NHAI Clarifies Road Surface Cave In On Delhi–Dehradun Corridor
ROADS & HIGHWAYS

NHAI Clarifies Road Surface Cave In On Delhi–Dehradun Corridor

The National Highways Authority of India issued a clarification saying a road surface cave in on the Delhi–Dehradun Economic Corridor resulted from localised water stagnation following rains and from constraints in commissioning the permanent cross drainage system at the site. The authority stated the cave in was observed at Km 55+480 during routine route patrolling in the early hours of first July 2026. After the affected stretch was detected the project team initiated restoration works without delay and prioritised repair to restore safe and uninterrupted traffic movement.

The agency said the location was repaired on priority and that interim measures were put in place while permanent works remain pending. As a temporary step the authority commenced construction of a parallel drain of approximately one point five km and is redesigning the drainage gradient to ensure safe disposal of rainwater until the permanent system can be commissioned. The site has been placed under continuous monitoring and additional resources have been deployed to manage the situation and maintain traffic flow.

The office explained that the balancing culvert designed to convey rainwater across the carriageway could not be commissioned because local residents have been using the culvert opening as a vehicular crossing and resisted commissioning. It also noted that permanent slope protection and chute drain works remain pending owing to an ongoing land related dispute which has prevented execution of the approved drainage infrastructure. The authority indicated these constraints contributed to the localised stagnation that affected the carriageway.

The statement said the agency remains committed to maintaining highway safety through timely maintenance and proactive asset management and will keep the location under observation until permanent works can be completed. It added that necessary personnel and equipment have been mobilised to ensure safe and smooth traffic movement and that any further remedial action will be taken in coordination with relevant stakeholders.

The National Highways Authority of India issued a clarification saying a road surface cave in on the Delhi–Dehradun Economic Corridor resulted from localised water stagnation following rains and from constraints in commissioning the permanent cross drainage system at the site. The authority stated the cave in was observed at Km 55+480 during routine route patrolling in the early hours of first July 2026. After the affected stretch was detected the project team initiated restoration works without delay and prioritised repair to restore safe and uninterrupted traffic movement. The agency said the location was repaired on priority and that interim measures were put in place while permanent works remain pending. As a temporary step the authority commenced construction of a parallel drain of approximately one point five km and is redesigning the drainage gradient to ensure safe disposal of rainwater until the permanent system can be commissioned. The site has been placed under continuous monitoring and additional resources have been deployed to manage the situation and maintain traffic flow. The office explained that the balancing culvert designed to convey rainwater across the carriageway could not be commissioned because local residents have been using the culvert opening as a vehicular crossing and resisted commissioning. It also noted that permanent slope protection and chute drain works remain pending owing to an ongoing land related dispute which has prevented execution of the approved drainage infrastructure. The authority indicated these constraints contributed to the localised stagnation that affected the carriageway. The statement said the agency remains committed to maintaining highway safety through timely maintenance and proactive asset management and will keep the location under observation until permanent works can be completed. It added that necessary personnel and equipment have been mobilised to ensure safe and smooth traffic movement and that any further remedial action will be taken in coordination with relevant stakeholders.

Related Stories

Gold Stories

Next Story
Real Estate

LML Realty Sells Out Jhirka Valley Industrial Park in Haryana

LML Realty, the real estate arm of LML Group, recently announced the complete sell-out of its Jhirka Valley Industrial Park in Haryana, with over 1.17 million sq ft of industrial space acquired by more than 50 companies. With utilities and internal infrastructure in place, the company has commenced plot handovers, enabling buyers to begin construction and establish their operations.The industrial park has attracted companies across diverse sectors, including chemicals, metals and alloys, textiles, electrical equipment, energy, logistics, construction, polymers and engineering. Key buyers inclu..

Next Story
Real Estate

WSB Real Estate Partners Exits Six Housing Investments

WSB Real Estate Partners recently announced the successful exit of six residential investments across Bengaluru, Mumbai Metropolitan Region (MMR) and National Capital Region (NCR), delivering an average internal rate of return (IRR) of 19–21 per cent and an overall investment return of 1.4 times.The real estate-focused investment firm invested approximately Rs 7 billion across six mid-affordable housing projects over the past four years. All six investments were fully repaid between April and November 2026, several months ahead of their original investment tenures.WSB collaborated with sever..

Next Story
Infrastructure Transport

Aluminium Industry Seeks Policy Support for Rs 4 Trillion Investment

The Aluminium Association of India (AAI) has recently urged the government to introduce supportive policy measures to safeguard the sector’s proposed Rs 4 trillion investment pipeline. The association highlighted the need for a predictable policy framework to strengthen domestic manufacturing, expand production capacity and reduce import dependence.AAI submitted its recommendations for the Union Budget 2027-28 to the Ministries of Finance, Commerce and Industry, and Mines, along with the Department for Promotion of Industry and Internal Trade (DPIIT).India’s aluminium demand is projected t..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code