junction Road and Banni Mantap Road.

The three stretches are nearing completion of white-topping, or concrete road construction, along with the relocation of underground utilities. The work is intended to improve traffic movement during the festival period, when Mysuru typically receives a significant increase in visitors and vehicles.

Concretization began in April 2026 under Phase 1 of the project, and final work is now being completed before the roads are opened to the public. Drainage conduits, water pipelines, power cables and telecom networks were shifted to side corridors before the road surfaces were laid, a measure intended to reduce the need for future road cutting.

The Mysuru district administration has also ordered a temporary suspension of white-topping work on the remaining nine major city corridors from early October until October 21, 2026. The pause is intended to prevent work-related bottlenecks during the high-density holiday period and keep key routes available for festival traffic.

The broader project covers the concretization of 46.088 km of important city roads at an estimated cost of Rs. 3.94 bn. It is planned to provide a 20-year pothole-free lifespan, improve visibility for drivers and lower long-term maintenance costs. The reopening of the three stretches ahead of Dasara is expected to provide additional capacity on the city’s arterial network during the celebrations.

The Mysuru City Corporation (MCC) and the Public Works Department (PWD) will reopen three major arterial road stretches by October 5, 2026, to manage the expected increase in traffic during the Dasara celebrations. The roads are Manandavadi Road, Manipal Junction Road and Banni Mantap Road. The three stretches are nearing completion of white-topping, or concrete road construction, along with the relocation of underground utilities. The work is intended to improve traffic movement during the festival period, when Mysuru typically receives a significant increase in visitors and vehicles. Concretization began in April 2026 under Phase 1 of the project, and final work is now being completed before the roads are opened to the public. Drainage conduits, water pipelines, power cables and telecom networks were shifted to side corridors before the road surfaces were laid, a measure intended to reduce the need for future road cutting. The Mysuru district administration has also ordered a temporary suspension of white-topping work on the remaining nine major city corridors from early October until October 21, 2026. The pause is intended to prevent work-related bottlenecks during the high-density holiday period and keep key routes available for festival traffic. The broader project covers the concretization of 46.088 km of important city roads at an estimated cost of Rs. 3.94 bn. It is planned to provide a 20-year pothole-free lifespan, improve visibility for drivers and lower long-term maintenance costs. The reopening of the three stretches ahead of Dasara is expected to provide additional capacity on the city’s arterial network during the celebrations.

Related Stories

Gold Stories

Next Story
Equipment

TIL Revenue Surges 143% to Rs 1.98 Billion in Q2 FY27

TIL Limited, a manufacturer of material handling and infrastructure equipment, has reported a 143 per cent year-on-year increase in consolidated revenue to Rs 1.98 billion for the second quarter of FY27, compared with Rs 814.5 million in the corresponding period last year. Consolidated EBITDA surged 433 per cent to Rs 173.7 million, while EBITDA margin improved to 8.8 per cent from 4 per cent.The performance was supported by equipment deliveries, defence contracts, aftermarket services and the contribution of Tulip Compression Private Limited (TCPL), which became a majority-owned subsidiary in..

Next Story
Infrastructure Transport

India to Develop Civil Aircraft Within Two Years, Build 100 Airports

India aims to develop its own civil aircraft within the next two years as it seeks to strengthen domestic aerospace capabilities and reduce dependence on foreign aircraft manufacturers, Civil Aviation Minister Ram Mohan Naidu said on November 12. He said the ambition extended beyond assembling aircraft to developing expertise in aircraft design and production. Speaking at the inaugural session of the Confederation of Indian Industry (CII) Partnership Summit 2026 in Visakhapatnam, Naidu said India wanted to establish itself as a major aerospace manufacturing hub. The government’s approach is ..

Next Story
Infrastructure Urban

Two Korean Firms to Invest Rs. 13.7 bn in Tamil Nadu

Two South Korean automotive component suppliers to Hyundai and Kia plan to invest a combined Rs. 13.7 bn in Tamil Nadu over the next five years, according to sources in the state industries department. The proposed investments come after a political dispute over the reported movement of some automotive investments to Andhra Pradesh. The state government has received letters of intent (LoIs) from Hwashin and Seoyon, while memorandums of understanding (MoUs) are expected to be signed shortly. Both companies communicated their investment plans in letters dated November 11, reaffirming their inten..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code